Sheduling by Milestone Operations

All, I have a scenario where my customer would like to calculate the lead time to produce materrial based soley on the length of time which is entered on Milestone operations. Currently durations are maintained at each operation and we do not want to remove this as it is important for costing. A simple example is below;
Step

Hi Gordon,
What I have understood from your requirement is that you wish to use Non - Milestone operation only for costing and not for scheduling but the scheduling for these operation must be done in milestone operation.
I suggest you follow the below steps.
1. Remove the NON Milestone Operations from scheduling in control key.
2. In Mile stone Work center add another standard value key as wait time or previous operation time. (I assume u will have space to add another standard value key.)
3. Please assign the control key meant for scheduling in this work center.
4. Please note the activity type assigned in this standard value key must be dummy and unit cost must be negligible to avoid costing duplication. you can contact finance or costing team in this possibility.
5. In routing, you can use the new assigned standard value key to assign the total time taken by operation before this milestone operation. Hence the scheduling could be done in mile staone operation and costing will not be duplicated.
OR
Using Queue time means you will have to maintina std. queue time and mini. Queue time.
You can try using wait time in routing as the wait time can not be reduced.
Let me know in case of any issue.

Similar Messages

  • Manufacturing Lead time, milestone operation wise

    Good Evening to All !
    I have a scenario. I am explaining this scenario through 1 example.
    We have a material 'X'. Inhouse production time for this material is 6 days, which is maintained in MRP2 view.
    Now in Routing of this material 'X' there are total 10 operations starts from 1 to 10. Operation No. '4' & Operation No. '10' are milestone operation. The workcenter for both milestone operations are different. Now in house production time which I maintained in material master is total lead time for material 'X'.
    The requirement is:  Workcenter of Operation "4 "wants to know on daily basis that what quantity should be delivered from their workcenter.
    Now my question is that can I maintain this lead time(6 days) in 2 parts as:
    Till operation "4" my lead time is 5 days &
    From operation "5" to Operation 10 lead time is 1 day.
    Please suggest all possible solutions.
    Can APO help in this scenario.
    Thanks in Advance.

    If you run MRP with "lead time scheduling" (instead of "basic dates"), it will schedule the order by the routing, and let you know the planned workload for each WC in advance.

  • Scheduling by Milestone Operations

    All, I have a scenario where my customer would like to calculate the lead time to produce material based soley on the length of time which is entered on Milestone operations for a routing. Currently durations are maintained at each operation and we do not want to remove this as it is important for costing. However they want to have the queue times at the end of a group of operations instead of on each individual. A simple example is below;
    Step Duration Milestone lead time
    10 1 hr
    20 3 hr
    30 2 hr 8 hr
    40 2 hr
    50 2 hr 8 hr
    In this example the customer would want this order to take a total of 16 hours. They have a good idea of how long it takes the product to get from Milestone to Milestone. They want to capture all of the queue time in the milestone steps. Also they may have another order which has 7 steps but the overall leadtime the wish to capture is still 16 hours. This is a way for them to set general parameters without having to do time studies for every routing

    Hi Gordon,
    What I have understood from your requirement is that you wish to use Non - Milestone operation only for costing and not for scheduling but the scheduling for these operation must be done in milestone operation.
    I suggest you follow the below steps.
    1. Remove the NON Milestone Operations from scheduling in control key.
    2. In Mile stone Work center add another standard value key as wait time or previous operation time. (I assume u will have space to add another standard value key.)
    3. Please assign the control key meant for scheduling in this work center.
    4. Please note the activity type assigned in this standard value key must be dummy and unit cost must be negligible to avoid costing duplication. you can contact finance or costing team in this possibility.
    5. In routing, you can use the new assigned standard value key to assign the total time taken by operation before this milestone operation. Hence the scheduling could be done in mile staone operation and costing will not be duplicated.
    OR
    Using Queue time means you will have to maintina std. queue time and mini. Queue time.
    You can try using wait time in routing as the wait time can not be reduced.
    Let me know in case of any issue.

