Standard cost estimation after goods movement when material ledger is activ

Hi!
our client is activated material ledger, for some materials standard cost estimation is done till marking but not released.
goods movements have been posted for those materials.
Now system is not allowing to release the standar price for those material in the current period, as material ledger expects same price for entrie period.
what is the alternative way to update the standard price for those materials ( with out reversing the goods movements).
regs,
ramesh

Hi Ramesh,
When you are using Material Ledger, after goods movemnets for materials, no need to change the standard cost estimate as Actual costing run will take care to derive the PUP price.
If there is no standard cost estimation release for sold materials (e.g.FG), you will get an error message duirng the billing document release to accounting. To aviod this error, if you are using split valuation (valuation types) and mixing ratios (CK91N & CK94), try with the below steps:
Create a new valuation type for the same material
Crate CK11N & CK94,
Run CK11N
Run CK24.
Then release the billing document.
Let me know if you need more details.
Thanks & Regards,
ADI

Similar Messages

  • MM closing period problem when material ledger is activated

    Hi!
    the MM period is opened for period 7,2010, now we want to close that period and open period 10,2010 ( this is sand box system only, so no one used from last 3 months), but when I am executing MMP to close period 8 ( as we have to close periods till 10th period) , system is giving erros saying key duplicate records are not allowed in table "ckmlkev" ( as material ledger is activated), in this table already periods are existed till 9,2010 for all valuation areas.
    Now how to close 7th period in MM ( MMPV)?
    can any one suggest alternative ways?
    regs,
    ramesh b

    Hi,
    As it's your sand box and you don't need to fix the root cause of the error, try to execute MMPV with option "Close period only".
    Regards,
    Szymon

  • Stock price is in negative (when material ledger is activated)

    Hi All
    While reversing the GRN for import PO system is throwing the error message stock price is in negative.
    Please help it's URGENT.
    B. Kandre

    Hi,
    As it's your sand box and you don't need to fix the root cause of the error, try to execute MMPV with option "Close period only".
    Regards,
    Szymon

  • Routing during Standard Cost Estimation

    Dear all,
    We are executing the Standard Costing using t_code CK11N for a finished product,,,for the same we have maintained BOM, but no routing has been created,,
    so, during execution of Standard Costing system is prompting a msg: No routing could be determined for material AUBF0018 (green indicator not an error msg), so if we try save the costing a success msg: "The cost estimate is being save" is being prompted,, but the standard cost did not get updated in material master.
    what would be the cause? Is routing essential prior to standard cost execution,,, as our Client says that without routing also they could excute/update the standard cost earlier,,, why this problem is occuring? is there any thing need to be defined in customization for routing not to consider during standard cost estimation,
    Please help us in this regard,
    thanks
    Kumar

    Dear Urendra,
    1.After executing the costing run with quantity structure in CK11N and saving the datas,it only saves the cost estimate.
    2.Marking and release should be done using CK24.First the same has to be marked and then using the same T Code you have to
    release it,only after this steps it get's updated in the material master.
    3.In your case you have done only CK11N and not CK24.
    4.Moreover the routing get's picked automatically by the costing variant that you use,in your case even though there is no
    routing,the systems throws the message before saving,but the status will be saved with errors.
    Check with this and revert back.
    Regards
    Mangalraj.S

  • Standard Cost Estimation Functionality removal from S.O.

    Hi Friends,
    I would like to know, is in SAP system there is an option to remove funcionality of auto Stadard cost Estimation i.e. we don't like to make Standard cost Estimation at the time of Sales order creation.
    Can you Please tell me about this feature.
    Rgds, Krishan Raheja.

    Hi,
    I am talking about the Cost Estimation happens, as it shows the cost via menu path---> Extra --> Costing. Further, the system will make the accounting entries for consumptions/Receipt w.r.t. to cost calculated vai this estimation. VPRS condition is not having the same prices as calculated in Costing. Further, the stock will also remain with same prices as calculated in price.
    Can you please suggest, if there is any option, so that we can omit this costing calculation and system make consumption/receipt entries with the values in material master.
    Rgds / Krishan Raheja.

