Manual Budget Planning with Budget Control System

Hi Friends,
The below scenario i have found in Periodic/Closing Operations:                                        
What is the purpose of Manual Budget Planning with Budget Control System
Can anybody provide the link or document with configuration for above scenario
Thanks
Venkat
Edited by: venkata raju khottari on Feb 14, 2009 2:52 PM

Dear venkata raju khottari,
Budget control is one part of Project System.  Normally we have two types of Budgets one Budget for CAPEX and Budget for Over Head expnes.  Max companies PS will take care by the Budgets.  If u need any information let me know.
thanqu
raj

Similar Messages

  • How to execute Script in Test Plan with two different System Data Container

    Dear members,
    I have a requirement.
    I need to execute one Test Config in a Test Plan with one System Data Container and another Test Config in a Test plan with another SDC.
    How to achieve this ?
    Kind regards,
    Pradeep
    Edited by: Pradeep Singh Rawat on Mar 23, 2011 7:10 AM

    >
    Pradeep Singh Rawat wrote:
    > I need to execute one Test Config in a Test Plan with one System Data Container and another Test Config in a Test plan with another SDC. How to achieve this ?
    Currently it is not possible, to maintain more than one SDC on a test plan.
    A workaround is, to maintain one SDC on a test plan and specify no target system direct in a test plan. If you maintain then your  two systems in one SDC, you can specifiy each target system in the test configuration, where it is needed.
    Here the example:
    test plan:
    systemdata container: SDC_ALL
    target system: <empty>
    test config 1:
    systemdata container:
    target system: CRM
    test config 2:
    systemdata container:
    target system: ERP
    systemdata container: SDC_ALL
    target system: CRM -> rfc 1
    target system: ERP -> rfc 2
    Kind regards,
    Christoph

  • RoboHelp Server 8 - compatible with "source control system" ?

    Greetings,
    Using RoboHelp Server 8, is it possible to add in a "source control system," such as Subversion or Bazaar, to track updates and versions? Is there another "source control system" alternative?
    Also, is there a hosted RoboHelp Server 8 option, where Adobe provides, sets up and maintains the server hosting the RH?

    Hi again
    Well, sort of. Note that basic WebHelp and FlashHelp are capable of being merged. This allows a search to occur across the merged set. As I said earlier, merging can be automatically enabled or disabled in the RoboHelp Server. So theoretically, you could turn off merging at the server. Then you could publish ten projects. Perhaps you want two of those projects to be isolated islands where search only occurs in them individually. But for the other eight, you want a search to be performed across the eight projects. You could create a standard merge in this case and publish to the RoboHelp Server and have a search work across the eight merged files. You could also open each of the eight individually and search only that file set.
    At least that's my understanding of how it works. Perhaps fellow Adobe Community Professional and fellow Adobe Certified Instructor John Daigle will pop in and offer some clarification if I've muddied the waters.
    Cheers... Rick
    Helpful and Handy Links
    RoboHelp Wish Form/Bug Reporting Form
    Begin learning RoboHelp HTML 7 or 8 within the day - $24.95!
    Adobe Certified RoboHelp HTML Training
    SorcerStone Blog
    RoboHelp eBooks

  • Wireless Control System Error Msgs.

    Hi,
    I have a problem with Wireless Control System (WCS v7)  WCS-STANDARD-K9 and installed with WCS-PLUS-100 (installed two licenses) so total licensed installed is for 200 Acesspoint's in WCS. I have 149 AP's connected to WCS and its shows error " System is in voilation of license. The number of APs (149) registered is greater than licensed (0). Please go to the license center under the Administation Menu to add additional WCS licenses.
    What would be the reason for this error,? Thanks

