Returnable & Non returnable material issue

Dear Guru,
Can any one explain about Returnable & Non returnable material. How its integrating with Gate entry pass. We need full cycle of that.
thanks
babu

For RGP & NRGP follow the following steps
Creation of RGP with reference to Purchase Order with item category u2018Lu2019.
Step 1:- Create a PO with item category u2018Lu2019 assigns the same material as component at
Material tab.
Step 2:- Issue the material to the vendor with movement type 541 with reference to PO
by using T- code MB1B
Step 3:- Take the print out by using T-code MB90.
Step 4:- Receive the material from vendor to our stock by using movement type 101
Please Note: -
For both the above mention process you have to create the material with Material type UNBW - Non valuated material.
For the second process purchasing view is mandatory along with basic data and accounting view
1 .Create Material with mat type UNBW
Select the following views from material master
u2022 Basic data 1
u2022 Basic data 2
u2022 Purchasing
u2022 General Plant data /Storage 1
u2022 General Plant data /Storage 2
u2022 Accounting 1
u2022 Accounting 2
2. Upload the Material by using MB1C at 0 (zero) price
Use Movement type 561
Enter 0 (zero) price as Loc. Curr.amnt
Save the doc
3. Create Purchase order by using movement type ME21n
Use document type RGP u2013 Returnable Gate pass
Enter all the mandatory fields
Please use the field Requisitioner as Indenter and Tracking No. as Approver
Note: Please check the box of u2018Free Goodsu2019
Enter the same material as component at item level under material tab
And save the document
4.
Issue the good to vendor by using T- Code MB11 with 541 mvt
Create the Material document with reference to PO
Note: - No accounting document will be generated
To check the accounting doc use T- code MB03
5. Good Receive from vendor
Create Material document with reference to PO
Use T- code MB01 with 101 mvt

Similar Messages

  • Returnable & non returnable gate pass

    Hello SAP Experts,
    There is the requirement for the procedure & configuration of returnable & non returnable gate pass for any material going out for repair or for refillment in our company.Also tracking its billing documents which can include service + replacement of any spares.With print out of the document.
    Service Management is not configured in our company.
    Thanks & Regards,
    Anisha

    hi
    >1. im not able to get the print out in MB90
    Check following if useful to u
    1. Maintain the Printer Name in SPRO->Malt Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Printer Setting
    2. Ensure that in SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Item Print Indicator, 1 stands for Matl Doc print out
    3. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Print Version, maintain Print Version 2
    4. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Maintain Print Indicator for GI/Transfer Posting Documents
    5. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Output Determination->Maintain Output Types, for the Output types WE01, WE02 and WE03, ensure the foll:
    a. Default Values: Dispatch Time is 3 or 4 as per reqmt. and Tr medium is 1
    b. Print Parameter is 7
    6. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Output Determination->Printer Det->Pr Det by Pl/StoLoc, maintain the Output device for all your Plants
    7. Go to MN21, for Tr Type WE, Print Version 3, maintain Print Item as 1.
    Now the settings are ready for Printing Material doc
    8. While doing MIGO, ensure that in General Tab, you get "3 Collective Slip" beside the Print Indicator and you tick mark the field.
    9. Now depending on the setting in 5a, the Matl doc is printed. If it is 3, you have to print it using MB90. If it is 4, it is printed immediately.
    >2.for the m/c sent for repair, if they found some damaged part & replacing it, then how to capture its bill part.
    this part will come in ur process part
    if ur using ur own part then agin u have to issue it to the vendor
    or if its been used by the vendor then u have to pay charges manually
    regards
    kunal

  • Non- Returnable gate pass issue

    Dear All
    Kindly explain the process for sending an item outside the company on NRGP/RGP/Invoice for which item code is not available in SAP e.g., a machine part which comes out a machine; or a door which comes out of buiding.
    Rgds
    Srini

