Selection of usage decision based on % of rejection done thorugh Insp Lot

My business scenario is as follows:-
I have created new usage decision codes as mentioned below through QS41and assigned the same to code group RI-UD and catalog 03. 
I3     INITIAL REJECTION >75% to <=100 % (1) 
I4     INITIAL REJECTION >50% to <=75% (40)
I5     INITIAL REJECTION >25% to <=50% (60)
I6     INITIAL REJECTION <=25% (80)
and quality score maintained the same through QS51
Code Group     Code     Shot Text for a code                                               Code Valuation         Quality Score
RI-UD     I3     INITIAL REJECTION >75% to <=100 % (1)     R Rejected (not OK)     1
RI-UD     I4     INITIAL REJECTION >50% to <=75% (40)     R Rejected (not OK)     40
RI-UD     I5     INITIAL REJECTION >25% to <=50% (60)     R Rejected (not OK)     60
RI-UD     I6     INITIAL REJECTION <=25% (80)                          R Rejected (not OK)     80
I need to automate the selection of usage decision code to be done by system based on the accepted/rejected quantity entered.
How to go about it.  Can anybody on this please?
Thanks in advance.
Ravi

Anything can be done SAP!   But what you want would be all custom.  There is no SAP functionality that would do that for you.  I'd start with the auto UD program first.  Have the programmers modify the selection parameters to select the list of lots.  Than process those lots with the logic you want o use and change the UD accordingly.  I'd make sure I could run the program manually as well.  Similar to some of the other UD workload programs.
FF

Similar Messages

  • Work flow for Rejections in Quality- Usage decision

    Dear all
    We are in the process of activating work flow for Quality Inspection, During Usage decision there may be rejections for which we need to trigger a mail to the Internal department , stating the Remarks, description, rejected quantity etc ,
    If any one has come across the same scenario kindly help us so as to implement the same in our organization.
    Regards
    Rahul Bhat

    Hi,
    You can do any of the following according to you Requirement.
    1) Below the Rejection Branch using the Send mail you can send the mail to Respective person.
    2) Other wise using the Function Module you can send the mail, refer this l[ink|https://wiki.sdn.sap.com/wiki/x/nYKdAw ].
    3) Else place this Std. Task TS20000139 and provide the necessary binding below the Rejection branch a popup will open and the user can enter the comments and it will go to the Person whom you want.
    Try any of this according to you requirement.
    Regards,
    Surjith Kumar

  • QA16.. Mass Reject Usage Decision

    Hi
    Is it possible to do a Mass Reject usage decision?
    With QA16 you can mass accept lots .. but do you have to do rejections on an individual basis manually?
    Thanks
    Lee

    Hi Ram,
    Thanks for the fast reply.. can I just clarify your second comment "For automatic UD the pre requistes are no char.reject, no q-note or defect records created. So, automatic UD for rejections not possible."
    I am not sure I follow this... we will create potentially a 200 hundred inspection lots per day but do not plan to input inspection results so there will be no basis for automatic usage decision I guess.
    We are hoping for each production receipt to go into QI with an Inspection Lot then at a later point for a Usage Decision to be made to accept or reject.
    If there is a problem during the shift then tens or hundreds of lots could be affected. Can you suggest a method I could investigate to reject all of these without manually going to each?
    Thanks
    Lee

  • QM_Follow up action in usage decision

    Dear QM Experts,
    1.     We can record the defects in inspection lot (01 origin) which creates quality notification in background under F2 type.
    2.     If the defects are recorded usage decision is given as Rejected.
    Requirement is auto email should be sent to predefined email addresses briefing defects and number of defects. This has to be done only for those lots whose UD have been given as Rejected. Question is which follow up action and which function module to be used for this?
    Best Regards,
    Anand Rao

    hi
    kindly check whether the following FM can be used
    QFOA_MAIL_REJECTED_RESULTS-Follow-Up Action Module: Send Mail for Rejected Characteristics
    QFOA_MAIL_SENDING-Send Info MAIL After Usage Decision (Mail Contains UD Data)
    QFOA_MAIL_SENDING_STANDARD-Send a Short Info MAIL After Usage Decision
    you have to assign these follow up actions with FM to the rejected UD code
    regards
    thyagarajan

  • Automatic Credit/Debit Memo linked to Usage Decision Code

    Dear SAP Masters,
    Can any one help me in setting up a process in system for automatic creation of Credit/Debit memo on selection of usage decision code in notification?
    Points will be awarded to any useful reply.
    Thanks and regards

    Dear Sir
    What is you business can you explain it in detailed?
    Because there is facility available to create (SDMR) Service Debit Memo Request  or SCMR(Service credit memo request) against the order & not notification.
    if you tell me ur business i can put more focus on it .
    Regards

