WIP over-completion increased component requirement qty

Hi all,
In normal situation, produce 1 product just 1 component. So that we create a discrete job in ebs to produce 1000 pcs of product and the component requirement qty is 1000 pcs.
However, in some cases, factory can produce more products based on this components.
To record the actual completion, we use 'Over-completion' and input 1011 pcs of product to complete.
The ebs system automatically change the component required qty = 1011 pcs. It makes factory seems need to procurement 11 pcs more to complete the production. (it also affect the MRP planning).
Please kindly advise how to fix it.
Best regards,
Laurie

Hi,
As mention "WIP over-completion increased component requirement qty" - yes, this is seeded functionality.
In Oracle, WIP Over completion qty is nothing but extra produced qty as per WIP job Qty. (ex. Job qty=10, total produced qty=12, i.e. 2 is over-completion qty)
Please explain expected requirement with example so that will figure out possible ways.
Thanks
ND

Similar Messages

  • WIP Assy Completion -The onhand qty is zero for the selection criteria ente

    Hi,
    I am trying to do a Work Order-Less completions with Transaction Type as 'WIP Assy Completion', the assembly items are not serial and lot controlled.
    When i am trying to save it, it throws an error as 'The onhand qty is zero for the selection criteria entered'.
    Please suggest.
    Thanks

    Do you have onhand quantity for the components under that assembly?
    Thanks
    Nagamohan

  • Multiple 261 movements allowed over required qty in work order

    Does anyone know why 2, 261 movements can be performed for the same components in a work order using MIGO? The transactions were performed within 2 seconds apart. Is it possible that SAP didnt update the work order within those 2 seconds?
    I have tried to duplicate this issue and I keep getting the correct message that I cannot perform over the required qty.

    It has to do with the configuration setting for the order type, verifty
    confirmation parameters for the given order type (at the header level)
    Under checks tab(Tcode: OPK4), it should be maintained as
    "  Error when overdelivery tolerance is not checked"
    If you maintain the above setting, he system would not allow you to do excess Goods Issue (mvt type 261) for the given work order
    Please come back if you have further ?s
    Edited by: Eshwer . on Jan 24, 2009 4:42 PM

  • Withdrawal Qty exceed requirement Qty in production order

    Hi: guys
    In our system, withdrawal Qty can exceed requirement Qty for a production order, even we use planned GI. That means when we use MIGO/MB1A to process GI to reference production order, we can manually change withdrawal Qty. Even this Qty has exceed requirement Qty of production order, system also not give me any message.
    Anybody can tell me how to customize settings to limit this function, such as give me a message (error or warning), and ensure withdrawal Qty can not exceed requirement Qty.
    thank you.
    Henry

    Henry,
    I got what excatly the problem is in your case, the guy who executed has done it very cleverly.
    What must have happenned, is that in the change mode of the order, the component quantity was increased and then Issued. Latter on in the change mode of the order again the quantity was reduced.
    I think this is the excat case what you are having now in the system, the only clue left out for us is to check whether the manual change was perfomed or not. In the components overview scroll to the right side of the screen till you reach column with heading "ChngeProc.", here if the field value is "1" - then it is obvious that there was a manual change in qty for the component.
    The possible resolution to prevent in future is to Make the dynamic message "CN" - 752 as Error in the prodcution order change program. You need to work with your ABAP person for this.
    Hope I was able to get to the right problem and possible resolution.
    Regards,
    Prasobh

  • This component requires that the embedded font be declared with embedAsCFF=true.

    Hey all,
    I fall into a small problem with fonts embedding. In my application I have embedded over 50 fonts and all expect one works as expected.
    That one shows an error "warning: incompatible embedded font 'Algerian-CFF' specified for spark.components::RichEditableText (RichEditableText310) . This component requires that the embedded font be declared with embedAsCFF=true."
    I have been looking all over the internet for similar problem, without success. Why this font is not working while all the rest does? Any clues?
    /* CSS file */
    @namespace s "library://ns.adobe.com/flex/spark";
    /* embedded font */
    @font-face {
    src: url("ttf/ALGER.ttf");
    fontFamily: Algerian-CFF;
    Thanks.

    Thanks,
    My issue is not to embed a font twice. Let me describe the issue so this will helpful.
    I have embed a fonts like below code.And apply LucidaBlackletterSpark font for spark component but it gives me error like
    "warning: incompatible embedded font 'LucidaBlackletterSpark' specified for spark.components::RichEditableText (RichEditableText2301) . This component requires that the embedded font be declared with embedAsCFF=true".
    But Font have already embedAsCFF property true. I am not able to find the solution why it is give me this warning.Due to that i am not able to embed a font.
    @font-face {
              src: url("assets/fonts/LucidaBlackletter.ttf");
              fontFamily: LucidaBlackletterSpark;
              embedAsCFF: true;
    @font-face {
              src: url("assets/fonts/LucidaBlackletter.ttf");
              fontFamily: LucidaBlackletterMX;
              embedAsCFF: false;

  • Requirement Qty in Report MCRE(Based on S026 Info Structure)

    Hi, PP gurus
    Issue:
    When i run report MCRE for material usage wrt Prod.order selection as input.
    Requirement qty as per BOM component explosion is not updating correct figure.
    suppose say my BOM comp. reqd qty 100 it is showing there in MCRE as 200.(Exactly 2 tim
    again i have restricted user from not changing component qty in order.
    Actual withdrawn qty showing that is correct but reqmt qty are not updating in S026/MCRE.
    Suggestion and Solution required.
    Rgds,
    Yogesh Thorat.

