Hi,
Prerequisites: Plan work 260 hours. Constraints on start and finish date. Distribution rule is equal to distribution according to factory calender. For scenario 2) actual work is 100 hours. Remaining work is 160 hours. Duration of activity is 1 year.
Scenario 1) When calculating project cost forecast without any actual cost from time reporting, the cost forecast is distributed over the remaining duration of the activity.
Scenario 2) When calculating project cost forecast with actual cost from time reporting, the cost forecast is planned on the same period as the forecast report is run. We would like this to be done in the same way as in scenario 1 above and distributed according to the factory calendar and not have all of the remaining cost on the last period of the activity.
If someone out there has experience of this issue, we appeciate your advice.
Best Regards ,
Ioannis

Hi Ioannis,
Please see the online document
http://help.sap.com/erp2005_ehp_04/helpdata/EN/c2/1ad778462611d2b4310060
94b9c9be/content.htm                                                    
to see how the internal-processed activity should work in CJ9L.
I do think, the described scenario 2 do not work in that way because the factors you described.  As far as I remember, the following factors are relevant for such case.
1. If the activity is paritally confirmed. What are the actual finish and forecast finish (or remaining duration).
2. Is the forecast work maintained.
3. What is the key date of CJ9L.
Generally there is no logic just to put the remaining costs in the last period, but it can happend that based on the factors above, which uses the last period as remaining time frame.
Kind regards,
Zhenbo

Similar Messages

  • Cost center planning for overhead calculation

    Gurus,
    I have a doubt regarding the cost center planning for overhead calculation.
    My scenario is:
    There is a service cost center from which a certain percentage I want to allocate to the products as overhead. Now while doing so I have created a cost center and a cost element of type 43 (internal activity allocation). This cost element is the base for overhead calculation. Also I have created one cost element of type 41 (overhead rates). I have defined the credit (of cost sheet) with the cost element of type 41 and the cost center as mentioned.
       Now I am facing a problem while planning the cost center with cost element type 43 through KP06.The system is throwing the error message: 'Cost element xxxx can only be used for activity input'. My understanding is we must carry out the planning for the cost center to allocate a certain percentage to the product cost estimate. If I am not allowed to use the cost element of type 43 to plan, what should I use for the planning?
    Request your suggestion.
    Thanks in advance!
    Snigdho.

    Hi
    Since you mentioned catg 43 cost element, I thought you are using Activuty Type
    To apply overhead on the product during CK11N, you need not plan any value on the cost center... The values planned in the cost center can not be used as a BASE in your costing sheet....
    It goes like this
    1. Your cost estimate has BOM + Routing
    2. So, the cost elements that you would see during CK11N, can be broadly classified into 3 types
    a. Primary cost ele - Material Consumption accounts for BOM components
    b. Secondary cost ele (Catg 43) - If you use any actvity type in the routing
    c. Secondary cost ele (Catg 41) - These cost elements are parasites... They need some basis to calculate the overhead value... That basis can be either the (a) or (b) above.....
    I think, what you are planning to do is Plan Primary cost ele in a cost center and trying to use the same as the Basis.. That wont work!
    What you need to do is
    a. PLan the values in the cost center, say, 100,000 USD
    b. Absorb it on the basis of 2.a or 2.b
    If 2.b is not applicable in your case, since you are not using activity types, then 2.a is the Only option left for you
    Hope it is clear....
    Regards
    Ajay M

  • Delete a Cost Forecast version

    All,
    I have a CO 'Cost Forecast' version in a development client. It is only flagged for 'Plan'.
    It has been used for project forecasting (cj9l).
    I want to delete the version. How do I delete the dependent entries before I could delete the version itself?
    Appreciate your help.
    thanks, Mathavan
    Edited by: T.P.R. Mathavan on Apr 22, 2010 4:01 PM

    therefore donot varry about the CE, it is okay latest one is valid for your production
    i hope you got the point.
    reward amd close the thread or come with the question

