Inspection at operation level

Hi frds,
I have created a routing with 2 operations. My clinet wants that once the 1st
operation is confirmed a inspection lot has to be created and unless that lot is cleared they should not be able to confirm the 2nd operation.
Kindly guide me the steps that needs to done to do this right from the inspection type to be maintained..etc.
Rajnish

Hi,
1. In mm02, choose qm view.
Choose QM proc then click inspn setup tab.
Choose 03 for halb/fert
04 for final inspn (after prodn)
01 for roh. & click active.
2. Qi01 - create info record
3. In the routing choose first operation & choose inspn characteristics & choose eg.hardness & then sample as (eg) fixed sample.
4.md61,md02,md04
When you confirm first operation inspn lot will be created.
5.In qa02 you can see the details.
6.qe51n results recording. lot origin eg;01
mtrl no:xyz
enter the sample as 1 it should turn green/
7.QA11 record usage
Ud code accept.
enter eg: 100 nos in unrestricted use & save
Regards,
Senthilkumar

Similar Messages

  • In process quality inspection in operation of a process order

    Hi,
    PP-PI inprocess quality inspection at operation level
    I am creating a process order having two operation. the first is quality inspection (inprocess inspection) & last is related to consumption of some materials.
    The control key in operations are pi02,pi03(miles stone confirmation). i am using insp type 03 in material master 
    user needs  insp. happen first then consumption of material.
    my question is
    1.when operation first get triggered  quality lot generated i enter RR & do UD.but here i can not see the insp lot stock as subscreen. why? then how can i block defect qty in block stock?
    2.how can i consume material in the same quality operation? 
    With Regards,
    Kareena

    Hi Kareena,
    I think the thread is going in other direction. You were asking for some solution to mentioned the consumption.............
    That can be taken care..........
    For 03 - "In process inspection" lot as yield confirmation by activating the STD function of SAP as I have mentioned in my last post.
    For 04 - "Inspection against GR form Production" lot, by stock posting.
    For any lot you can do customization in "EXIT_SAPLQEEM_011", to post the material consumption at each MIC/Operation valuation.
    But now the entire scenario what you are asking is bit confusing.
    You wrote
    I think for process order,
    quality activity confirmation we are talking
    & for this i have not maintained inspection
    point or inspection point identification.
    i am doing RR from qe11.
    It seems you we are talking about 03 type inspection lot. that you can relate with the option I have mentioned in the beginning of this reply.
    in my inspection plan for the material
    i have maintained 5 different characterstics
    in that row i can not see the sampling
    procedure,base unit of measure,
    base quantity all these field are gray in color
    i have defined sampling procedure also
    i have not maintained inspection point identification.
    Where you have mentioned these 5MICs?
    If it is inspection plan, then it will go with 04 Type.
    If it is Master Recipe/Routing, then it will go with 03 Type.
    Now the other point you wrote the MIC Line item have the fields GREY for Sampling Procedure,&...........&.......So to activate them,
    Select the line item for MIC, click on the Control Indicator (Sampling Procedure) and then you will be able to assign the Sampling Procedure to MIC.
    The fields "Inspect" & "Inspected" are related with the "Insp. Scope" with the MIC. The scope is define at the Control indicators for the MICs (On Page2 for the Indicators). There are four Radio Buttons to define the Inspection Scope.
    Scope not Fixed
    If you set this indicator, the number of inspected units is defined by the user for results recording.
    This number does not have to agree with the precalculated number of inspected units.
    E.g. If the the sample size for that particular MIC is not fixed ever and you will supposed to enter it at the time of RR you should define this indicator and the field will open for entry in QE11.
    Fixed Scope
    If you set this indicator, the number of inspected units must correspond
    to the precalculated number of units to be inspected for results
    recording.
    The system can perform a valuation for the inspection characteristic based on the number of nonconforming units or the number of defects in the sample.
    And the field will be GREY, non - modifiable.
    Similarly the larger and smaller scopes work.
    Best Regards,
    Shyamal