    If you go to the license center in WCS, do you see a total of 200 AP support. You need to make sure you have a base license before you add additional plus license. I had an issue before, where I added a whole bunch of plus license after I installed a 250 base. I had 400+ APs and ran into the same issue but I had 250 base. Well I forgot to add the other 250 base so I had to remove all the plus license before I could add the other 250 base. Then I had to add all those plus license after that. The license center will tell you exactly how many APs it will support. From what you posted, it looks like you have 0.
    Sent from Cisco Technical Support iPhone App

  • SRM 7.0 for Public Sector integrated with FM (Budget Control System)

    Hello!
    I'm starting an implementation project of ERP 6.0 and SRM 7.0 for Public Sector.
    It would be necesary the integration not only SRM with ERP but with FM (Fund Management), with BCS (Budget Control System) specifically.
    Is it possible? has anyone experience on it?
    Thks so much in advance and best regards!
    Marcela.-

    Hi,
    Certainly... If you have FM implemented in your project, you will have to make integration with SRM.
    I did it some 3 years ago and it was quite problematic (a lot of notes were created by SAP on this matter, also as initiative from our project), but since then, I assume, it should not pose specific problems.
    Regards,
    Eli

  • Funds Management with Budget Control System (BCS) submodule

    hi sap gurus
    can any one give me the details for the
    Funds Management with Budget Control System (BCS) submodule   
    if any material pls send to my mail id : [email protected]
    its very urgent pls
    thank you

    Hi,
    Try executing FMAVCREINIT report and check if the problem persists.
    Regards,
    Eli

  • Budgeting and control system

    friends,
    we implemented fi, co, mm, sd, pp and project systems. we want to implement budgeting and control system. what is the exact flow of BCS in between these modules,
    regards,

    Hi,
    Prepare Funds Management Installation
    When implementing the Funds Management Government component, you should take care to carry out the individual steps in a particular order. You enter the required preconfigurations and functions at different points in the SAP System.
    So when implementing Funds Management, you should observe the following sequence:
    1. You use the "Enterprise Structure" to create company codes, FM areas, and controlling areas. For more information, see the Enterprise structure IMG in sections:
    a) "Define, Copy, Delete, Check Company Code"
    b) "Maintain FM Area"
    c) "Define, Copy, Delete, Check Controlling Area"
    2. You then assign an FM area to each company code and controlling area relevant to Funds Management.
    For more information, see sections:
    a) Assign company code to FM area
    b) Assign controlling area to FM area
    3. You create your G/L accounts in the General Ledger Accounting menu. For more information, read the chapter: Create G/L accounts in the G/L accounting IMG (FI-GL) under G/L account master records.
    4. Use Financial Accounting customizing to maintain the field status definition groups. These determine which fields in the account can accept input, must be maintained, or are hidden, when you are entering business transactions. For more information, read: "Maintain field status variants" in the Financial Accounting Basic Settings.
    Note that the additional account assignments "Commitment item", "Funds center" and "Fund" will only accept input if you mark the relevant fields as required or optional entries. This applies, however, only to G/L accounts whose commitment items are assigned with the 30 such as a revenue account. G/L accounts whose commitment items are assigned with a transaction other than 30 should have the error hidden.
    If you want to reference earmarked funds when posting a payment, you must define the additional account assignment "Earmarked funds" as a required or optional entry.
    5. Likewise, for Materials Management purchase requisition and purchase order postings which do not go into stock, you must flag the "Commitment item", "Funds center" and "Fund" fields as required or optional entries in order to be able to make entries in them. You can find more information in the Purchasing IMG in section "Maintain account assignment types" .
    6. If you want to integrate inventory management with Funds Management, there are different ways of controlling this, depending on the warehouse concept you chose. For more information, go to the Funds Management IMG and read sections Make Other Settings and Integration with Inventory Management.
    7. If you want to integrate Assets Accounting, you must go to the Funds Management implementation guide and flag as budget relevant the transaction types for the individual transactions (acquisitions and retirements). You can find more information in the IMG Funds Management Government in the section Flag Transaction Types as Budget Relevant.
    8. If you want to integrate Payroll Accounting with Funds Management, you must define funds centers and funds for the individual Infotypes. For more information, see the Funds Management IMG Funds Management Government in the section "Define Start Date for HR Integration (Without HR Commitments Scenario 2)".
    9. If you want to integrate Travel Management with Funds Management, the "funds center", "commitment item" and "fund" fields must be ready to accept input when you post in Travel Expense Accounting. You enter these settings in the Travel Management IMG Dialogue and settlement control -> Screen layout for trip data input -> Set up variable construction for account assignment objects.
    10. You switch to the Funds Management application menu, create your master data (commitment items, funds centers and funds) and then define your account assignment derivation.
    For more information on account assignment derivation in Funds Management, see component Funds Management (PSM-FM) under Account Assignment Derivation as well as section Define Account Assignment Derivation.
    For more information on creating master data, see the component Master data in the componentFunds Management (PSM-FM).
    11. You can then subsequently make the remaining settings via the Funds Management implementation guide. For more information, read the following chapters.
    Further notes
    The Funds Management application component can not be used simultaneously with the components Cash Budget Management and/or Project Cash Management if you use year-dependent master data in Funds Management.
    If you want to use Funds Management with Cash Budget Management and/or Project Cash Management you must note that Cash Budget Management and Project Cash Management only process 10 character commitment items.
    Regards,
    Eli