    Dear Yogesh,
    As per ur post it is clear that only for this material  problem is
    Now from here it is tough to judge
    As i said earlier, Just check in COOIS, MB51 & MCRE
    Also check for that particular prdocution Component view for the Qty
    You should able to Figure it out
    Good Luck !!!!
    Regards
    Madhu

  • Sub con PO : component Data Qty

    Dear All ,
    i have created Sub Con PO for line item 1 & 2 for A & B material respectively .
    the component required for the Same A & B is R only .
    in which table i will be getting the Qty of Components Item wise of PO ?
    Pl guide

    hi,
    For this you shd see the BOM tables..
    TABLES:
    STKO BOM - header
    STPO BOM - item
    STAS BOMs - Item Selection
    PLMZ Allocation of BOM - items to operations
    MAST Material to BOM link
    KDST Sales order to BOM link
    STPN BOMs - follow-up control
    STPU BOM - sub-item
    STZU Permanent BOM data
    Hope it helps..
    Regards
    Priyanka.P

  • Requirement Qty more than BOM Qty

    Hi,
    I have a scenario, in my Component Overview of Prodn Order, Requirement Qty of Components in Prodn Order is Different than BOM Qty.
    I checked the exploded Qty in CS11, CS12 and CS13. But the Reqt Qty vary with BOM Qty.
    Note: No Scrap is maintained
    Please guide.
    Thanks in advance,
    Harris
    Edited by: Harris Panchal on Feb 17, 2010 6:58 PM

    Hi,
    1. surely there is a mistake happening at your end.
    2. System is robustic on this kind of transactions
    Check the below items
    1. if any scrap has been maintained at the assembly level for the header material in the material master
    2. If any scrap has been maintained for the materail at the BOM item level.
    3. check if the unit of measure is same and any relationship is maintained.
    4. Also do re-xplode your CS11 and check if it works fine as per your expectation..if it is giving any issue in the production order , it should also give the same here..
    kindly validate and let me knwo the feedbakc
    reg
    dsk

  • Component / Requirement Quanity in CSMB

    Hi Gurus,
               Can anyone please explain the difference between component and requirement quantity in tcode CSMB.
    I have a multilevel bom.For example here is what I see:
    Item                        Component qty                          requirement qty
    item 1(stockable)               888.890                                      98
    item 2(stockable)               .8976                                          1
    item 3((stockable)              .6899                                          1
    item4(text item)                   45                                           45
    item 5(stockable)                40                                              5
    item 5(stockable)                31.120                                        4
    Thanks you all.

    Hi,
      First check whether it is in CSMB OR CS11
      Required qty:  Your requirement qty for FERT (Example 10 pcs reqmt qty)
      Component qty: For producing 1 pc of FERT
                              how many HALB AND ROH is needed(Example 1 and 2 respectively)
       So for producing 10 pcs your HALB Reqmt is 10 pcs
                                          your ROH Reqmt is 20 pcs.
    Regards,
    nandha

  • This component requires that the embedded font be declared with embedAsCFF=false.

    I'm getting the following warning for my project.
    "warning: incompatible embedded font 'MyFont' specified for views::MyViewInnerClass0 (MyViewInnerClass0_61) . This component requires that the embedded font be declared with embedAsCFF=false."
    Here's what I have in my style.css file.
    /* CSS file */
    @namespace s "library://ns.adobe.com/flex/spark";
    @namespace supportClasses "spark.globalization.supportClasses.*";
    @namespace views "views.*";
    @font-face {
              src: url("assets/MyFont.ttf");
      fontFamily: "MyFont";
      advancedAntiAliasing: true;
      embedAsCFF: true;
    @font-face {
              src: url("assets/MyFont.ttf");
      fontFamily: "MyFont";
      advancedAntiAliasing: false;
      embedAsCFF: false;
    The 2nd font section I have is what is suggested as the fix in most places but that isn't working out for me. I wonder if I'm missing something else.

    I tried changing the name and it didn't work. Tried all sort of combinations too and none worked. Tried a different font and that didn't work too.
    Turns out the problem wasn't in the declaration of the fonts but where I was using it.
    I initially had the font declared globally
    global
       fontFamily: DroidSansMono;
    I saw that, in your comment you had mentioned "..then apply it to the component" so I applied the font to the label component
    s|Label
      fontFamily: DroidSansMono;
    and boom.. no warning. Problem solved.
    Thanks so much.