  • Control the Posting of Quantity through Usage Decision

    Hi Qm Gurus,
       How will i control the posting of quantities from quality inspection to any types of stock? For instance, If the Usage Decision Code made is Rejected, how will the user be controlled or prompted to post quantities only to blocked stock and not to unrestricted or any types; without viewing the Manager's Usage Decision "Rejected".This is very crucial to pharmaindustries because normally, the manager is the one who made the usage decision, and the rank and file will be assigned to post the quantities. how shall this be resolved. Hope anybody can help me. if possible teach me on how to configure this, and there tcodes to be used by different users. I think Qa11 by manager.
    Regards,
    Matildo, edsel
    Qm Consultant

    Dear Murugsan,
    Can i control the posting of qty from UD in storage location level e.g. if a user give the UD from Q/INSP. location (1701) & by mistake he does not change the location TO (2500 BSR) then system put the qty in 1701(unrestricted) my requirement is that system by default pick the 2500 location if UD is given for acceptance as OK.I have seen your reply to another similar type of requirement but does not find any storage location option in QS51.
    R SEHGAL

  • Quality Management - Usage Decision error

    Hi all,
    My scenerio is - There is a material ABC which is procured from the supplier. The Quality of the material is 'below standards'. However, material ABC, in Tcode QA11 Usage decision was done as ACC1 (accepted). Since the material ABC is not meeting quality standards, Usage decision is changed to RET1 (Bad Raw Material - Return) using Tcode QA12.
    Now the problem is that when I enter QA11, the system does not allow me to enter as a message appears 'Detailed Info- Usage decision made is disallowed' is showing.
    Please provide me a solution as the material is lying in the unrestricted stock and it has to be returned to the supplier. Also please consider costing implications.
    Thanks in advance

    Cancel the inspection lot in QM using the function to change the usage decision.
    Logistics - Quality management - Quality inspection - Inspection lot - Usage decision - Change with History - Usage decisions - Functions - Cancel lot 
    Reward if cleared and close the thread.

  • What will effect the usage decision on vendor, Stock, purchasing,production

    Hello Expert,
    what will effect the usage decision on vendor, Stock, purchasing,production
    Thanks regards,
    Ram Rathode
    Moderator: Please, avoid asking basic questions

    Hi,
    Usage Decision completes the inspection and  life of Inspection lot will be over - when you take UD. Thus: by UD:
    ·        A quality score is determined for the inspection lot
    ·        The quality level (inspection stages for the next inspection lot) is updated
    ·        The quality management information system is updated with statistical data
    ·        Automatic follow-up actions are triggered
    Affect of Usage Decision on:
    Vendor: rating would come down.
    Stock: no affect (unless you make it mandatory for "Accept" UD to be used for stock posting).
    Purchasing: if the stock is returned to vendor, Purchase order would still be active. Also, Vendor rating would be affected
    Production: UD has no affect on production except when it is linked to stock posting.
    Outgoing certificates: In Certificate profile, if "accepted" lots are to be considered for Quality Certificate creation, then it may cause problem.
    Regards,
    KrishnaM
    Edited by: Krishna. Madduri on Jun 13, 2011 3:56 PM

  • Automatic storage location selection while doing usage decision

    hi gurus,
    My client wants to do automatic determination of storage location depending upon usage decision.
    i.e. if usage decision is reject than gr to be done at rejection storage location. if usage decision is accepted than gr to be done at respective storage location.
    The storage location can be changed manually but they require automatic determination of storage location.
    Regards,
    Deven

    hi, deven,
    go to qs51, select catalog 3 enter plant
    select selected set that u used for the plant that u select
    in posting proposal ud tab u select inventory posting automatically for return delivery , unrestricted stock etc
    u just r & d with in that t code
    if u get solution please share with me too
    regards,
    umesh

  • QA40 making usage decision for 03 lots with rejected MIC also

    Hi Friends ,
    QA40 is making Usage decision for 03 type lots having defects also and also for the lost having rejected MICs . can anybody explain why its so because SAP help has mentioned that for automatic UD there should be no rejected MIC .
    Regards

    What you are thinking about is QA10, not QA40.
    QA40's criteria for making the UD is based upon the order status.  I.e. the three radio buttons in the screen, orders completed, technically complete and confirmed.
    The idea is once one of these statuses is reached, you wouldn't have any more testing.  Also, it is not unusual to have out of spec results during in-process testing.  In many industries that would be the norm, not the exception as often times a step in the process has a test repeatedly perform until a certain result is achieved.  % water or % solids for instance.
    03 lots also do not control stock.  So it's not as critical that tests be in spec at this point to perform the UD.
    Craig

  • Usage decision rejection

    Hi Gurus,
    What will be the procedure after rejecting the usage decision. Stock from quality moves from quality to Blocked. So i tried moving the stock from blocked to quality through the inventory movement transaction, for which it giving an error "Managed by QM view".
    So what is the transaction should i use to get the stock back to quality.
    What would i recommend to my User if he asked what should i do if the inspection lot is rejected.
    Please suggest.
    Thanks in advance,
    Quantum.