  • Sheduling  time for operation is not exact

    Hi Friends,
    I am performing backward scheduling  for the production order.
    I have maintained standard values for the 1st operation /  set up time:10 min /   machine exec time : 10 min
    when i am sheduling the 1ST operation for 5 qnty of a an order
    the system proposes a date in CO02  operation overview ,12/12/2007 and strats set up at 7.00.00 hrs and shedules the processing time at 7.10.40 hrs (machining time)and shedules the next operation , ie 2 ND at 8.01.35 HRS.
    whereas it should start the  processing at 7.10.00 hrs and start the shedule the setup of 2ND  operation at 8.00.00 hrs.
    so from where the system takes the floats like 40 second for set up and 55 seconds for processing time? but the work center capacity is booked exactly  as that of the standard values  maintained in routing.
    I have removed the shedule margin key and tried but not able to rectify the time floats coming in sheduling.
    so please suggest how to proceed in this senario?
    Thanks and Regards
    omkar

    Hi   Pradeep,
    sorrry for replying you late.
    i have proceed like this.
    i have three shifts- A               B .           C
    having  durations   8 hrs          8 hrs         6.30 hrs
    breaks                 30 min        30 min      30 min
    version  of cap       10              20           30
                             1 st shift      2nd shift    3 rd shift
    shift seq              1                    2             3
    and in intervals and shifts tab in capacity header of work center  i have declared the versions and here for each version i have  declared
    for version 10- shift seqence - 1  for 7days week -A shift
                     20                       -2       7do         Bshift    
               30                       - 3        7do -         C shift
    there is no deviation in shift seqence, every day we have 3 shiftsA,/B/C one after another .
    Ihave gone for the settings as suggested by you  in OPEB
    STILL NOT GETTING THE RESULT:
    THE DEVIATION IN TIME FOR SET UP &PROCESING  IS ALMOST CONSTANT ie: setup deviation is : 40 sec s and processing  :  3 min 40 sec for each operation and it also shedules in break tine.
    pleae suggest
    Regards
    om

  • Non-Milestone Operations to display in Co11N

    Some operations in my Routing have a control key that says its a milestone operation and some operations with a control key that says Confirmation possible. When I went to CO11N to do confirmations only the Milestone operations are showing up for selection.
    I can manually type a non-milestone operation no and do a confirmation but I was wondering if there is a way to make these Non-milestone operations also appear in the selection.
    Thank you

    Dear,
    In customisation of confirmation parameters (OKP4) for the plant, order type combination you need to activate the check box for +Confirmable operations in the tab page "Operation Indv. entry using intial screen".
    Regards,
    Prasobh

  • Default hrs proposal for non milestone operations should not happen

    Hi,
      I have a sequence of 4 operations among which last operation is milestone and all other three operations are confirmed automatically when 4 th operation is confirmed. But I have removed the default proposal of activity hours in the confirmation parameters of that order type.
      So when I confirm the 4 th operation automatically the first 3 operations are also confirmed with default activity hours as proposed by the system. But for 4 th operation system is not proposing any activity hours based on the configuration setting in confirmation parameters. But if I confirm first 3 operations individually using co11 then hours are not proposed and so there is not activity hours on confirmation.
    My requirement is I donu2019t want any hours to confirm on the first 3 operations as default when I confirm the 4 operation which is milestone. Is there any setting required or any other way it can be avoided?
    Regards
    mohan

    Dear ,
    Reference to your requirement , you go for setting Not relevent for costing in Operation Overview  in case Standard values is schedulling issue .
    Othewise , try the below option in OPK4
    1.In operation individaul entry scree keep -Confirmable operation check box marked
    2.In general valid setting  : in Check : Set Temination when operation sequence are not adeher too .
    3.Create an operation control key where Confirmation not possible option is there .Copy from standard and assing the same in operations whihc u do not want to confirm .
    Would like to know why do u need this kind process where u have operation hrs but u do not want to confirm ? what is the logic of keeping them in roouting  and schedueling through APO ?
    Regards
    JH
    Edited by: Jiaul Haque on May 25, 2010 8:29 PM

  • Reporting point backflush and milestone confirmation

    hello pp experts,
                           if we have the option of milestone confirmation then why do we use reporting point backflush, actually what's the difference between them?

