Budget exceed

Hello Everyone,
I have a Project which runs from 01/2006 to 12/2007 with Availability-control set for the Budget, the project is technically complete and the Project cost report shows a excess value posted to a particular WBS in the structure.
when i checked the total postings for each year /each month through standard reports for Actuals (Cji3) and Commitments line items and budget supplements for individual years,i find that at the end of the first year 2006/2007 there is still budget remaining in the proj,
  and  the Budget report cj30 (assigned) for 2006 shows only the value equal to Actuals posted to the WBS not considering the commitments, in the year 01/2007  i assume from the analysis the amount equal to remaining budget value plus the commitments is carried forward to next year and is consumed over the year 2007 with additional supplements, still at the end of the year 2007 i have budget left so why the Cost report showing the excess value.
02/2006  Budget      15000 (starting of the Project)
       2006  Actuals    12000     
       2006  Commit     2000
Budget Report showing for 2006 (cj30)
        Assigned         12000
        Current            12000
it has allowed the carryforward
Budget Carried Forward to 01/2007 is  3000 ( i assume it is 1000 balance + 2000 commitment)
      Total Supplements in 2007 is 15000
       Actuals         12000
       Commitment   5000
        Balance        1000
Now the system (Cost report) is showing an excess amount(-1000)
I.e Total Budget for 2007 is 18000 , consumed is 17000 ,Balance is 1000
The budget report shows for 2007
Current 18000   Assigned 19000
    I have not exceeded in any of the years so why is the Cost report giving me wrong picture.
  If i have gone wrong in analyzing or have missed any link please guide me.
Thanks in advance
Vinayak.
Solutions will be duly rewarded>>>>>

SAP recommends to re construct the availability control if:
1. you install a new release
2. you haved changed the availability control settings in the budget profile (e.g. from overall to annual values)
3. you have changes the tolerance limits for availability control
4. you have defined exempt cost elements - that is, cost elements which are not subject to availability control
5. you have changed the order update settings for orders for projects
6. you suspect errors in the data - for example, in objects from older releases or after incorporating corrections relating to budgeting or availability control
T Code CJBN
Try doing this for a specific project so that you can observe if any corrections are done.
Regards
Sreenivas

Similar Messages

  • Budget Exceeded but no Error message Assign more than allocated

    Hi Gurus,
    I am stuck in a situation where the Error Message BP603 while creating a PO for a wbs at level 2.
    IN cj30 , i found out that  Budget = 69500000 and assigned = 69950772
    if i create a PO OF even .30 (thirty paisa) the budget exceeded amount = 450772.35, which is actually the diffrecene betweenn assigned and Budgeted values.
    Now we are not able to raise any PO
    Below is tolerance limit
    please key in your valuable inputs.
    Regards
    Rohit

    Hi Rohit,
    In Budget report, Assigned value = Actual + Commitment
    If your assigned value is great than Budget, then you will get Budget exceeded error when you try to do any further posting against specific WBS element.
    So, you will need to supplement Budget to cover shortfall.
    You can also refer following SAP note which shows how assigned value is calculated.
    178837 - Availability control: Incorrect assigned value?
    There are lot of threads already discussed in this forum for error message you are mentioning.
    Please search them.
    Regards
    Tushar

  • Budget Exceed Issue in work Order (P.O) in Production Server.

    Hi Friends,
    I am getting different type of budget exceed issue, that to only in Production server.
    Here the issue is when I am creating the work order P.O (Acc.As. Cat.P, Itm Cat. D) with different service line items with respective WBSe with in the budget limit, then I am doing SES for some quantity, now when I am changing (I am decreasing not increasing) the same P.O line item available quantity and creating the new version now system is calculating the old version line item quantity + new version quantity (nothing but double) then giving budget exceed error.
    One more strange thing is, if I change quantity for one line item then system is giving budget exceed error for another line item which is having the different WBSe which was saved with out giving any error at the time of P.O creation.
    This issue is happening only in Production server ....same scenario I have run with the same values in both Dev. and Qau. (Where the config. is same in all 3 clients) but in both the clients it is working fine...but in production why the system is behaving in such a way I am not getting. 
    In the below I have given the test scenario...
    Service P.O Creation
    Line Item
    P.O Quanity
    Value
    WBS
    Budget
    Commitment
    SES. Quatity
    Actual cost
    1
    10
    100
    WBS 1
    2000
    1000
    5
    500
    2
    20
    200
    Wbs 2
    4000
    2000
    10.00
    1000
    3
    30
    300
    WBS 3
    6000
    3000
    15
    1500
    4
    40
    400
    Wbs 4
    8000
    4000
    20.00
    2000
    Service P.O change with new version
    Line Item
    P.O Quanity
    Value
    WBS
    Budget
    Commitment
    SES. Quatity
    Actual cost
    1
    6
    100
    WBS 1
    1000
    1000
    5
    500
    2
    20
    200
    Wbs 2
    2000
    2000
    10.00
    1000
    Budget exceed with the double value
    3
    30
    300
    WBS 3
    3000
    3000
    15
    1500
    4
    40
    400
    Wbs 4
    4000
    4000
    20.00
    2000
    If any one has come across with this type of issue and solved ...please suggest me ..
    Regards,
    Srikanth