  • In process inspection - Rejection Booking at operations level

    Hi All,
    Need some help regarding inporcess inspection.
    As we aware about '03' insp type is not stock relevant
    The requirement is , i having operations are like 0010 ,0020 ,0030 ,0040,0050 in Production order in Routing
    Now while operation wise confirmation i want to book the rejection and that needs to get effect on further operation confirmation.
    For example : Suppose I have confirmed 50 TON against operation 0020 , hence at the time of confirmation 0020 i want to book the rejection 2 TON
    Hence while confirming 0030 system should not allow to cofirm 50 TON , system should allow to confirm only 48 TON through CO11N and Some where that rejection has to be display in report.
    Is there any provision in standard to enter rejection at operations level.
    Stock posting not required , Only qty tracking required like operation wise confirmation.
    Please advise to make this scenario success.
    Thanks,
    Abhishek

    Hi Abhishake,
    As in inspection type 03 lot you dont have stock posting option, you can scrap the rejected material operation wise in CO11N at the time of confirmation (Mov Type 551).
    As scraped material will no more in system, you can also look forward for bi-product assignment in bom if you don't want to go with first option.
    Also you can check for early lot creation if can solve the purpose, as in this case you will get inspection lot of inspection type 04 at the time of release of production order and stock will be adde to quality inspection as you do confirmations operation wise.
    Regards/Rohit

  • Error in operation level result recording

    Hi,
    I need held; result recording of inspection type =03 (operation level Quality inspection)
    A product manufacture via three operations (10, 20, 30)
    All operation quality inspection active let operation no-10, all products reject and confirm as rework.
    Next operation level quality record is done but confirmation not allow Reason is operation -10, rework quantity, (Actual quantity is more than planned quantity)
    How to add the quantity after reworks for next operation quality inspection?
    Pl helps me finding the solution.

    Hi,
    As per your more clearence , As per Example  production order Quanity =1, passes 3 operation10,20,30
    Operation=10 require rework as per quality ,
    Operation =20 system raise the error message = Operation =10 rework .
    If want to operation =10 ok Quantity =1 then system raise error messges =Actual quanity more than planned Quanitity
    ( 1 Rework + 1 Ok ) .
    Supose rework order create and confirm then next 20 & 30 operation how complete .
    Real scenerio :- Rework on operation =10 then again Quality check then goes to 20 operation Quality check pass / Rework if rework then again quality pass then goes to next operation level
    I hope under stand my problem
    Need help- please

  • Mass change for QM at operation level in routing

    Dear Experts,
    I have to carry out mass change for Quality Management at operation level in routing. The steps that I am carrying out for an individual record are as follows.
    1.     CA02
    2.     Inspection point 100 is maintained at header level
    3.     Go to operation level
    4.     At operation level work center and control key have been maintained
    5.     Double click on operation
    6.     When I scroll down here I go to Quality Management: Inspection Points view.
    7.     There by default in Insp.pointCompletion system shows the option as u201CQuantity, valuation (production) and radio button selected default indicates u201CQty-relatedu201D
    8.     I want to change these options as only u201CValuationu201D and u201CNo relationu201D respectively
    My queries are,
    1.     Is there any T-code available to carry out these changes in mass?
    2.     Is it possible to do this without any Z development?
    I am doubtful about using LSMW here. I would be highly grateful to you if someone can help me step by step.
    Thanking you,
    Anand Rao

    Hi Sujit,
    Thanks for your reply!
    I tried CWBQM. Unfortunately could not succeed. I think may not be feasible through CWBQM.
    But I came across T-Code CEWB . There I opted "SAP_OPERATION" as working area and it worked. Its quite useful T-Code.
    Thanks again for your input.
    Regards,
    Anand Rao

  • UD at operation level

    Hi,
    Is there any possibility in standard SAP for UD to be given in in-process inspection at each operation level of production?
    Please answer.

    You can use the functionality Operatoin Complete.  This is available in 6.0, maybe a version earlier.  Can't remember when it came in.  You'll find the config set up under,
    QM-->Quality Inspection >Resutls Recording>Make Settings for Operatoin Complete.
    It will allow you to assign the selected set of UD codes to the inspection type/plant combination.
    This functionality has not integrated functions in SAP at this time and is primarily information only.  But you could use user exits at various points and custom programming to check that operations are complete before performing other actions in the system.
    FF

  • Authorization on operation level

    Dear Gurus,
    I have a case that in my inspection lot...there are two operations: chemical and microbiology
    Each operation has a user responsible for it, is there a way to prevent a user from recording results in the other user's operation.
    Regards,
    MaX

    Inspection lot autherization has objects like Inspection type ,plant & material.
    On operation level control is not possible.
    At the max you can explore the concept of Digital signature for result recording !!