  • SAP - Cost Center Planning - Version 1

    Dear All
    Recently we have started to use the cost center planning through KP16 under plan version -1
    However we are unable to down the plan data in excel with a cost center break up through KSBP report.
    We are not using any special ledger
    System is showing the following error
    No plan cost line items recorded.
    Message no. KB419
    Diagnosis
    No planned costs line items are written to controlling area DXES in version 1 of fiscal year 2009.
    System Response
    The report cannot be executed.
    Procedure
    Check your selection criteria or activate the line item update function.
    Note
    The line item update function is controlled depending on the application:
    Cost center planning
    Here you can define the update for each version and fiscal year. You can maintain the corresponding indicator (integrated planning) in the version maintenance (settings for the fiscal year).
    This indicator you can either
    set manually when creating a version or
    set later via the menu sequence "Planning -> Planning aids -> Integration active".
    Regards
    Anilkumar

    Hi,
    The impact is that the planning is stored also as line items and the planning is integrated between the CO-PCA components. In SAP words:
    - All available plan records for controlling area/version/fiscal year are posted as line items. The R/3 System posts these line items to the AC interface.
    - Any existing line items in the plan allocation transactions (plan assesment, distribution, or accrual calculation) are posted to the AC interface as well and made available to other components.
    Regards,
    Eli

  • IW32  control data tab cost varaiant actaul and cost varaiant planned field

    Hi Team,
    In my preventive maintenance order , in control data tab cost varaiant actaul and cost varaiant planned field is not avialble it is hidden , but comming in PM01 order tye.
    Tcode OIAN for preventive maint. order type
    Cstg variant actual CAUFVD-KLVARI             
    Cstg variant planned CAUFVD-KLVARP
    Input indicator is selected.
    What may be the reason.
    Thanks in advance.

    Hello,
    I already ran the report Z_FILL_COSTING_VARIANTS and after that I will go to calculate costs in the order but nothing. I this order I already had confirmations but when running the cost calculation the system doesn't made the calculation.
    Can you help me?

  • Sales Pricing without Inquiry using detailed Cost element Planning

    Deal All,
    I need to use use Sales Pricing without Customer Inquiry to Genrate Quatation from Project.
    In my project client is asking to use deatiles cost element planning for same. So, let me know
    Weather its possible to use Detailed cost element planning for doing Sales pricing in DP82
    or Do we need to use ECP only to do Sales Pricing??
    Also, let me know if there will be any change in RA method also.
    regards,
    Atul

    Hi Atul,
    You can use any of the cost planning method (i.e Details cost element planning, ECP or Network Costing) to create Quotation using DIP Profile.
    Coming to the second point..any effect on RA calculation..This Quotation creation process is no where effects RA calculation.
    basically for creating Quotation usign DIP Profile, there should be cost element wise planned cost required.
    Hope this clears you...
    regards,
    Hari.

  • Cost forecast and project stock

    Dear all,
    in our setup, we are using non valuated project stock. However, the 1st project to buy a component has to pay for it. Therefore, we activated the "Planification" flag in the network type (OPSC).
    As a consequence, planned costs from network orders append the WBS element planned costs but not the assigned values.
    We would like now to use cost forecast. It means we have to assign values which is exactly what we disabled by our previous config.
    We are looking for a way to raise assigned values and roll up planned costs for project stock materials.
    I tried to have a look in the Item Category setup but so far, I did not find anything.
    Would anyone have an idea?
    Thanks,
    Thibault

    Hi
    thank you for your reply.
    OPUV and OPSV are already configured as per your details.
    However, we needed to tick the "Planification" in OPSC in order to have planned cost for Project Stock materials.
    We are using non valuated project stock and it's the only way we found to roll up planned costs for those materials...