  • The split (i.e., 70% & 30%)during standard cost estimation (CK11)

    Dear All,
    A component(Y) in the BOM of X is manufactured in house (70%) & procured directly from vendor (30%).
    Can we have the split (i.e., 70% & 30%)during standard cost estimation (CK11)
    Based on the cost we deside to make or buy.
    Please explain the procedural steps in arriving at this solution.
    Regards,
    Kumar

    Dear Mr.Kumar,
    <b>For any material in the material master , for Price
    Control indicator in Accounting 1 View we can either
    maintain S or V.</b>
    <i>For In House Manufactured materials we maintain S
    (Standard price) & for Sub contracted or bought out
    items we maintain V(Moving Average price).</i>
    <b>During cost roll up & release as far I know we cant
    split like 70 & 30% and we can do the costing.</b>
    So either you have to use the moving average price for
    both inhouse & bought out.
    <b>Because 1 material cant have both standard price &
    Moving Average price.
    Because bought out item's doesnot have standard price.</b>
    If your vendor is ready to give the material(Finished
    product) using the same amount which you spend for
    producing inhouse,then no issue,you can use
    standard price.But Practically it doesn't occur.
    I hope this will help to clear your doubt.
    <b>If useful reward points.</b>
    Regards
    Mangal
    Message was edited by:
            Mangalraj

  • Goods movements of material with serial numbers

    Hi,
    1. Is there any report or table where I can see goods movement of material with their serial numbers?
    2. Also in MMBE i can see 'On order stock'. I know this is PO open PO quantity.
    Now this open PO qty will not be there against any storage location. I got some stock on this status in some storage location.
    How I can move to 'unrestricted stock' status?
    Please advice.

    Hi,
    Is Serial number is the one obtained thro stadard batch management or is it a Zfield.
    On Order stock cannot be converted to unrestircted stock unless a GR is made.
    With regards,
    Jeeva

  • Dump when execute MMPV (Material Ledger is actived)

    Hi experts,
    This is my scenario:
    - We are testing in a Development system (No productive system)
    - Material Ledger is actived since 12-2011
    - No Material Ledger period end closing made in 12-2011
    When we execute MMPV the system shows the dump:    SAPSQL_ARRAY_INSERT_DUPREC
    We applied the sap note: 1123034 - MMPV: SAPSQL_ARRAY_INSERT_DUPREC error in SAPLMLCCS, but the dump continues.
    I checked the table ckmlkev and I saw registers to Company Code 0200 Period 2 and Year 2012, however if I check OMSY transaction, I saw only Company Code 0200 Period 1 and Year 2012.
    There is something extra to do?
    Thanks in advance for  your help,
    José Luis

    Hi,
    This short dump is produced when the system tries to insert a new
    entry in table CKMLKEV but a duplicate entry already exists in the same
    table.
    CKMLKEV indicates in which period which cost component structure is
    used for the actual cost component split. CKMLKEV entries are created
    by MMPV. Their existance for these periods indicates that the period was
    shifted already by MMPV.
    What you can do now is the following: please check the period
    status in ML.
    If the status is undefined, then delete the CKMLKEV entry and re-run
    MMPV.
    If the status is period opened (or higher), then you have to reset
    the MM period.
    Best Regards,
    Arminda Jack

  • Material Ledger not activated in Material Master--Urgent

    Dear Gurus,
    We have created Material Master  of Project Material With tag "Do NOT Cost" but Material ledger not get activated. although In plant material Ledger  is activated .
    Can any body Help to find out solution
    Regrds
    Mahesh
    *Assign full marks

    >
    Kishore Kumar Chiluka wrote:
    > Hi
    >
    > Please get in touch with your BASIS consulatant , as the updates are not performing rightly, this seems to be asystem error.
    >
    > Thanks & Regards
    >
    > Kishore
    Thanks a lot Kishore.
    But unfortunately we don't have any Basis Guy separately. I was doubling up as Basis as well APO in my org . I'm pretty new to all these stuff. I searched in help.sap.com about this a lot, but couldn't find anything useful.
    Can you help me in identifying a solution to this problem?
    Thanks,
    Rajesh Manoharan

  • Difference in the Material variant  BOM Qty during Standard Cost estimation

    Hi SAP Experts,
    We are trying to estimate the cost for the material variant, but the BOM exploded
    during the cost estimation, the quantity differs slightly with the BOM exploded
    during CU50.
    What might be the reasons for difference.
    Please give your valuable Inputs.
    Thanks
    Best Regards
    Siva

