Capital Investment process-- questions

Hi,
I am totally new into this process and have no idea about it.
I have a few queries as ->
What is an investment order illustrated with examples
what is an asset under construction and illustrated with examples
What is an internal order and how are they created?
What is a superior order and how are they created and how sub orders are assigned to the superior order and finally how the costs are settled to an AUC?
Moderator: help.sap.com

Hi,
the following link gives you a overview:
http://help.sap.com/erp2005_ehp_05/helpdata/EN/2a/f9f294493111d182b70000e829fbfe/frameset.htm
asset under construction  
A fixed asset that is in the process of being completed at the time the balance sheet is being produced.
Typically, assets under construction are shown as a separate balance sheet item for the enterprise. Assets under construction can be managed for bookkeeping purposes in the FI-AA component using asset master records in special asset classes.
To also benefit from management accounting functions that go beyond the asset accounting level, you can use capital investment measures in the Investment Management component. Investment measures can be managed in the form of internal orders or projects.
internal order
An instrument used to monitor costs and, in some instances, the revenues of an organization.
Internal orders can be used for the following purposes:
Monitoring the costs of short-term jobs
Monitoring the costs and revenues of a specific service
Ongoing cost control
Internal orders are divided into the following categories:
Overhead orders - For short-term monitoring of the indirect costs arising from jobs. They can also be used for continuous monitoring of subareas of indirect costs. Overhead orders can collect plan and actual costs independently of organizational cost center structures and business processes, enabling continous cost control in the enterprise.
Investment orders - Monitor investment costs that can be capitalized and settled to fixed assets.
Accrual orders - Monitor period-based accrual between expenses posted in Financial Accounting and accrual costs in Controlling.
Orders with revenues - Monitor the costs and revenues arising from activities for partners outside the organization, or from activities not belonging to the core business of the organization.
Regards Bernhard

Similar Messages

  • Capital Investment process

    Hi,
    Can someone explain to me in details the steps followed in capital investment process.
    What are the basic steps followed in details?

    Hi,
    When you have decided to buy a capital equipment, following procedure is usually followed.
    FICO:
    > Create an investment order for that asset.
    > Create an asset, with reference to the above investment order.(can 'asset under creation' or permanent asset class, which will be decided by FICO)
    MM:
    > create a material master for the asset (equipment)
    PM:
    > create PR with account assignment   'F' and use the investment order as the account assignment. This will link the FICO activity to the procurement process and will continue as integration.
    MM:
    > convert the respective PR to PO and do the GR.
    PM:
    > create equipment master for the asset received with acquisition date filled.
    > when commissioning is completed, give the start up date and install the equipment.
    FICO:
    > when the asset is commissioned, FICO will convert the AUC into permanent asset, if required or start the depreciation activity immediately. The permanent asset number may be entered in the equipment master.
    > There are two ways to achieve link the asset to equipment master automatically and FICO can give more details on that activity.
    James Prabaharn

  • Internal Order, Capital investment order enduser documentation

    Can any Guru send me enduser documentation for Internal order of type Capital Investment? Email: [email protected]
    Thank you!

    Hello,
    the little late answer to your question is the table IMZO. It links the investment program / positions to internal orders. I found this thread while searching for my own problem which is quite the same:
    In my WebDynpro for ABAP investment planning tool I'm using the FM BAPI_INTERNALORDER_CREATE to create internal orders as a result of the planning process. This BAPI is similiar to the transaction ko01 except that I can't assign an investment program / position to my internal order (this is also pointed out in the help to the BAPI/FM).
    But how can I assign an investment program / position to my internal order NOT using an ABAP insert/update statement on the table IMZO (which links the internal orders and investment programs/positions).
    Does anybody know a FM or BAPI I could use? I really don't like the idea of a self made insert/update into a sap table...
    Thank you in advance,
    Christian Bracht

  • How to map the user to Responsible Person for Proj/ Capital Investment Prog

    Hi All,
    Could you please help me in mapping the user to Responsible Person for Proj/ Capital Investment Prog.
    Here is the scenario. I am trying to restrict the user to access only WBS under a cost center but not to have complete access to the Cost Center. I in my way to do, I found out that we can create a user name using OPS6 tcode and use the reference number of the user we created in CJ20N, so as only the person who was added in the Responsible Person for Proj/ Capital Investment Prog list will be able to access particular WBS.
    Now my question is, How to map the user which I created using OPS6 tcode to user in user master record. I am not able to map the user, as its taking any random name to add in the list. Could some one please help me in mapping the user created in the list with the user master record.
    Hope I managed to put the question clearly. If you have any queries, please feel free to ask. Appreciate your time and thanks in advance.
    Farooq.