    Dear,
    If u do confirmation without RP it is like order level confirmation co15 in discrt all teh opeation is confirmed at once.Here u canot use operation wise.
    So in REM we use MFBF reporting point back flush like CO11n which carried out on operation basis as milestone  operation is confirm previous also get confirm.
    To see the RP overview after confiramtion at each RP u can use MF26, this will give WIP qty to be conformed at each reporting point.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Milestone Confirmation of Phases

    ello,
    In our design of master recipe, we have two operations 0010 & 0040 each with 2 phases. Milestone control key
    is assigned to the last phase. FS relationship is maintained betweed  the phases. The phases for both
    operations have activities maintained to be confirmed as per standard values in the resource.
    When I am doing milestone confirmation for the last phase using COr6N, clicking on the actual data is not
    giving automatically the activities for the previous phases (assigned to 1st operation) to be confirmed. The
    activity value assigned to the last operation is available for confirming.
    However on confirmation the previous phases are getting confirmed.
    is it that for phases with different operations, the milestone confirmation does not propose the activities
    of previous phases to be confirmed?

    Dear Debdutta1
    you will not be able to see  activities for the previous phases if you post the milestone. In case of milestone the system post the planned activities based on the quantity. See
    http://help.sap.com/erp2005_ehp_05/helpdata/en/b1/c04d69439a11d189410000e829fbbd/frameset.htm
    [....] In milestone confirmations, planned activities are always posted on the basis of the confirmed quantity. If you have entered activities manually during a milestone operation, planned activities are also confirmed when the preceding operations are automatically confirmed. The exception to this is the setup times, which are always confirmed fully, independently of the entered quantity [...]
    Hope this helps.
    BR Sabine

  • Movement Type & Milestone conf

    Hi
    For Auto goods receipt which movement type system will use?
    what is the difference between movement types 101 and 131?
    what are the disadvantages of Milestone confirmation?
    Regards,
    Srihari.M

    Hi,
    For Normal/Auto goods receipt system uses the same Movement type depending upon Descrete or REM.
    For Descrete for GR - 101 Mvt. Type
    For REM for GR       - 131 Mvt. Type
    Advantages of Milestone confirmation:
    If you confirm your milestome operation, system will automatically confirms the all the operations till the previous Milestone operation..
    Hope this helps..
    Revert for further discussion.
    Regards,
    Siva

  • Milestone Confirmation for Process Orders

    Hi,
    We are using PPPI and I am trying to perform a milestone confirmation for phase (COR6).  Although it is working without errors, it prompts you for which phase to confirm. 
    In discrete PP, you set up milestones, and when you go to CO11 - confirm operation, the system automatically goes to the details for the first milestone operation.
    Is there any way you can do this with proces orders for COR6, ie automatically go to the detail screen for the milstone phase?
    Regards,
    Fotini Delgado

    Hi
    u can use t; code COR6 : confirmation of process order
    we can enter operation number (same as final one )
    so we can directly confirm last Phase
    or
    We can use
    CORR : for collective confirmation of process order
    or
    CORZ : confirmation : for time event
    please tell me if u have any more question
    Thanks
    Sunil Singh