  • Standard Report for missing parts at production order operation level?

    Hi PP Gurus,
                We have standard report for missing parts at production orders level.
    For our client, they need a report for missing parts analysis at production order operation level. Do we have any such standard report in the SAP?
    Please help.
    Thanks,
    Reddy.

    Hi Arvind,
          Thanks for for your response.
    1. List: Components,  Layout: Standard layout          set the Missing part
           It shows the component requirement/withdrawn  quantity for each operation of production order. It is not showing the commit quantity.
    2. List: Components,  Layout: Pick list          set the Missing part
           It shows the component requirement/withdrawn  quantity for each production order.
    3. List: Components,  Layout: Missing Parts List-Material View          set the Missing part
           It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
    4. List: Components,  Layout: Missing Parts List-Order View          set the Missing part
           It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
          We are unable to get the solution from all these 1 to 4 reports from COOIS.
    Do we have any option to change the existing layout (ex: 3 ) to get the commit quantity for operation with missing parts indicator?
    If avilable, what is the procedure to be followed?
    Thanks,
    Reddy.

  • PM: change all Orders from sub-operation to operation level

    Hi Folks,
    I've a requirement to change all PM-Orders from Operation-SubOperation to only Operation Level.
    Example:
    Op SubOp --> New Op   (no subOp)
    10__10__-->____10
    10__11__-->____11
    10__12__-->____12
    10__13__-->____13
    10__14__-->____14
    20__10__-->____20
    20__11__-->____21
    Does someone here know, how I can make do this in an easy and save way?
    The only way I see is to make an own report with calling BAPI BAPI_ALM_ORDER_MAINTAIN.
    Have someone another solution
    - SAP-Standard-Report?
    - LSMW?
    Regards

    Hi Raghu,
    Many Thanks for your quick reply.
    Okay ... no LSMW.
    And also no Standard-Reports?
    Do you think, making my own program is the best way?
    Regards,
    Daniel

  • User status at operation level

    Hi,
    I have created one user status profile and attached in order type. In this profile I have included Operation and Order header as an "Allowed object type"
    My problem is when I am changing  user status at order level , it is not getting changed automatically at operation level.
    Pls suggest me the solution.
    Thanks

    Hi,
    I dont think it is possible .
    A suggestion not sure if it works .
    Assign user status profile operation wise and then have some development to check the operation status and
    then update production order status with same user status you mentioned in operation.
    FM: STATUS_CHANGE_EXTERN will help you to change the user status of order.
    Regards,
    Vishal

  • BAPI to change data at operation level

    Hi,
    I have this requirement:
    I need to change data at operation level, more particularly Person No (PERNR) by using a BAPI.
    Is there any BAPI - in which I can pass the basic data (say Order data and Operation data) and change the PERNR for it.
    The name of the BAPI and its usage will help.
    Ankur

    Hello,
    Assuming you are talking about maintenance or service orders, you can use BAPI_ALM_ORDER_MAINTAIN. See function module documentation from SE37. The structure BAPI_ALM_ORDER_OPERATION contains PERS_NO field.
    -Paul
    Please use Enterprise Asset Management (EAM) forum for PM/CS specific topics
    Enterprise Asset Management (SAP EAM)

  • Cannot attach documents at order operation level in PM order.

    Hi,
    We have recently upgraded to EHP6 and I have activated the EAM business functions including LOG_EAM_CI_6. In my PM work order, on the Additional Data tab, I can see the "Document Assignment" section at the bottom. Here I attach an existing document and choose Assign to Order. Then I attach another existing document and choose Assign to Operation (0010). After saving the order if I go back into it (IW32/IW33). the document assigned to order header is still there but the document attached to the operation disappears.
    I have defined the document type that I am assigning at header level and operation level in Customizing for Cross-Application Components under Document Management --> Control Data --> Define Document Types. I have also specified in Customizing that the assignment to objects PMAUFK (order) and/or PMAFVC (operation) is allowed for the document type of those documents.
    Can someone please advise what's wrong here ? I have to attach/assign docs to operations.
    Thanks,
    Sandy