    Dear Mr.Kumar,
    <b>For any material in the material master , for Price
    Control indicator in Accounting 1 View we can either
    maintain S or V.</b>
    <i>For In House Manufactured materials we maintain S
    (Standard price) & for Sub contracted or bought out
    items we maintain V(Moving Average price).</i>
    <b>During cost roll up & release as far I know we cant
    split like 70 & 30% and we can do the costing.</b>
    So either you have to use the moving average price for
    both inhouse & bought out.
    <b>Because 1 material cant have both standard price &
    Moving Average price.
    Because bought out item's doesnot have standard price.</b>
    If your vendor is ready to give the material(Finished
    product) using the same amount which you spend for
    producing inhouse,then no issue,you can use
    standard price.But Practically it doesn't occur.
    I hope this will help to clear your doubt.
    <b>If useful reward points.</b>
    Regards
    Mangal
    Message was edited by:
            Mangalraj

  • Standard cost estimation along with departmental transfer

    Hi Friends,
    I will like to have the overview of the
    1. departmental transfer price.
    2. CKM3N (i.e. material price analysis, what is the difference between activation and non activation of it.)
    3. KB21N (Direct activity allocation)
    What are their connection in estimating the standard price.

    Hi Friend
    1) Transfer prices
    Transfer price is a price used to valuate the transfer of goods and service between profits centers. Precondition is that you have Material Ledger active
    Legal View = Company Code
                                                 Parallel  Valuation Approach
                                                /                       |                     \
                                        Group                Legal               Profit Center
    -  If currency type 32, transfer price is active
    -  Internal moves are always valued at procurement price
    2) CKM3N
      Before you activate Material Ledger you would have the option of S or V Price control, however when you activate ML  you   can value Materials at "periodic unit price", this price takes into account all the transactions of a material in a period(i.e goods movements, procurement etc..) and then at the end of the period revaluates the Material with a new periodic unit price.
    3) KB21N
    Allocation in general means taking cost accumulated on one object and allocating it to another, usually a cost center.
    Direct Activity Allocation is where you use transactions KB21 (KB21N) to manually allocation costs from the cost collector (e.g. Order) to a specific Cost Center. The activities can come from PS or from CATS Activity Recording. These activities are assigned to an order/wbs/network. And from there via the transaction KB21/KB21N they are allocated to a specific cost center.
    I hope the above information helps.
    Regards,
    Declan

  • At co11n in goods movement screen material not showing

    hi all,
           when i m doing co11n n going to goods movement screen it not showing  material and its quantity though after the confirmation material deducted from its stock, plz help me in this matter

    Hi dear,
    In Production order in operation overview check if control key is correctly maintained or not.
    Also in Production order component over view if the back flush is unticked then that material will not be seen in CO11N goods movement.

  • How to undo changes in Delivery after goods movement happened

    Dear All,
    I need to undo the manual changes done in delivery note but the goods movement and billing document has been created.
    Advise me regarding this.
    Thanks in advance
    Raghu

    Agreed with Amit. It doesnt make a sense that after doing PGI and billing user can change delivery document. This is standard functionality of SAP to avoid missuses of Sales documents. Like Delivery document you also can't change billing document or delivered items in sales order. For this you need to go reverse your whole sale process e.g Reverse billing VF11 > Reverse PGI VL09 change or delete delivery document VL02N and change or delete sale order VA02

  • Send IDOC DESADV4.DELVRY03 after goods movement

    I need to send an IDOC DESADV4.DELVRY03 when a goods movement type 951 is done. The IDOC is standard but I need to fill it manually, obviously, because there is no real delivery with data to fill it.
    I think the steps are the following but I need a little help to do everything:
    1 - Go to transaction NACE and for application 'ME' define a new output type. But how I do that? What are the steps here to generate a message when a goods movement type 951 is created?
    2 - Now... I expect to have data in table NAST, for generated output messages, but I'm missing some configuration I think.
    3 - In WE20 I define a partner profile for my IDOC, there I specify in Message control tab the application and message defined in NACE, and a Z process code defined by me in transaction WE41. That process code will be related with a Z function module to generate manually the IDOC.
    As you can see, I have a bit knowledge about this but not enogh to finish it.