    Hi Stephan,
    Thanks for your time and finding SAP note for me. I got the problem fixed. The solution for the above problem is, When we create a responsible person for the project through OPS6 tcode, we have a column called "Offer User", next to the person responsible. We must add the user name next to it. And we can add only the user name which is present in the user master record.
    It solved my problem, but when I pressed F1 for help in this column, there is nothing mentioned about its mapping or anything.
    Thanks again for the help, Cheers,
    Regards,
    Farooq.

  • Order 23 is not a capital investment measure for Asset accounting(AUC)

    Dear All,
    Help This Error
    For T Code  Ko02 select order for AUC  getting this error
    Order 23 is not a capital investment measure
    Message no. AY097
    Diagnosis
    Object concerned: Order 23 .
    The object is not an investment measure, either because there is no investment profile entered for it, or the indicator "manage asset under construction" is not set in the investment profile.
    System Response
    Processing is not carried out.
    Procedure
    If you want to create assets under construction for the object, then enter an investment profile in the master data for the object.
    Check if the the indicator "manage asset under construction" is set in the definition of the investment profile.
    Replay solution ASAP
    Regards
    Nag
    Edited by: Nagaraju Chagonda on May 24, 2011 1:18 PM
    Edited by: Nagaraju Chagonda on May 24, 2011 1:19 PM

    Hi Nag,
    Please check if correction note 1165656 is valid to your release. It can correct this error.
    Best Regards,
    Vanessa.

  • Creation of Assets for Capital Investment Measure

    Hi,
    Can some please tell me how to create an Asset for Capital Investment Measure.

    Hi,
    First you have to create master data using asset class AuC.
    You have define asset class for Capital Investment Measure (AuC class) in t-code : OAOA. And still in the same t-code (OAOA), you choose "investment Measure" in box "Status of Auc".
    If you choose "Investment Measure", the assets under construction in this asset class can be created solely in relation to capital investment measures (internal orders or WBS elements).  So you cannot create and post in Asset Accounting directly (Example post using t-code : F-90).
    If you use WBS Elements then you can post to the asset for Cap Invest Measure using t-code : CJ8G or CJ88.
    Hope it can help.

  • Capital Investment order settlement

    There are some AUCs created via capital investment orders. But the problem is These AUCs were creted during the time when the Depreciation area is de-activated for the particular class. After that there s GR, IR & Payment all with reference to PO.
    One point tp note, as the AUCs were created when the dep area is in-active, the depreciation tab is in active in the AUC master record. When you are running theorder settlement (KO88), there is an error message saying "NO DEPRECIATION AREA DEFINED FOR THE AUC NO:12345".
    The solution I am able to see as of now is:
    1. Create a new investment order so the new AUC
    2.Reset the clearing (Payment document)
    3. Reverse the IR
    4. Reverse the GR
    5 Change the order reference in account assignment tab in PO
    6. Do the GR
    7. DO the IR
    8. Clear the Vendor Account
    9. Settle the new order
    But not sure how to delete the old AUC, I am able to close the old order in this fashion. But not in a position to delete the AUC. Any idea?
    Also please suggest me if there is any other easier way, because this will take a hell out of time.

    Ananda,
    Transferring all the costs out of the CI Order into a new one with a new AUC attached should automatically zero & deactivate the old AUC.
    Depending on your setup, a journal from old --> new Order should suffice.
    You may then run settlement to the new AUC with Depreciation Areas activated.
    I don't think any of the drastic measures outlined are necessary.

  • Capital Investiment Order

    Hi,
    Can anybody explain me the functionality of Capital Investment order (PM07) .How it can be used in Plant Maintenance.
    Regards,
    Raj.