    hi
    SAP doesn't provide any option for creating Gate Pass (Returnable & Non-Returnable) in standard.
    Returnable Gate Pass: -
    1. MM01 - Create Material Master for every Spare Part / Machinery to be sent to Vendor for Repair as Non-Valuated (Material Type "UNBW") (Do not extend Accounting and Costing views since you don't require postings of Stock value and consumption values, you only want to track the Service/Repair Charges)
    2. MIGO - Goods Receipt > Others (Receive the quantities of these materials using Movement Type 501 / 511)
    3. ME21N - Create Subcontracting PO (Here Main Material and Component will be same material)
    4. MB1B - Transfer Posting w.r.t. Subcon PO (Mvmt Type - 541, Spare Part stock will get posted to Vendor Stock)
    5. MB90 - Take Print out of this Material Doc as Returnable Gate Pass (U need to configure Message Determination of Inventory Mgmt)
    6. MIGO - GR against Subcon PO (101 - Receive Spare Part, 543 O - Consumption of Spare Part form Vendor Stock)
    7. MIRO - LIV for Service Charges w.r.t. Subcon PO
    Non-Returnable Gate Pass: -
    1. MIGO - Goods Receipt > Others (Receive the quantities of these materials using Movement Type 501 / 511)
    2. MIGO - Goods Issue > Others (Issue the quantities of these materials using Movement Type 501 / 511)
    3. MB90 - Take Print out of this Material Doc as Non-Returnable Gate Pass (U need to configure Message Determination of Inventory Mgmt)
    Note: - If Client is not satisfied with this then you need to go for development of Gate Pass System.
    please check transaction code LECI
    Related configuration
    SPRO --> Logistics Execution --> Shipping --> Basic Shipping Functions --> Registration of Visitors and Means of Transport
    try making a zprogramme and z transaction
    regards
    kunal

  • Need to demo to issue naterials on returable and non returnable basis,with

    Dear SAp Experts,
    please advise me that we need to demo to issue naterials on returable and non returnable basis,with refernce of service po and without PO ref in full cycle.
    Thanks
    Mohit

    Hi,
    Please check below link for the solution. Thanking you.
    Returnable & Non returnable material issue

  • Non Returnable gate pass

    Hi Experts,
    Is there any mtype for NRGP or we have to configure it?
    If to configure- How?
    Plz give some details for the above?
    Regards
    Pratap

    Hi,
    There is no standard transaction for this.
    You can customize a transaction for your requirement with the help of Abapers.
    In our company, we too have customized it. We have created a transaction for Out Gate Pass. In that, we have given an option of 'Returnable' & 'Non-Returnable'.
    If its Non-Returnable, the corresponding option is to be selected & then a series of releases like HOD Release, Excise Release if applicable, Security exit, etc.
    Once security exit is done, the OGP is closed & the material cannot be returned back against the same OGP document.
    If its Returnable, after security exit, another release is done by the security person to accept the material when it comes back against same OGP document & the OGP is closed after that.
    Reward if useful.

  • Non valuated material consumption in projects

    Hi,
    How to track the non valuated material issued for consumption against network that is not planned in the project? I would require reversing the consumption based on material the contractor returns after actual consumption at the site. My default material valuation is valuated project stock. 
    The purpose is to track the non valuated material consumption project wise.

    Thanks Ahmed,
    Our business process starts from receiving order from customer to deliver a set of material and related work.   We are procuring material as a valuated project stock. As and when the material received partially at site, immediately a partial bill is raised to customer for material received value. Itemized billing is required each time to deal the taxes.  (Suggest a strategy to be followed at this stage). 
    The same material is to be issued further in to project for consumption, contractor wise. (How to identify the contractors in the project) So far we are identifying them thru network. Each network represents a specific contractor.  At the end of the job, the contractor returns the left out material after actual consumption.
    Based on the joint measurement, we raise a service bill to customer for services/work done partially at the site.

  • Development of Form for Returnable and Non-returnable material Gate pass

    Dear Experts,
    I am working with an Indian client impementing SAP PM. I need help in developing a form for Returnable and Non Returnable Gatepass. Requirements are below;
    RGP/NRGP should be made for all materials going out of the factory, irrespective of it being coded or not
    It should be plant specific
    It should have reference to material movement document for tracking purpose
    It should have details of vendor, transport company, vehicle number, permits if required, etc
    A Z report should give details of all RGP/NRGP based on material document number and date
    Please guide me based on your experience.
    Thanks,
    Boby

    Boby,
    This can be met. But before developing this, have you implemented the refurbishment process of PM module? This will really help in tracking the equipment and also for the development of RGP/NRGP.
    First you have to create a form for the gate pass  and have to create an enhancement in MIGO for triggering the RGP/NRGP, else you can also create a separate Z transaction code for printing the Gate pass. You will get all the fields like vendor, material, QTY, movement type from the MIGO GI document. 
    For the gate pass the MIGO document will be the reference all the times, you can also develop a Z report for the records for the gate pass.
    Regards,
    Praveen

  • Returning material issue

    Hi,
    I have configured standar process for material issues with services rule also, but I need to know the standar process
    in order to returning material (issue by mistake for example).
    There is an indicator in report NMCOL where it suppose used to bring canceled consumptions, but where do we
    cancel consumptions? (standar only please).
    Best regards.