  • Calculated Std cost est vs Material Master Std cost price

    Hi all,
    Why will a calculated std cost est not be equal to my standard price in my costing 2 view on the material master? For ex:
    I calc a price for material 1 = R11.50
    The price in the material master (MBEW-STPRS) is R10.80.
    I can see that the difference is some activities for one of the operations in my production process, but it does not show on my material master.
    Can anyone suggest a solution?
    Thanks,
    Hein

    The planned price can be copied from CO-PC, or entered manually depending on your settings in CO. If you open the standard material cost and release it the two price of planning price and standard price will be same.
    As to the price of PO that is another price, actual cost happened.
    FYI.
    If no marked standard cost estimate exists, you can enter a price in this field manually. This makes it possible for the system to find a price when costing an assembly via the valuation strategy, even if no standard cost estimate with status KA (correct) exists for a BOM material (such as a raw material or semifinished product).
    If you subsequently create and flag a cost estimate for this material, the results of this cost estimate are adopted as the future planned price, and the manual entry overwritten. It can then no longer be changed. Therefore, you are recommended to use the Planned price 1, Planned price 2, and Planned price 3 fields to maintain the planned prices of material components and to define them in the valuation strategy.

  • How to accomplish Revenue and Cost forecasting in Oracle?

    We are implementing Oracle Rel 11.5.10. and have a specific business requirement for Revenue and Cost Forecasting.
    We have Projects integrated with OM using custom extensions (We are not using Project Manufacturing). Revenue is based on scheduled shipment dates and Cost is based on PO Promise Dates. Both Revenue and Cost are forecasted for 2 quarters and are rolled up on revenue category level. When Scheduled shipment date changes it is required to automatically forecast the revenue in the period scheduled ship date falls into. We understand that out of the box functionality does not support roll up of forecast at revenue category level which leads to displaying budgets, commitments and atuals in different lines. Has any one done this in any of there client engagements? Can anyone explain how Revenue and Cost forecasting is done in a High tech Network Equipment manufacturer which usies Projects.
    Any help will be highly appreciated.
    Thanks in advance
    Amit

    Hi
    My understanding is that your entire solution is based on custom proceses.
    You might have a program that reads the scheduled shipment date from OM and generate budget lines for revenue.
    You might have a program that reads the PO Promise date from Purchasing, and generate budget lines for costs.
    You could integrate those sources and generate a new version of forecast every time you need to update your plans in Oracle Projects.
    Dina

  • Monthly Cost Forecast In SAP PS

    Hello All
    Is it possible to show monthly cost forecast in SAP PS?
    If yes can you please explain how to do it,
    Thanks & Regards
    Shailesh

    Hi,
    For Forecast, view Report S_ALR_87013540. On leftside click on Period/Year.
    For Plan & Actual cost for each month, view reports S_ALR_87100186 & S_ALR_87100185
    Regards,
    Kabir

  • Capturing Plant & machinery Cost while planning

    Please advice, how to capture plant and machinery cost while planning in PS on activity basis.

    You can define your plant-machinery as 'work center' which is helping you manufacture the goods required in the project, you should use thse plant-machinery as a work center. You can define the operating rate for this plant-machinery. when you are suing this plant-machinery as work cneter in network activity, the planned costs will be calculated. Also when you post the activity confirmation, actual costs will be posted on network activity.
    For detailed configuration take help of CO consultant on setting this up.
    Regards,
    Mahendra Dighe

  • Error while uploading cost element planning data into KP06 transaction

    Hi,
    I am facing the below error while uploading the Cost Element Planning excel file in KP06 transaction code. Please help me in fix this issue.
    We are trying to enter a budget upload using Transaction code: KP06. We get the following message errors  when we do this. It seems revenue accounts cannot be entered using cost centers. Question, how should these accounts be added? Kindly help me how to add Revenue cost elements to this planning?
    Error accured when generating data for the planning processor
    Messange no.K9400
    Revenue element 451000 can not be planned on cost center 9720
    Thanks
    Kishore

    The cost element which have  category 01 only can be planned in the Kp06.
    Regards
    Ranjan

  • Retraction Cost Center Plan Data into SAP R/3

    Hi All,
    I am working on Integrated Planning and we have a requirement to retract the Cost Center Plan data to SAP R/3. Can anyone tell me how to do it in SAP BI-IP envirinment.
    Regards
    keyrun