    Dear Raj
    Capital Investment Order is a type of order used to Track whatever Capital expenditure done in the plant through Plant Maintenance.
    Generally in Plant if I want to Replace Pump with New Pump , Old Machine with New Machine  this is generally done by Capital Amount Allocated . You can do this in PS module by Allocating WBS elements & Settling to WBS Element.
    or
    In PM you can create  PM07 Order type input the resources ( Material & Labor required for Installing) & Settle it to Allocated WBS Element.
    The Main Concern for the Company is that they must know what is Capital expenditure done for a particular duration , So that they can pass this Expenditure Cost to Final Product by Depreciation.
    Regards,

  • Capital Investment Area was posted Depreciations in an incorrect period

    Hi ,
    Capital Investment Area was posted Depreciations in an incorrect period, they skip a period.
    Can you determine if we can reverse those postings so that they can post in the correct period?
    Would appreciate your fastest reply.
    Regards
    Prasad

    All,
    Thanks for your answers, the solution would appear to be that the commitments have been accidentally carried forward into 2010 Fiscal instead of 2009 fiscal.  
    There are no Invoice plans set up on the PO's, thanks for that suggestion though.
    The reversal in KSCF does not work and produces an ST22 error dump on our system.
    SAP note 971411 appears to fix the error so we will implement the note and hopefully be able to reverse out the commitment.
    Thanks to all and if I can assist you FI guys with MM answers I will
    Allen

  • WAAS Application Requests - Process Question

    Non Technical Process Question
    We all have forms we have our users complete when a firewall rule or change is needed.  You may even have a similiar documents for when load balancers or DNS changes are required.  Does anyone have document they can share that outlines what pieces of information are needed for intergrating applications into WAAS?  What about ongoing changes?
    Source, destination and TCP port information is really a very small portion of the what needed to maintain a clean a defined methodolgy within the WAAS manager.  Does anyone have an example or can describe how you collect the initial information to set up WAAS but how do you keep track of changes that may be needed as the application charaterics change or the server farm expands horizontally?
    Thanks - Sam

    Sam,
    the general answer for detailed information on how to configure WAAS for certain applications is described here:
    http://www.cisco.com/en/US/docs/app_ntwk_services/waas/waas/v501/configuration/guide/policy.html
    In general, WAAS comes preconfigured for the most widly used applications in the industry.
    In order to understand, which configuration is necessary for a new application, one needs to understand the basic options WAAS offers.
    These are two options:
    1) Use an Application Optimizer (AO) if you need some dedicated protocol know how. ( e.g. (e)MAPI, CIFS, SSL, HTTP, ICA, to name some)
    2) Generic TCP traffic is optimized using TCP Flow Optimization (TFO), Data Redundancy Elemination (DRE) and Lempe Liv (LZ) compression.
    The in terms of processes, the question is:
    1) Is there a policy preconfigured for the new application?
         a) yes
              If an AO is used, does the AO need configuration? ( example: SSL AO requires certificates)
              Do we have specialities which require further fine tuning? ( Answer is mostly: no, Example: non-standard ports)
         b) no
              You define what you need for the application based on the protocol characteristics.
              If you have defined these characteristics you can choose one of the AOs, or define which of the "generic" options fit the traffic. For example, for traffic that is already compressed, it does not much benefit from LZ, so choosing only TFO and DRE. Another example is traffic that has not much of dublicate data, perhaps it does not benefit a lot from DRE, so you configure TFO only.
    Does that answer your question?
    Thanks,
    chris

  • Question related to my previous "background process" question.

    Hello Folks:
    Can I start a "Notification Service Subscriber" process through the
    normal startup procedure for other servers---i.e. by adding it to the
    config(ubb) file. If so, can I implement the background process as two
    different CORBA servers calling each other asynchronously to accomplish
    the work. Please let me know if there is any other way to accomplish
    what I have stated in the "background process" question.
    Thanks,
    Ram Ramesh
    678-358-3581

    Go to your forum preferences and set the email options.  You may also need to unsubscribe from forums / topics you are currently subscribed to.

  • Capital Investment Progrom - Copy of plan to budget

    Hi All
    I've been asked to copy the Capital investment plan to the Capital Investment Budget as well as do a Capital Investment Plan rollover to the next financial year. Having never done this before, could I please have some pointers on what to do, transactions to use and what pitfalls to lookout for? Unfortunately the person who did this last year has left!!
    Regards Juliet

    You ise T Code-
    IMCCP1 - Transfer Plan to Investment Program Budget
    Mention the IM program details and the Plan version which needs to be copied and set the indicator 'Post budget as supplement or return' as per your business case.
    Use T Code-
    IM64 - Plan/Budget Transfer from Old Investment Program
    Ensure that you've selected the right settings.
    I would suggest you try this in test system and carry them out later in production.
    Regards
    Sreenivas

  • Cj88结转报错:You have not yet settled all items from capital investment measure

    通过cj88把工程成本结转到在建工程时候系统报错
    :You have not yet settled all items from capital investment measures from the previous year.
    我看了下 对应的wbs 2008年的工程成本都没有结转。
    如何才能结转以前年度的工程成本呢
    cj88上面的几个参数 结算期间,记账期间 会计年度分别对应什么意思
    比如我现在要结算2010年8月的工程成本那对应3个栏位就是 08 08 2010
    那如果我要结算2008年工程成本 三个参数应该填什么