    Hello Milasanz,
    To be able to reverse/cancel a material consumption in IS-H, an appropriate good issue must be reversed/canceled. To cancel a good issue you must use, for example, the following MM t-code: MBST - Cancel/Reverse. It is the logic, BUT actually once you cancel a good issue, a system still issues an error message when you try to cancel a material consumption (it is wrong behavior of SAP). We've written to SAP about the mistake.
    To cancel a material consumption, you must use t-code NMMC1.
    Regards,
    Alexander.

  • Returning non stock items from a return sales order

    Hello Everyone:
    I have a return sales order that I am receivi9ng an error meesage on for only two of the line items...
    The Error Message is "update Control of movement type is incorrect (entry 651 X__L)...the other items on the sales order that are being returned are not having this issue only these two non stock items.
    i looked in OMJJ and see my movement type  and everything....I am making the assumption that this is due to the material type being non stock...they do not have a MRP view either....the VOV5 also shows the item category for the non stock item with DN...what am I missing...please help...thanks in advancve...

    Thanks for you replies...However I would not want a stock transport order receipt for this which is what the "X" would be...this is a customer return from a sales order...again this works for stock material that is being returned by the customer...it is not working for a non stock material only.  That is my issue..it is only erroring out on the non stock item category only....I am MM and have stepped into a position that was previiously handled by another...I have not ran into this error before so help would be appreciated.....Thanks in advance...

  • How does the Apple Headphones with Remote Replacement Program non-return fee work?

    I have a pair of Apple In-Ear Headphones with Remote and Mic that I purchased a year ago. According to the "Apple Headphones with Remote Replacement Program", http://www.apple.com/support/headphones/replacementprogram/, these headphones are also covered in the program. Currently, there are some issues with my headphone's remote, as it is extremely unresponsive. I don't know how Apple determines the headphone's purchase date, but their online service request page accepts my iPhone's serial number. Is there any way that i could ensure that Apple's willing to replace the headphones for free (E.g. mailing my current ones in first) because the non-return fee is basically its retail price. I do not live in the US so I can't go and exchange at an Apple Retail Store. Thanks in advance.

    I would just bring them into your local Apple Store/Genius Bar and ask.
    B-rock

  • Vendor return via delivery, material sales view needed?

    Hi,
    We wish to retur material to vendor via Delivery process Return PO --> Delivery -->  Goods issue
    We ticketed 'Return to Vendor' checkbox, we created ship-to customer and saved Vendor
    now my question is Do we need create material master sales view??
    Ideally since thse will be purchase materials will not have sales view
    I didnt check, can some one please through light here

    now my question is Do we need create material master sales view??
    Yes,you need to extend material master(using MM01)
    for sales view i.e,sales orgn1,sales orgn2,sales:general plant data.

  • Non Returned Receiver Fee

    Dear AT&T Customer Service, About a month and a half ago (circa early June), one of my receivers stopped functioning properly. I called tech support. Tech support remotely diagnosed the receiver and found the unit needed replaced. They told me a new unit would be shipped. A few days later I received and installed the new receiver. At the time, I found it odd that there were no return instructions or prepaid shipping label included in the box the new receiver came in. I surmised from the lack of instruction that the defective receiver did not have to be returned, but I put it into storage just in case. Yesterday I accessed my current bill and found a $150 "Non Returned Receiver Fee" on it. I called customer support today and spoke with 2 representatives (yes, I actually asked for a second representative because I couldn't believe what I was hearing).  Both told me there were no return instructions or shipping label provided for the return of the defective receiver; that I needed to call AT&T for the correct procedure to return the old receiver. I was told this is standard AT&T procedure. Eventually I was given return instructions and told the $150 would be credited to my account within 2-3 billing cycles after receipt of the return. What if I didn't have the means to pay the $150 on my current bill? Does AT&T charge me late charges if I pay the bill short the $150? Does the aforementioned procedure sound reasonable to you? No instructions or label and the customer only finds out about it after he/she is charged? As a business professional, this seems like a very devious business practice to me. As a customer, it is outright, and blatant poor service. I look forward to hearing your thoughts on this matter. Thank you.         