    Hi Keyrun:
    Please refer to slide 7 of document below.
    "SAP NetWeaver 7.0 Data Retraction in BI Integrated Planning"
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/30af46fb-eb4f-2a10-4899-9167af035742?quicklink=index&overridelayout=true
    >Online documentation: http://help.sap.com/saphelp_sem60ep1/helpdata/en/99/97157967e3440a94d199538959cd0b/frameset.htm
    >See SAP Note 525543 for additional documentation on field mapping.
    Regards,
    Francisco Milán.
    Edited by: Francisco Milan on Jun 22, 2010 8:13 PM

  • Use of forecast planning function in Integrated planning

    Hai ,
    Can I Know What is the use forecast planning function in Integrated planning.
    Give me One Example.
    Please tell What i hv to select in aggregation level, Filter, and Planning function for doing forecast.
    Regards
    Kishore.

    Hi,
    Filter is indeed used in IP similar to how planning package was used in BPS. There really is no difference 'conceptually'.
    What you have seen is the different options IP offers compared to BPS regarding planning function execution. You can execute planning function directly or using a planning sequence in an application (although in planning modeler, its only a planning sequence that can be executed, for eg., for testing purpose).
    If you just execute a planning function without specifying any restriction, it will operate on the entire set of planning data. Whether its a planning sequence or planning function, the data it operates on can be restricted by binding the various characteristics (or variables) using various DPs in the application. What kind of dynamic selection are you looking at?
    You can see following links if you have not read them already -
    http://help.sap.com/saphelp_nw70/helpdata/en/43/f0f8dc73b56bede10000000a11466f/content.htm
    http://help.sap.com/saphelp_nw70/helpdata/en/44/33a31fd463060ce10000000a155369/content.htm
    http://help.sap.com/saphelp_nw70/helpdata/en/43/f0f92373b56bede10000000a11466f/content.htm
    These are for WAD; you can find similar links for the BI Analyser.

  • Service Order Planned Costs and Cost Center Planned Line Items

    Experts,
    I am curious of Service Order Planned costs, and whether or not these planned costs are being posted to the Cost Center linked to the Service Order Operation's work center.
    I am a but puzzled as I don't see any planned costs from any Service Order Operation in a cost center linked to the Operations work center, when reviewing "Cost Centers: Plan Line Items" report.
    BR,
    Cenk

    The planned costs were input in one of the Service Order operations as planned hours. There is a column for it in the operations list. The amount of hours have incurred a planned cost on the Service Order header.
    I simply assumed that this cost would be credited to the Cost Center linked to the operation's Work Center. But that is obviously not the case. I am not familiar with the PLICC field and the functionality it provides.
    Thanks!

Maybe you are looking for

  • PO screen custom fields are not in correct order

    Hi Experts, After creating Shopping cart and purchase order successfully created. Added my custom fields for PO structure INCL_EEW_PD_ITEM_CSD_PO fields are visible in PO screen automatically with out adding my custom fields in PO layout /SAPSRM/WDC_

  • Data Not coming Properly for 0HR_PA_OS_1 Data Source?

    Hi Experts, I am trying to load data to 0PAOS_C01 using 0HR_PA_OS_1 data source. For field 0POS_OCCVAC key figure i am not getting any data from Data Source. I checked in RSA3 for 0HR_PA_OS_1 data source and  in that it is not populating data for fil

  • Not getting the complete output in the crontab script

    Hi All, I am running a script to find the CPU and memory utilization of the Oracle 10g server. Script name is atul.sh. When i run this script then it gives the desired output as mentioned below: bash-3.00$ cat ./SCRIPTS/atul.sh *A=`date| cut -d" " -f

  • Working with video clips located on an external firewire drive

    This is surely a simple question that I am hoping has a simple answer. I have an external drive mounted to my MacBook Pro and this is where I have 300+ GB of dv formatted clips stored. How do I add clips from this drive to an iMovie project without h

  • BP ROLE ACCOUNT _ CRMACC

    Hi , I have seen a new BP ROLE Account(Standard role not enhanced role) , it has same views and data sets as Sold to Party and also the Standard assignment for BP role Account is Sold to Party. Now my question is what is difference between both Accou