  • How system calculate the required qty. after MRP RUN

    Hi,
    I want to know if we are using MRP Type as PD and also we are calculating automatic saftey stock and re order point qty. after MRP RUN according to which rule formula system calculate the safty stock, reorder point qty. and the required qty. as a PR.
    and if we are not using calculate safety stock automatically and if we set safety stock qty. manually in this case how system will calculate the required qty.
    regards,
    zafar

    please check the below links.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/6f/b441a9a1b011d3a82d0000e82a3c24/content.htm\
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d256344af11d182b40000e829fbfe/content.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/ff/515c4749d811d182b80000e829fbfe/content.htm
    please check the above links may get some idea.
    Regards,

  • I set up time capsule using a wireless 4g modem.  it's been five hours and it still is saying making backup disk available (4.97 GB of 18.52 GB).  Can I stop the whole thing, get a ethernet cable and start over to increase the speed of the backup?

    I set up a new time capsule on a wireless 4g modem.  I started the initial backup.  It's been five hours and it still says "making backup disk available (4.97 GB of 18.52 GB)."  Can I stop the whole thing, connect my computer to the time machine using an ethernet cable and start over to increase the speed of the backup?
    Thanks,
    David

    Bunce wrote:
    oh i already did that. Im working on my imac and looking into this on my macbook. Was able to reproduce the issue again by trying to open TM. Locked out the finder again and had to restart. I checked the serial number and it was an early 2009 purchase with no coverage.
    If you bought a Mac and got AppleCare with it, within 2 years of buying the TC, the TC is covered, too.
    I have to admit that this $500 unit was the first to apparently junk out. The western digital that had my main data on that is my daily external that I store about 2TB of data on is still perfect and the new technology TM appears to already be cashed. Love the computers, not to big of a fan on the externals of the apple TV's. No life expectancy. Neither here nor there.
    suggestions before I either get this looked at or scrap the HD on it and move forward.?
    Reset the TC. See [Resetting an AirPort Base Station or Time Capsule FAQ|http://support.apple.com/kb/ht3728].
    Try a "full reset" of Time Machine, per #A4 in [Time Machine - Troubleshooting|http://web.me.com/pondini/Time_Machine/Troubleshooting.html] (or use the link in *User Tips* at the top of the +Time Machine+ forum).
    If all else fails, take it to your local Apple Store or Authorized Repair location, they may be able to determine whether the disk is dead.
    If it is, they might replace the TC for you. If not, they won't repair it, but if the electronics are ok, you can replace the HD yourself, if you want to. See http://discussions.apple.com/thread.jspa?threadID=2542983

  • Off set for component requirement  in PM order

    Dear Experts,
    In my PM order,  offset date for component requirement date is working only for the first component. for the next component it is taking basic start date( i e order generated date by default) as the requirement date even though i entered offset for some days.
    Experts, please explain me how to come out of this problem.
    Thanks & Best regards,
    Praveen

    Dear Praveen,
    Its working Praveen.
    Please check this way: 1st operation>double click operation no.>put component>double click item no. of component>now set offset
    2nd operation>double click operation no.>put component>double click item no. of component>now set offset
    Now suppose you taking two component for same operation then for the second you can have different offset by clicking item no. of that componet.
    Please check and let us know again.
    Regards,
    Kaushal Rai

  • Component requirement date in subcontracting PO

    Hello All,
    I have subcontracting PR having delivery date as 26.11.2010 and release date as 17.10.2010 and planned delivery time as 40 days. I change the PR release date to 10.10.2010 and it shows the requirement date for the components as same as 10.10.2010 which is my requirement. But when I convert PR to PO it is showing the component requirement date as 19.09.2010 and release and delivery date same as in PR.
    How system is showing requirement date in PO as 19.09.2010? Is some one has any idea?
    Mayur Phalak

    Hi,
    Can you upload screenshots of what you see in ME53N & ME23N with details as seen in component list & the dates to picasaweb or some portal?
    Regards,
    Vivek

  • Component requirement date in subcontracting case

    Hello All,
    I have subcontracting PR having delivery date as 26.11.2010 and release date as 17.10.2010 and planned delivery time as 40 days. I change the PR release date to 10.10.2010 and it shows the requirement date for the components as same as 10.10.2010 which is my requirement. But when I convert PR to PO it is showing the component requirement date as 19.09.2010 and release and delivery date same as in PR. I want system should not change the component requirement date.
    How system is showing requirement date in PO as 19.09.2010? Is some one has any idea?
    Mayur Phalak

    Hi Mayur
    The requirement date for component in subcontract is Delivery date of the item minus planned delivery time -This is what SAP library says. But in your case I see a huge difference. Is your PR manually created or MRP generated?
    Have you maintained info record? Is planned delivery time is copied from info record? You can see planned delivery time in PO delivery tab. (find out which value has been copied).
    As per SAP standard when you press enter button in PO requirement date is redetermined based on planned delivery time in the PO delivery tab. So try giving Planned delivery time in PR or info record to adjust requirement date
    Write to me if you are not clear.
    Regards
    Antony