    If you wish to address Customer Service and you wish a reply, then you should send them a Private Message, including your Name, Billing Account Number, and preferred contact information:
    Please click this Customer Service link to send a Private Message (PM) to the AT&T customer service team to help you resolve your issues. You can expect a reply via return PM (the blue envelope   in the upper right hand corner of this site, next to your avatar and name) in a business day or three.

  • Return of semifinished material to vendor

    hi gurus,
    i have a peculiar situation in one of our client place. the scenario is like this:
    raw material is received at stores and issued for production. here they have got some 8 steps to get the finished product.
    say after 2 or 3 steps (ie) the semifinished material at this stage has to be returned to the vendor.
    how can this be achieved.
    thanks in advance.

    If consumption in bom is in equal ratio (1:1) then adopt below procedure,
    Bring semi finished material stock to quality inspection,In QA32 record usage decison,In inspection stock tab
    enter stock of material you want to return "To new material"(ie. Raw material),enter storage location(meant for return).
    Now stock will come back to raw material.
    or
    Reverse production confirmations done already,bring stock to raw material
    Then do vendor return using return delivery in migo,reverse excise using J1IS if invoice not done for GR material.
    or
    Other wise
    Create return purchase order(with return tick),do migo(161 mvmt),reverse excise using J1IS,post credit memo(MIRO).
    Edited by: Jeyakanthan A on Jul 14, 2010 4:49 PM

  • Error saving map. Stored procedure returned non-zero result. Check if source and target schemas are present.

    I am using VS 2012 and BizTalk 2013 and attempting to deploy an application to BizTalk when I get these errors:
    Error 47
    at Microsoft.BizTalk.Deployment.Assembly.BtsMap.Save()
       at Microsoft.BizTalk.Deployment.Assembly.BtsArtifactCollection.Save()
       at Microsoft.BizTalk.Deployment.Assembly.BtsAssembly.Save(String applicationName)
       at Microsoft.BizTalk.Deployment.BizTalkAssembly.PrivateDeploy(String server, String database, String assemblyPathname, String applicationName)
       at Microsoft.BizTalk.Deployment.BizTalkAssembly.Deploy(Boolean redeploy, String server, String database, String assemblyPathname, String group, String applicationName, ApplicationLog log)
    0 0
    Error 49
    Failed to add resource(s). Change requests failed for some resources. BizTalkAssemblyResourceManager failed to complete end type change request. Failed to deploy map "XXX.BTS2013.XXX.Maps.map_XXXX_R01_InsLabProc".
    Error saving map. Stored procedure returned non-zero result. Check if source and target schemas are present. Error saving map. Stored procedure returned non-zero result. Check if source and target schemas are present.
    0 0
    Error 46
    Failed to deploy map "XXX.BTS2013.XXX.Maps.map_XXXX_R01_InsLabProc".
    Error saving map. Stored procedure returned non-zero result. Check if source and target schemas are present.
    0 0
    I also tried to Import a MSI file from our test environment to see if that would work...got the same errors.  After spending hours (not kidding) looking for an answer, all I could find is that a hotfix would work.  So, I got the hotfix from Microsoft
    Support and applied it then rebooted.  Still getting the same errors.  I'm absolutely at a stand still.  Interesting that I got this application to deploy yesterday and then the next time I deployed it I started getting these errors.  I'm
    ready to pull my hair out!
    Is there an answer for this out there somewhere?  Any help would be appreciated.
    Thanks,
    Dave

    Hi Dave,
    Which hotfix have you applied? I don't think a hotfix of this issue is available for BizTalk 2013 yet. You should create a
    support ticket with Microsoft to get a solution.
    If this answers your question please mark as answer. If this post is helpful, please vote as helpful by clicking the upward arrow mark next to my reply.

  • Return of raw material on production order

    Dear Experts
        Is there is any way to return raw material issued in production order back after issuing it

    Hi,
    Here is the solution for you( Hopefully)..
    If you proceed in 262 movement it ll reverse all the materials against the order.
    For that ,You have to reverse " to reservation". befor that change the production order BOm with the actual consumed QTY.
    In production order the reservation number will be 12356.
    For that particular material you ll have the reservation number be 12356-12( this you can get from double clicking the line item number of the material).
    In MB1A , Give the reservation number (both the nubers 12356 and 12) And find it solved..
    hope this clarifies..
    karthick
    Edited by: karthick PP on Mar 23, 2009 7:58 AM