    Hi,
    We can see how to create invoice
    1. Create logical system in BD54
    2. Assign logical system to client in SCC4
    3. RFC Destination - SM59
    4. VK01 - Condition Element
    Give usage (B) and application type (v3)
    select condition types and click on continue
    click new entries to create youe own condition type
    Give access sequence 0001 , transmission medium 6 , partner bp , date - 4
    Click processing program Here enter the program name as RSNASTED and form routine as EDI_PROCESSING.
    Then in the initial condition type screen click partner definition button and add new entries and enter the data.Save and exit the screen
    Select Access sequences and press enter.
    There will be a list access sequence already defined, select u201810u2019 for the field access and click ok.
    Save and exit the screen and return to the initial condition element screen.
    Select Procedures in the condition element screen and press enter.
    Select the procedure u2018V0001u2019 which is defined for the access sequence u20180001 and then click control.
    Define the Step no, Control and Condition type and then save
    Port Definition:
    Transaction Code: WE21
    Create a file port as u2018YINVu2019 and in the function module field give u2018EDI_PATH_CREATE_USERNAMEu2019 in the outbound file tab.
    Partner profile:
    Transaction Code: WE20
    Select partner profile as type u2018KUu2019 u2013 Customer and select u2018<custno>u2019. Check the outbound parameter for message type u2018INVOICu2019 corresponding to invoice is there or not. If not define it by add entries. Then double click the message type to define the outbound parameter.
    Outbound parameter:
    Here you specify the receiver port as u2018YINVu2019 which was created and basic type as u2018INVOIC01u2019 in the outbound options. Then define parameters in the message control tab v3 , inv , sd09 and save
    or
    try http://www.saptechnical/Tutorials/ALE/Guide/Index.htm

  • Difference in the BOM Qty during Standard Cost estimation

    Hi SAP Experts,
    We are trying to estimate the cost for the material variant, but the BOM exploded during the cost estimation, the quantity differs slightly with the BOM exploded during CU50.
    What might be the reasons for difference.
    Please give your valuable Inputs.
    Thanks
    Best Regards
    Siva

    Dear Mr.Kumar,
    <b>For any material in the material master , for Price
    Control indicator in Accounting 1 View we can either
    maintain S or V.</b>
    <i>For In House Manufactured materials we maintain S
    (Standard price) & for Sub contracted or bought out
    items we maintain V(Moving Average price).</i>
    <b>During cost roll up & release as far I know we cant
    split like 70 & 30% and we can do the costing.</b>
    So either you have to use the moving average price for
    both inhouse & bought out.
    <b>Because 1 material cant have both standard price &
    Moving Average price.
    Because bought out item's doesnot have standard price.</b>
    If your vendor is ready to give the material(Finished
    product) using the same amount which you spend for
    producing inhouse,then no issue,you can use
    standard price.But Practically it doesn't occur.
    I hope this will help to clear your doubt.
    <b>If useful reward points.</b>
    Regards
    Mangal
    Message was edited by:
            Mangalraj

Maybe you are looking for

  • How to set up Link Aggregation on Windows 7 ?

    I am going to buy a new Switcher that is LACP (Link Aggregation Control Protocol) supported so I can get a little bit better internet by combining my two ethernet ports on my MacPro (Mid 2012) where i have Windows 7 Ultimate installed as well as Mac

  • Problem with jFreeChart

    Hi I am trying to bring up jFreeChart and have unsuccesfully trying to run the following "hello world" chart example: // ChartTest.java - 05/10/04 // Test jFreeChart package mypackage; import org.jfree.data.*; import org.jfree.chart.*; public class C

  • Budgeting on account & cost center level

    Hi ALL, My company is planning to implement SAP in the near future and I'm taking the SAP course now. According to what SAP instrcutor said, budgeting cannot be done on account & cost center level. In my company, our current practice is to record all

  • Publish site / FTP issues arggg

    Long time fan of Apple. Purchased iweb09 last week and built a site for my small business. <Edited by Host> Well I have tried but I can't resolve the following issues: (1) FTP Server Test Connection returns OK. But when I try to load the site I alway

  • PM01 - Custom Infotype "No entry in table T589A for P"

    I created a custom PA Infotype with PM01 and now get error "No entry in table T589A for P". T589A is a table with function codes e.g. DIS, INS, LIS and also "P" & "Z". T589A is read when the dynamic PF-STATUS processing is done for Infotypes. I'm try