    Hi,
    I have face similar issue in deleting PO line items.
    Even though I delete items, system check budget for deleted qty with the currency conversion + value & gives budget exceed error.
    In some cases we have asked user to deactivated AVAC asked to do the transaction, which is not recommended.
    You can try running CJBN & CJBV in sequence for affected WBS.
    Thanks & reg,
    Sam

  • Error: Order 300401 Budget Exceeded while doing PO w.r.t PR

    Hi Experts,
    We are getting error, Order 300401 budget exceeded  while doing service PO
    In budget shows exceeded in making the P.O of approx amount Rs 411,500. While in the below PO Value, it is clear that the indent still has the amount of RS 1,760,737.
    Indent No. 1000031924 Total Value = 3,230,000
    Sr No.     P.O     Value     
    1     3900006041                       456,774     
    2     3900006146    Line item 1       101,467     
                            Line item 2      266,414     
    3     3900006184                       326,158     
    4     3900006188                       318,450     
         Total P.O's Value               1,469,263     
    Total value of Indent                  3,230,000
    Total P.O value in the Indent     1,469,263
    Balance Amount in the Indent     1,760,737
    Regards,
    Manjunath

    Hi,
    Budget is exceeded w.r.t to maintained Internal Order in PR /PO ,Use below options.
    1 ) Re-construct Budget-KO31 or
    2 )Either de-activate budget-KO32 or
    3) Maintain budget for IO-KO22 .
    This will resolve your issue.
    Thanks & Regards,
    Sandesh Sawant

  • Budget Exceed Error during creating of Purchase order in reference to PR

    Hi,
    I am getting the subject error (Budget Exceed Error) every time when I want to create a purchase order related to purchase requisition of my project.
    Issue is that after release the project when the purchase requisition has created for non stock item under activity I found in transaction CJ31 the assign value has already updated.
    Let say my budget is 400 US$, and the purchase requisition has created for 380 US$. Now when I check with CJ31I found the assigned value is 380. Now If I create a purchase order it throws an error that budget exceed.
    The tolerance limits are following:
    SA     ZSA01     Budget Profile Overall AVAC     ++     1     90,00
    SA     ZSA01     Budget Profile Overall AVAC     ++     3     100,00
    SA     ZSA01     Budget Profile Overall AVAC     01     1     90,00
    SA     ZSA01     Budget Profile Overall AVAC     01     3     100,00
    Please advice what will be the proposed solution for the above issue.
    Thanks in advance.
    With Regards,

    Your budget is 400$ and PR value is 380$ but you have not mentiond what is the tax value ?
    when u r creating PO at that time system will check the budget against PO value considering taxes also.
    eg. 380$+tax value.
    after considering taxes your total PO value imay be getting updated more that 400$.
    Explre you error by clicking on error information you get the exact diffrence in budget and PO value.
    Hope this will sove your problem, reply after doing this.

  • Error in PO "IO Budget exceeded"

    Hi All,
    I am working with extended classic scenario , I am facing a problem while changing the PO.
    When I try to add or delete any line item in the PO it throws error of "Budget Exceeded for the IO XXXX" for 1st line item or any other line among the PO for which the PO is ordered and Budget is available.
    e.g.
    1) PO is created with one IO 1P , its in ordered status . after that I try to add 2nd line item in the same PO with IO 2P, that time it throws error " Line item 1 Budget exceeded for  IO 1P "
    2) Po created with 8 line items with different IOs.. When I try to delete 6 line item , it throws Budget exceeded error for other line item.
    Its working fine in Test system, I tried to replicate the same scenario in ET2 ( Test system ) but I didn't get any error there, so its really very difficult to analyse exactly whats happening in production system.
    Please help me out to resolve this issue
    Regards,
    Sheetal