  • Operation scrap and expected yield variance

    Hello guys,
    I have a question on the operation scrap and the expected yield variance.
    I have a product which has four operations, and on one of the operations (2nd operation) the operation scrap of 10 % is maintained.
    So, I have created a production order for 100 Pcu2019s.
    For the confirmation, I confirm first operation with the total order qty (100Pcs). After the confirmation the expected yield of variance of 10 Pcu2019s is set on the order.
    I just wanted to understand why the expected yield variance is set with planned operation scrap. According to my understanding, the expected yield variance is only set if a scrap value is mentioned in the confirmation.
    I am having a problem because my 4th operation is a milestone operation ( I confirm 2Nd, 3rd and 4th operation at a time.
    I donu2019t use the back flushing option coz I do my GR in MIGO.
    So here is the situation.
    I created and order for 100 Pcu2019s and I confirm the first operation for 100 Pcu2019s
    Second milestone confirmation (2nd, 3rd, 4th ops) for 40 Pcu2019s u2013 GR is done after that.
    Third milestone confirmation (2nd, 3rd, 4th ops) for 40 Pcu2019s u2013 GR is done after that.
    Fourth milestone confirmation (2nd, 3rd, 4th ops) for 15 Pcu2019s but I can only receive 10 Pcu2019s because of the operation scrap and expected yield variance.
    Thanks,
    sashi vardhan

    Dear Shashi,
    Since you have maintained 10% as operation scrap system considers that 10% of your total qty in the opration is scrap material and hence system allows only confirmation of 90 components only.
    This is std SAP behaviour.
    Regards
    Suri

  • Default operation in CO11N

    We currently have 3 operations associated with one material.  In CO11N, when entering a production order number, is it possible to skip operations 0010 and 0020 and go straight to 0030 (our milestone operation)?  This would be so the person confirming production orders does not have to worry about selecting operations.
    To clarify, this is so no operation would need to be selected, only the default 0030 will appear when a PO number is entered (unless another operation is individually selected in the 'Oper./activity' field).  I've searched through OPK0 and I cannot seem to find the configuration I'm looking for.

    Cameron,
    I could be wrong...but try to do the following things:
    -run OPJ8
    -select your Control key which is set for operation 0010 - look at your Routing. goto Details and set '3' in "Confirmations" field
    -do the same for Control key which is set for operation 0020
    -make sure your Control key for operation 0030 is set as '1'
    ('3' means 'confirmation not possible')
    please try in DEV - also try CO11 instead of CO11N (exactly for your situation)
    good luck

  • Material backflush in production order after finished goods GR

    Dear all,
    I once started similiar topic several months ago, but didn't recieved any response. I'm gonna give it another try, so maybe you'll be able to support me after all.
    So, the situation is like this. We have a production order, in which MC team maintained the materials to consume. The problem is, that very often it comes that we have to use same material part, but under 2-3 different partnumbers. E.G.:
    Production order target: 1000 finished goods
    Required materials: Part A 1000 pcs, Part B1 700 pcs, Part B2 300 pcs, Part C 1000 pcs, Part D1 150 pcs, Part D2 450 pcs, Part D3 400 pcs.
    So yes, in case when it is Part B1, B2 and etc. it means that we're using physically the same part, but under different partnumbers. The problem is, that those material are all coming in pieces, not in meters or anything, and we can't allow to have, for example, 0.7 pcs of any of those materials (cause obviously you can't have 0.7 pcs of LCD panels stored in the warehouse).
    It wouldn't be a problem if we could just confirm all operations in production order in 1 batch, but production order is being confirmed partially, every time the pallet with finished goods is being released from production line (we have integrated system, that sends requests to SAP to confirm specific quantity of finished goods in production order). So, as an example, if 1 pallet contains 15 pcs of finished goods, you have 67 confirmations for production order [(66*15)+(1*10)]. And, since all those materials come in PCS, SAP is rounding up consumption if it has decimal, which leads to wrong materials consumption.
    Initially, I had an idea of adding 1 more operation in production order, which was supposed to be a manual use only, after finished goods GR, and MC team supposed to assign those B1\B2 and etc. material to this operation  E.G.:
    Operation 0010 - consume material from work center A
    Operation 0020 - consume material from work center B
    Operation 0030 - finished goods GR (milestone)
    Operation 0040 - consume material from work center C
    My idead was rejected, since I was told that after GR for finished goods is done and you continue consuming materials in production order - it will not be shown in financial reporting (don't know the details, it was quite a straight reject, without much explanation).
    So, question is - is there a way to consume materials after finished goods GR without creating mess in financial reporting, or if not - what other options do I have?
    thank you in advance