  • Budgeting control system

    Hi Experts,
    We are using ECC6, but would like to know if there is an available transaction code or program in the system that can  provide for preventive budgeting control system where the accounts are validated on-line with the available balance
    Thanks.

    Hi Ajay,
    We are uploading the budget in 7KEX per GL account per profit / cost center
    Thanks.

  • Budget and budget control system

    what is the differnce between budget and budget control system. is it possible in sap each po (purchase order) wise budget.if its possible in sap please provide config steps.

    Hi, guy
    In SAP, we can use IO, PS, FM to make the budget. The budget control system is a sub-module of FM. If you want to get some config step, please kindly refer SAP Best Practises.

  • Budget Control System in SAP

    Hi,
    I want active Budgeting Control system in SAP. Please let me know how I can activate, from first step to last step. Please help me.
    Thanks & Regards,
    Hemant Maurya

    Hi,
    For activating Budgeting
    In OKKP activate the Order management active for the budgeting in orders
    Commitment mangement active for the commit manaement active.
    Activate which all the area you want budgeting,Ex Projects,Sales order,costing object.
    Define Budget profile in OKOB.
    IN KOAB maintain the assignmnet of budget profile to order types.
    IN KOAO activate the commit management check box against the order types.
    Define the tolerance limit for the budgeting.
    Maintain number range in OK11.
    Now create any internal order & assign budget in KO22 transaction,check the same.
    Regards,
    Raj.

  • Budget Control System Configuration

    Hi,
    Please let me know how to configer Purchasing Budget, Overheads budget, sales budget, production budget and capital budget.
    Regards
    SAPCO

    Dear NRSAPCO,
    We can create budget either for cost centers or internal orders, generally. But if you wants to get more as Budgetory control system u must go to Fund management.
    Even in Cost center budgeting u can only create Budgets and at the end of the period u can get Actual Vs budgetted figures report. but u cont get any "Trigger" if u r actual figure (of a cost center) exceeds Budget figure.
    Where as in internal order u get get this trigger and u need to create subsequent budget (increasing the amont of budget) to get entry posted.
    Thank you

  • Use of Budget controll system in funds management module

    Dear all,
    Presenly we are using Former budgeting.Now we want to go for Budget controll system (BCS).Now our doubt is whether we have to convert  the former budgeting to BCS.Or we have to go for fresh implementation of BCS. For your information we have not migrated to ECC6.0. Only technical upgradation of ECC6.0 is completed.Kindly advice.
    Regd.
    Shivaji