    Hi CS,
    I have tried all sceanrios  before reporting this problem .I had created PO in R/3 and deleted , added line item in the same PO..  There is no any error in R/3 system.
    Its working fine. Only problem in the SRM side. That day I received one more same problem with another  PO.& IO..  User was trying to delete the PO line item , he wasn't able to delete it that day. But next day, he could able to delete the line item. & nothing was changed in that one day... This is really inconsistency of the system.. I don't know whats happening in the system and how to rectify this error. As  I said, I had tried to replicate the scenarion in SRM test system . In my first atttempt , i could able replicate the same error, but when I tried next day there was no any error in the PO...... After that I tried many POs but not able to replicate the same error.  I have raised OSS for this , but side by side I am trying to fix this problem from side, as many problems are reporting from the user side..
    Also I would like to share one more imp thing, that this problem is only one specific conutry.. We are supporting Globally, but not other than Thailand reported this problem and its nos are also increasing day by day.
    Is there FI-CO related check setting there in SRM & R/ 3?
    I have checked the R/3 Co setting for IO, so will the Tolerance limit setting affect in this case?
    Please let me know
    Sheetal

  • Budget exceeded problem in PR

    Hello Friends
    I created the project and allocated the budget in 2009,
    I created  PR in Feb 2010, but the problem is while i am changing the quantities in ME52N.
    I am getting the error message :item XXX WBS element budget exceeded
    Even i carry forwarded the budget from 2009(CJC0) to 2010.still the same problem exists.
    Regards
    Kiran

    Hi,
    Check the delivery date in the PR. If the delivery date is for next year
    2011 system displays the error message.
    If problem still persists then reply the thread with error message number.
    Regards,

  • Budget exceeded

    Hi:
       I  am  posting  in FI with wbs,the system gives me the following  error  message:
    Item 001 WBS element ******** budget exceeded
    Message no. BP604
    Diagnosis
    In document item 001 WBS element ***, budget for WBS element *******for fiscal year 2008 was exceeded by 320.00 CNY.
    but  there is stilll enought available budget in wbs(48,200.00 CNY), i confirm in report S_ALR_87013558   the budget is 48200 cny,the actual cost and commitment is zero ; the system should not issue error message, I am so  confused!
    Regards in advance.
    thanks.
    Edited by: junzhi wang on Aug 26, 2008 8:11 AM

    Availability control against overall value
    Indicator which controls whether availability checks are conducted against the overall value or against annual ones.
    Use
    In the project budget profile, the "Overall" indicator, used in conjunction with the "Releases" indicator, has the following effect:
    Ind. 'Overall' Ind. 'Releases' Avail. control against ...
    X - Overall budget
    - - Annual budget
    X X Overall budget released
    - X Annual budget released
    X = Indicator is set, in other words, checkbox was checked.
    if  Ind. 'Overall' Ind. 'Releases'  are both not ticked,it's  Annual budget ;we have done the Annual budget and  Overall budget  already.and some WBS with the same budget profile  have no problem when posting.

  • Budget exceeded BP604 (when create Invoice)

    Hi All,
    User got an error message budget exceeded BP604 when create invoice. How can i know what the configuration to check why system check budget( Investment management). I tried to check the configuration in SPRO (Define tolerance limit for availability control) shows that budget profile use ++ which are : (no invoice checking) but in actual it checks budget.
    ++     All activity groups           
    00     Purchase requisition          
    01     Purchase order                
    02     Orders for project            
    03     Goods issue                   
    04     Financial accounting document 
    05     CO document                   
    06     Budgeting                     
    07     Funds reservation             
    08     Fixed prices in project       
    09     Payroll                       
    Many thanks in advance.
    Nies

    Business transaction group 04 (Financial accounting document) contains below transactions:
    G/L account posting
    FI invoice parking
    Invoice verification
    Goods receipt for the order
    Cash budget management
    Payment transfer
    Down payment posting
    Inventory difference
    Regards
    Sreenivas

  • Budget exceeded even if enough budget available

    Hi,
       When we are trying to post document to a particular cost center its giving an error message saying tht payment budget exceeded. But actually there's no budget object selected for tht commitment item, So it should pull the budget from the parent item which has enough budget. Can any one help to find out why is this happening.
    thanks,
    Sravanthi

    Kindly check this thread
    Re: Budget Mail Alert
    If you have maintained the activity group "++" in the tolerence limit for the AVAC.
    then the PO value is also included in addition to PR.
    There are two options:
    1. Either increase the budget or
    2. Note: 955107
    Go to OPS9 In the Budget profile which u assigned to ur project, Check for Availabilty control parameters over there Overall Paramaters should be ticked. If not then make it selected.And reconstruct availabilty control thru CJBN then try out ur posting
    check this Sap Note: 178837
    Hope this will solve ur issue
    Regards,
    ANSAR