    你好
    如果会计年度2008在财务一侧已经关闭的了话,是没有办法我转结2008年以前的工程成本的。这种情况下,只能把报错信息AW624的状态从报错改成警告,然后把以前年度的工程成本转接到当前年度。详细的步骤可以参照SAP note 82514 和 425601.
    希望上面的回答会对你有所帮助。
    George

  • CJ36 -BP - 164 - Capital investment budget exists for & - update not allowe

    Hello Friends,
    We are trying to post supplements using CJ36 for a WBS,but the system giving the error message saying that
    " BP - 164 - Capital investment budget exists for & - update not allowed"
    Please give some idea on this.
    Thanks IN Advance
    Best Reagdrs
    Trupthi

    Hi,
    Even though CJ35 and CJ38 are both transactions to perform budget returns, it is important to know that they are working slightly different:
    a) via txn CJ38 you return money exactly for the WBS elements you indicate an amount for. So if you indicate 1 COP for
       WBS element XX alone, the return is only being carried out for this WBS element. Since this WBS element is
       not (directly) attached to an investment program position, this is not a problem.
    b) via txn CJ35, however, as per system design you return money for the WBS element you indicate  p l u s  for all WBS elements lying on the hierarchical path above, in order to guarantee that the budget remains consistent (= check error free).
       So by indicating 1 COP for WBS element XX, the system  also  tries to return the same amount from the overlying WBS element YYY.
    Since this WBS element, however, i s  attached to investment program position of investment program, the system blocks this posting because this program position forsees budget distribution and thus budgeting is allowed via budget distribution  o n l y  (txn IM52) -  see e.g. F1 help for indicator 'Budg.dist. ovrl' in the master of the investment program position.
    So basically you can say that txns CJ35 and CJ36 are not suitable for projects attached to investment program positions that forsee budget distribution. Please check your transaction IM52.
    Please check if this fits with your scenario.
    Best Regards,
    Vanessa.

  • General Ledger - Revaluation/Translation Process Question

    Application Release Version: 11.5.10.2
    MRC: Not turned on for new entities. (See details below)
    My customer has been using oracle from around 2001 and went through a process at the end of 2008 to setup a new chart of accounts and approx 6 different companies with multiple entities for each across different functional currencies. (The initial setup for these entities was done prior to my joining and I have no supporting documentation on what decisions were made and why.)
    Setup info:
    Set of Books - 'Cumulative Translation Adjustment Account' defined as an 'Owners Equity Account'.
    Revaluation - Gains and Loss accounts using the same account number as 'Cumulative Translation Adjustment Account'. Accounts being revalued are accounts that have outstanding Payables and Receivables balances as well
    as our intercompany accounts that have outstanding balances. (Balances that need to be payed or received.)
    Question:
    My question refers to the revaluation and translation process for the new entites that have a different functional currency from the reporting currency. (All under the same chart of accounts structure.)
    For instance entity1 - Functional Currency = 'CAD' and has 'USD' transactions.
    I understand that at the period end we need to revalue the 'USD' transactions to there 'Current' worth in 'CAD' as exchange rates will fluctuate. But shouldn't the 'Difference', revaluation amounts, be pushed to the Unrealised FX Gains/Loss account, not the 'Cumulative Translation Adjustment Account'. (I think this is normally only used when a company is using MRC?)
    This obviously affects whether the period balance appears on the Balance Sheet or Income Statement report for the consolidated monthly report.
    Also should these 'Revaluation' journals ever be reversed or just left to accumulate?
    Then looking at the 'Translation' process, if value is pushed to the 'Cumulative Translation Adjustment Account' then the balance is translated based on the 'Average' period rate as the account is an 'Owners Equity Account', but this seems wrong for the 'Revaluation' balance to be converted at another rate?
    Any help on this subject will be greatly appreciated.

    Firstly, why would there be any difference between the total of customer/vendor sub-ledger balances and the balance on the reconciliation account(s)?  The posting to the reconciliation account is happening automatically right, when you are posting to a customer/vendor (basing on the reconciliation account assigned in the customer/vendor master)?  And system would not allow direct postings to reconciliation accounts, which eliminates the threat of reconciliation GL account going out of balance as compared to the sub-ledger accounts.