    Hi Sandy
    Can you please make sure two things:
    1) IMG --> DMS --> Control Data --> Define Document Types --> Select Doc Type ---> Define Object Links. It must be something similar to this one. Without entering CREATE DOCUMENT settings, you may not be allowed to attach a document. That might be causing the issue. If you do not want from within IW31, someone is creating documents then make sure this setting has value =2.
    One more possible reason for this is 1:n field in this same setting. If 1:n is not selected, please read the help for that field and make sure the uniqueness of your document attachment to objects.
    2) IMG --> DMS --> Control Data --> Maintain Screen for Object Link
    For this one make sure that you have a screen entry for PMAUFK and PMAFVC.
    Now if attachment does not work, try creating a document and let us know what is the error message.
    And do you know that there is another way of attaching documents to the operation which is attaching them as PRT. Just select the operation, click on PRT button and select document and attach it.
    I hope this will help.
    Regards
    Savas
    Message was edited by: Savas Yazici

  • Printing the Pick List at operation level

    Hi all,
    Is  it possible to Print the Pick List at operation level.
    Components are assigned  to each operations and release of  production order takes place at operational level. Once operation is released then only relavent component assigned to that particular operation should come in pick list.
    Thanks in advance for your time and efforts.
    Regards,
    Siva
    Edited by: Siva Kumar M on May 19, 2008 3:40 PM

    Hi ,
    System will not select the Opertaion which has status CRTD by default.
    For further selection please try with below settings. ,
    Profile = std profile
    Production Order Number,
    Selection at Operation level
    System status = CRTD  and Actiavte Excl .check box.
    Now system will display the pick list for  released operation and it`s component only 
    Please check, Reward if it is useful.
    Pradeep
    Edited by: Pradeep Kumar on May 19, 2008 3:45 PM

  • Release of Production Order at operation level

    Dear Experts,
    Production order to be released at operation level automatically one by one, after confirmation of operation.
    Let us suppose
    Op 10 ...... 10 Confirmed
    Op 20 ...... 10 Confirmed
    then in the Op 30 ..... 4 Qunatity to be released automatically once Operation 20 is confirmaed.
    Please give your valuble inputs
    regards
    Ram Kumar

    Dear Experts,
    Production order to be released at operation level automatically one by one, after confirmation of operation.
    Let us suppose
    Op 10 ...... 10 Confirmed
    Op 20 ...... 10 Confirmed
    then in the Op 30 ..... 4 Quantity to be released automatically once Operation 20 is confirmed.
    How to create trigger point for this?
    Can anybody give clear idea, what all the fields I need to maintain ?
    regards
    Ram Kumar

  • FM/BAPI to update Production Order at Operation Level

    Hi Friends,
    Can any one help me in this issue.
    My rek is, needs to update Production Order Sequence Number(AFVC-CY_SEQNRV) at operation level.
    There are some Production Orders under one Project.User is updating theSequence Numberfor the first order in that group (TCode CO02),at the time of save remaining Orders in that group needs to be updated with the same Sequence Number.
    Please provide me with FM/BAPI(operation level not at header level)
    Points Rewarded,
    Thanks in advance,
    PRBode.

    Prathap,
    Have you tried using the Bapi :  BAPI_PP_TIMETICKET
    This would confirm at operation level..
    Hope it is useful.
    Regards
    Ram

Maybe you are looking for

  • Can I use my iMAC as a tape recorder?

    I would like to record my voice, reading a book, and then download it to my ipod.  Nothing fancy...just my voice. 

  • A tutorial needed for...

    I searched the net and found plenty of as2 tutorials for making a car racing game but none for as3?? anyone know of any good tutorials of such?? thank you

  • Email stops synching after 15 minutes (when it locks the screen). Any thoughts?

    I got the Droid 2 yesterday.  Email account (syncs to corporate email) works fine until the device goes to sleep (or what ever it does after 15 minutes that locks the screen then you have to enter a PIN to wake it up again).  Even after entering the

  • BEx QUERY DESIGNER AND QUERY ANALYZER

    HI!!! I want to learn to use the BEx Query Designer and the Query Analyzer, someone can help me with link, manuals, tutorials, cookbooks, everything about this? Thanks and regards

  • Creating timer in forms

    I have a form where the user prints their schedules. This form never closes, I mean no exit. It is open 24/7. I want to populate the data, I mean execute query and get data as the schedule_changes table gets data with various forms. Is there a way to