  • Error : Annual budget exceeded (FMAVC005)

    Dear guru,
    I want to create PR (ME51N), the net total amount is 50.000. But the error message shows :
    Annual budget exceeded by 11.812.000 IDR (FM PB Availability Control) for document item 00010
    Message no. FMAVC005
    Diagnosis
    The annual budget is exceeded by 11.812.000 IDR (FM PB Availability Control) for the document item 00010. Budget control on outgoing amounts ( ceiling type Expenditures) raised this message for the following combination of availability control ledger, fiscal year (and if applicable, year of cash effectivity) and control object:
    9H/2011/DUMMY/EXPENSE1
    FYI,
    Consumable Budget : 35.700.000
    Consumed Amount : 650.000
    Available Amount : 35.050.000
    The error message says it's exceed 11.812.000, it seem Available Amount for budget is - 11.762.000 (50.000 - 11.812.000)
    It's strange...
    Please tell me how to solve this...
    Thank you..

    It's solved with logout from system and then log in again
    It's a very stange thing...
    Dear Alex,
    Thanks anyway

  • Message error Item wbs element budget exceeded

    Hi
    when I do a purchase requisition imputed to WBS element, WBS element consuming, but when I'm going to make the budget document of the reserve (R) in a transaction FMX1 jumps me an error message:wbs element budget exceeded ,it is trying to consumed WBS element , when it has consumed in the purchase requisition.
    I have solved it error with limits tolerance but in the funds commitments consumed other time , we see these results  in the report S_ALR_8713558.
    Where is the problem????
    Than you

    You have to differentiate the beaviour of the availability control in customizing for PS > Costs > Budget > Define tolerance limit
    With the "transaction group" you can differentiate for:
    ++     All activity groups
    00     Purchase requisition
    01     Purchase order
    07     Funds reservation
    Ciao
    Giorgio

  • "Budget Exceeded" error not appearing at the time of changing PR but appearing at the time of PO change.

    Dear All,
    At the time of PR value change after creation of PO budget exceeded error is not appearing even though the PR value exceeds the budget. But at the time of changing the same value in PO, budget exceeded error is appearing.
    List of steps:
    PR created.
    PR released
    PO created with reference to PR and released.
    PR value changed to a value more than the available budget - No budget exceeded error.
    PO value changed in accordance with the PR - System throwing the budget exceeded error.
    Now the issue is why the system bypassed the budget exceeded error at the time of PR value change and only giving the error at the time of PO value change. Also, we observed that while changing the quantity in PR which results in exceeding budget, system is giving the error. But while changing the value system is not giving the budget exceeded error.
    Your inputs will be highly appreciated. Thanks in advance.

    Hello Saurabh,
    Thank you for your inputs. Below is the output of CJI5.
    Ref,Doc Category  Debit Date     Oty       Object    Cost Elem.   Val/CO Area Crcy   Total Qty.     UM
    PREQ                  28.05.2014    WBS     XXXXXX    XXXXXX           0.00                         0            EA
    POrd                    28.05.2014    WBS                                       14,000.00                1000          EA
    From the above output i think system is not capturing the PR commitment. I'm not sure as i'm basically into MM and  dont know much about PS.
    Why the system is stopping with budget exceeded error at the time of PR creation and not giving any error while changing the PR value after PO creation. System is giving budget exceeded error if quantity is changed in PR. Please explain the standard system behavior and suggest how to enable control at the time of PR value change.
    Thanks in advance.

  • Budget Exceeded : Message No BP603

    Hi Experts,
    I am having problem with budget exceeded error.
    Scenario - When trying to invoice the P.O it prompt budget exceeded error but budget was available when checked the S_ALR_ report.
    As it was very urgent, Budget was supplemented to pass the Invoice for P.O and after it is invoiced I could still see the budget available more than already available budget.
    Example.
    Invoice for Commitment PO - 200000
    Budget Available - 50000
    Supplemented Budget by 20K to pass on the Invoice as it thrown error while invoicing, Hence New Budget available after supplement is - 70000
    After the invoice of PO - 200000
    Budget report showed the same available amount as 70000 ( No Change in the original value of budget even after supplement of 20K)
    so now I tried to reduce the budget back to 20k and roll back the budget back to 50K but system throws me the error as attached here.
    I have tried to analyze the report such as CJI3, CJI5, CJ31 also executed RKANBU01, CJBN, CJEN.
    This is done on lower level WBS and I have checked all P.Os and tax charged towards it to see if the available budget has been consumed with the tax amount or not.
    Real values on the scenario are given below. I am not able to get the point on where the 4641.43 USD is budget exceeding
    USD
    930451
    commitment
    345550
    actual
    1276001
    total Budget Consumed
    1289263
    Current budget
    13263
    available
    Appreciate experts help and comments.