    Hi
    What will be the procedure after rejecting the usage decision. Stock from quality moves from quality to Blocked. So i tried moving the stock from blocked to quality through the inventory movement transaction, for which it giving an error "Managed by QM view".
    A)When a lot is rejected means you have done RD :122 Mvt.
    1.You can do 123 by activating 08 inspection type.
    2.Go to MB1B and do 123 Mvt type
    3.08 inspection type lot will be generated and Material will appear in quality can be seen thro' QA32.
    4.Then UD can be taken.
    B)When you move it to Block stock:
    1. Then You can activate 08 inspection type.
    2.Go to MB1B and do 349 Mvt type.
    3.08 inspection type lot will be generated and Material will appear in quality can be seen thro' QA32.
    4.Then UD can be taken.
    I hope this will help you
    Regards
    Sujit

  • Usage decision defaults always rejection

    Hello experts
    We have issues with the samples and the usage decision . Inspection lot qty - 1000 , Samples - 40 .
    We have three chars in the samples. the results are recorded as summation recording. . We are doing entry in QA32 - Results recording  like INSPECTED 40 and results 40,while entering  results 40 ,automatically rejection tick mark was updated master data cause the problem ?
    Any suggestion please
    Thanks
    JJ

    Dear JJ
    please let me  know was the summation results outside the specification limitation maintain in the inspection plan.
    What is the mic that you are using and what is the sampling type and valuation you are using
    Regards
    gajesh

  • Rejection in Usage Decision of an inspection Lot

    Dear Masters,
    I want to know that is there any standard method to trigger the notification for rejection of an inspection lot?
    Please do explain. Thanks in advance.
    Chin2

    Dear Pushpa,
    Once again thanks for your reply. In the case mentioned above I can only define one notification type, what if I have more than one notification type to be used on rejection in usage decision? I will explain my scenario as below:
    I have 3 different quality notification types i.e, 1) Engineering Calibration notification (For Engineering Equipments)
                                                                              2) Quality Calibration Notification (For Quality Equipments)
                                                                              3) Fleet & Trade Calibration Notification (For Fleet & Trade Equipments)
    Now, I have 3 different types of orders from which the inspection lot will be created and for those 3 different types of orders I want 3 different types of notifications to be generated on rejection of the inspection lot.
    Please do guide if there is any standard method to achieve this
    Thanks once again.
    Chin2

  • Return process for the PO which has done the usage decision with QM

    Hi Guru,
    We are running below process right now, and stop there, don't know how to return to vendor:
    PO for external vendor -> Goods purchased physically arrive -> Create a inbound delivery for this PO -> Post the GR with the inbound delivery created -> QA team performed the usage decision and rejected.
    At this moment, how can we reverse the good receipt? We canu2019t use VL09 to reverse the inbound delivery, and we can not use MBST to reverse the material doucment which created during Post good receipt.
    What's the correct process to return it to vendor?
    Thanks,

    Hi Rick,
    Can use t.code MIGO and select return delivery for material document or delivery note.
    Then select the respective document, it will display the details, now you can select the material which you want return and unselect the materials which you dont want to return and the quantities accordingly.
    Save the document.
    This will use movement type 122.
    Regards
    vk

  • Material Disposition After Usage Decision

    Hi Gurus,
    Im working on a scenario werein I need to change the Defect recording after I need to change the disposition of the material. The process is, the lot will be rejected, and will go to a certain Location. In this location, the user will decide whether it can be rework, return to vendor or use as is. User will need to key in in the system.
    At first, I though I can just use of changing the usage decision. But they say they need the disposition per item in the defect code. But once I have done usage decision, Defect cannot be changed.
    Please help to identify other process that I can do.
    Thank you,
    Raymond

    Dear Raymond
    Then in that case the only solution will be to activate notification.Please follow this process
    1) Maintaina default notification type in the inspection type in the config
    2) When defect recording is done automaticaly notification will be created
    3) When UD is given notification also gets closed automaticaly
    4) Go to notification ( in UD screen , select the defect and click on Notification and put the notification back in process (menu button > function> Put back in process
    5) Here you can edit the defect or add defect and automaticaly gets assigned to the inspection lot
    Please check and revert back
    Regards
    GN
    Edited by: Gajesh Nagesh on Feb 3, 2010 6:14 PM

Maybe you are looking for