    Hi Valentin,
    After GR also you can do goods issue. Till the order status is CLSD (Closed) you can book cost on to the order.
    Two ways to consume materials on order.
    In order component overview maintain the required part number with quantity. GI as can done with reference to order MB1A 261 movement type.
    Directly do GI with MB1A -261 movement type - Input the order number, material number and qty.
    Refer to the below discussion on unplanned GI which was discussed yesterday,
    http://scn.sap.com/message/14850196#14850196
    Thank & Regards,
    Ramagiri

  • Auto confirmation

    hi all,
    I want to confirm automatically a production order. I want to do this with define control key. But when I create define control key for this case, which properties  I must choose for auto define control key? ( TC: OBJ8 )
    Regards,
    Hilal

    Hello Hilal Çakir 
    Pl use SAP Standard Control key "PP03" which is meant for Milestone Operation confirmation , which will confirm all previous operations when you confirm the operation with control key ..
    As this control key have the AUto GR option also activated you can take a copy of the same and Unckeck the AUTO GR option of you dont want the same..
    However AUTO GR can be used with used with the confirmation of final operation , SO my suggestion Pl take a copy of PP03 and use its for all the milestone operations except for final operation.
    PS: as mentioned by other friend .."use of contol key
    PP98"[ , I just want to clarify that in Standard SAP there is no Predefined control key is "PP98 " , i hope its configued for there specific business ..(as I suggested you above ) 
    Standard SAP comes with only 4 control keys for PP , as below
    PP01     Routing/Ref. op. set - internal proc.
    PP02     Routing/Ref. op. set - external proc.
    PP03     Routing - in-house prod. auto. goods rct
    PP04     Routing - in-house prod. with check
    Pl come back if you need further details or close the thread and reward points..
    Best Regards
    Sumit

  • Direct production in collective order network, automatic 261...

    hi all,
    i have a problem in a schenario with collective order network.
    i have order B part of collective order network of order A. and material of order B has special procurement key 52 maintained in it. and colletive order of goods movement is selected in order type setting of order B.
    now the problem is when i confirm the order B, its header material automatically gets issued to order A (as per the settings that is fine.. ).
    but when i canel \ reverse the order A, i can not see 262 for material of order B which was issued automatically....??? why so?
    and if i try to revrse order B,  it stucs in COGI with the error of deficit of sales order quantity (or unrestricted quantity)....
    can somebody tell me how to sollve this? how to get 262 of the header material of order B?
    best regards,
    Maulin
    Edited by: Maulin Munshi on Jun 17, 2009 8:27 AM

    If you're doing the confirmation of parent order (leading order) at header level (meaning you use CO15) then you can only confirm that particular order and not any child order. If you want the child orders to be confirmed also after completely confirming you'd have to change the control key of last operation of routing in leading material as milestone and use CO11 or CO11N and just confirm the last operation, it will automatically confirm all the operations in the leading order and all the sub orders (child orders). I don't think your OPKI setting will solve the issue.
    Production orders that belong to collective orders are generally confirmed like normal production orders. However, you should note the following:
        When you carry out a confirmation at header or suboperation level, you can only confirm the order concerned.
        When you confirm at operation level, you can confirm operations for all orders as long as you work with milestone operations or progress confirmations.
        When there is a confirmation in the collective order, the system sets the status CFCO (release occurred in network) at the header level of the leading order in the collective order.
    If you want to read more than what I mentioned, you go to this link