    Hi Amit,
    We don't have release functionality maintained for budgeting.
    This is for child level wbs and sufficient budget is available.
    As requested I have attached the screen shot.
    Standard Report shows the budget in USD
    And CJ31 also displays the budget in USD
    I have also attached screen shot of budget in AUD, Where in on the available budget amount I am trying to reduce it by 20K in CJ38 which pops the budget exceeded error message.
    Thanks

  • Budget Exceeded error with message No BP 602

    Hi Experts,
    I am facing a budget exceeding error: Ntwk actvty 6000001 0020 budget exceded year 2009.
    following is the settings
    Availability control against: Overall                        
    Availability control against: Budget                         
    Availability Control in the Controlling Area Currency:       
    Activation type: Automatic activation during budget allocation
    Usage level in %:  0,00
    The project is P.0001
    Top lvl P.0001
    WBS P.0001.1
    Network Activity (External services) 6000001 0010 PR-($40000) PO($20000) & Service entery done with same amount($20000).
    Network Activity (External services) 6000001 0020 PR-($1)
    Actual   $20000
    Commitment 20001
    Assigned 40001
    Available $49
    Now we updated the budget as below:
    The original budget was 40050 in IM then modified to 45050 and distributed in CJ30.
    When we try to update the Service PR with 49 or more dollars, gives error in commitments and when the log checked, the budget exceeding message is there, if the PR updated with 48 USD, it gives the budge is exhausted.
    40050(Old Budget)-40001 (assigned) = 49 USD. Which means, the supplement of the  5000USD is not considered.
    Run the CJEN and CJBN to reconstruct the project but no use.
    Please help me out where to check and what went wrong. its in client prd.
    Regards,
    Ganesh

    Hi,
    You said in reports and in CJ31 , it is showing 60049 as available. I am confused here......including additional budget , total budget you gave is 45000. Then how it can show 60049 which more than Original Budget ?
    Have you distributed additional budget to the WBSE for which Service P.R is being raised ?
    What is distributable budget at the level of the WBSE for which P.R is being created in CJ30 ?
    What Is available budget against the WBSE for which P.R is being created in S_ALR_87013558. ?
    May be it will be of saome help for you.
    Thanks
    Saikishore.Ganga

  • Budget exceeded - Msg no BP603- While Deleting a PO

    Hi All
               I am Getting the error "Budget exceeded - Msg no BP603- While Deleting a PO " while deleting a Po-
    Budget exceeded by XXX amt ,in Documnet 020 in order xxxxxxx -PO is created  after the PR.
    Regards
    Shisac

    Hi
    Budget exceeds for INR 15.617.00 , The committment PO as INR 400000.00
    The Scenario is
    The PO as 3 line item , 1st line item  INR 400000.00 ( Deletion flag is marked ) , 2nd line item INR 19000.00, And 3rd line item 5000.00 , the client is trying to delete the 1st line item.
    I  saw the report s_alr_87013019 ( Available quality is 9535.00)
    Does this mean - system is checking for budget while deleting also ? ( i am not sure on this!)
    If yes is this a normal behavior of the system
    I am totally confused !

Maybe you are looking for

  • Why does my 3rd gen ipad only charge with an iPhone charger and not the 10w charger it came with?

    Im only asking this because it's annoying me , but my 3rd gem ipad will not charge with its 10w charger ? It will happily charge with my iPhone charger, and my iPhone will happily charge with the 10w charger but why won't the ipad charge with the cha

  • Concept of valuation

    Dear All, Please throw some light on the concept of valuation and explain with simple example difference between lowest value principle, strict lowest value principle and other valuation method. I tried to find it on help.sap but I'm not able to comp

  • Can i use this view in discoverer

    Hello I have a view like below in R12. GL_CODE_COMBINATIONS_KFV In etrm there is a warning: Oracle Corporation does not support access to Oracle applications data using this object, except from standard Oracle Applications programs. Can any one you p

  • Default to Color Printing

    I have a user that consistently prints to color printers and she would like to know if there is a way to set up Discoverer to always print to color every time she logs in. She currently changes to color in the advanced page setup, but when she logs b

  • Date Manipulations in J2ME?

    How do I add/subtract days from a given date using MIDP APIs?