    Hi, depends on your business requirements.
    Do you want to use Addresses(means not 1 to 1), AVC, Revenues Increasing the Budget, Cover Eligibility, Consistency Check etc.
    If former budget satisfied your bus. requirements , and you just need e.g. new account assignment(eg funded program), then may be there is no need for new implementation, just some correction

  • Plant stock procurement with budget control

    Hello,
    Our client has centralized stores which caters to FOS (Factory Operating Supplies) requirements of various projects and departments. Some of the FOS items include u2013 Wielding rods, Personal Protective Equipments (PPEu2019s) etc. These are procured at plant level.
    We have following requirement u2013
    1)     Above mentioned FOS material should be procured as Plant stock with budget control
    We have following queries regarding this requirement u2013
    We want this material as plant stock which will be issued as per requirement. If I create PR, PO without account assignment, there is no budget control. 
    If we procure this material against cost center, material do not come in stock.
    Please guide for solution.
    Regards,
    Milind Dumbre

    Hi
    If you have PS implemented
    then you can use account assignment category Q in PO and WBS element which will control your budget
    Or Go with value base contract or Quantity base contract with vendor so you can control it
    Regards
    Kailas Ugale
    Edited by: kailasugale on Nov 12, 2011 7:48 PM

  • How to Run a Cost Estimate with Budgeted Values parallel to the Std Cost Estiamte

    Hi Experts,
    My client want to run a parallel cost estimate with Budgeted values for each type of cost in a similar process like standard cost estimate(currently only Std business run only the std. cost estimate). Below will be provided to run the said cost estimate.
         1. Budgeted Cost for cost elements against each cost center
         2. Re-posting/distribution will be required run to allocate and apportion the cost from service cost centers to Production cost centers
         3. All Planned(future) Material Cost will be provided. (note that the valuation strategy of costing variant of standard cost estimate has below sequence
         4. Budgeted activity quantities will be provided. (Cost and activity qty for Kp06 and Kp26)
    Based on the above data business need to run a cost estimate with budgeted values parallel to the standard cost estimate(based on planned values), which will be compared with actual then Budget at each months.
    Simply an alternative cost estimate with budgeted values for a given period for all materials.
    Kindly advice the possibility of such a cost estimate in the system and if possible pls. mentioned the Process in order and configuration steps for the same.
    Thanks in advance.
    Aziz

    Hi..
    You can define costing variants which have valuation variant for budgeted values parallel to the standard cost estimate  in Customizing for Product Cost Controlling.
    You can define target cost versions using above costing variants under the customizing transaction OKV6 as below picture.
    When you calculate variances, you can check “all target cost version” flag to calculate variances  for all target cost versions in the controlling area as below picture.
    You can analysis the difference between actual cost and several budget cost using target cost version as below picture.

  • An SAP Solution for capital planning and Budgeting of Capital Assets?

    Is there an SAP Solution for the Planning and Budgeting of Capital Assets?
    A solution that provides planning, budgeting, and tracking for capital assets through the entire life cycle of each asset, from the initial request through the final disposal.
    The solution needs to be able to run “scenarios.” A scenario contains equipment that may potentially be purchased. Scenario items are used to help determine cost, capacity, and cash flow feasibility.

    Hi
    What you suggested is the ideal approach...
    However, if they say that the budget allocated to capital purposes (70%) applies to both capital projects and expenses and they would like to control it together, but have reports separately, it is not possible with standard SAP...
    If they want to have just one IO for both cap and exp, You can suggest them a work around to capture CAPITAL or EXPENSE in a ref field (XREF1 in BSEG) and you can run KOB1 with XREF1 displayed in it....
    In standard KOB1, XREF1 is not displayed, you have to use Exit COOMEP01 to include the fields you want... Add XREF1 to the Structure CI_RKPOS and write your code in the include ZXKAEPU01 of EXIT_SAPLKAEP_001
    Without an identifier @ the time of booking the transaction in the system (Either by way of IO or a ref field), you wont be able to generate reports later on
    Regards
    Ajay M