Plan, Actual & Commitment Report in Multiple Currency

Dear SAP gurs,
Is there any report where I can see Plan, Actual & Commitments in Multiple currency (see below format). In standard SLAR reports, values are displayed in one currency at a time either I can see in INR or USD.
Here each WBS is planed in USD as well as in INR. If PO is raised in USD, then actual value should be shown against planning done in USD.
WBS Elem     Plan          Actual          Commitment     
     USD     INR     USD     INR     USD     INR
WBS1.1     3000$     1000INR     500$               500INR
WBS2.2          50000INR          10000INR          300INR
Thanks,
Venkat

Dear Venkat
Each of the views in the hierarchy reports (such as 12KST1C) can       
only contain values for one currency at a time (because totals for    
multiple currencies would not make sense).     
Since only one currency can be displayed at a time, the Trans.currency view is not meant to show values in multiple currencies; rather, the Trans.currency view only provides a reference to the user of the currency involved in the Plan and        
Actual postings. For example, if the actual postings had been in      
mixed currencies like:                                                                               
Doc. date  Cost elem.    Value COCurr  CO.Cr      Value TranCurr  TCrcy  
   01-07-2007 911010000                 800   XXX                        1700  YYY
   01-07-2007 911010000              3,000   XXX                        3,000  XXX
Then the Trans.currency view would have contained:                                                                               
Trans.currency         Plan             Actual                      
  YYY                            0             800                   
  XXX                         3,700           3,000
  Result                     3,700           3,800
You can always switch between currencies in the report Settings ->    
Currency, but only one will be displayed at once.                                                                               
I hope this explanation helps you to understand the standard system   
behaviour.                                                            
Regards
Martina

Similar Messages

  • S_ALR_87013340-PRCtr Group:plan/Actual Caomparison Report performance issue

    I'm trying to get the "actual line item" details from the S_ALR_87013340-PRCtr Group:plan/Actual Caomparison Report and I get a
    ABAP run time error. I tried to running for just one month and on several accts. please help to me. how to get the report.
    or how to improve the performance of this program.
    Thanks in Advance

    hi,
      first we need to know what part of the code is taking time. Do run time analysis using SE30 transaction to know what part of coding is taking more time. use can ST12 transaction to get more detailed analysis.
    Since this is standard SAP report also check any OSS note exist for the performance problem.

  • Report Painter - Multiple Currencies

    Hi,
    I would like to know on how you create multiple currencies in report painter. We have a requirement
    whereby we have 3 different columns:
    Current Year (Actuals)  ---> Exchange rate Type X
    Prior Year  (Actuals)
    Plan Current Year  -
    > Exchange rate Type Y
    My question is how can i create a report that will enable me to prompt for exchange rate of Actuals and Plan data  as  we would like the user to enter different exchange rate type for actual & plan.
    Appreciate your help.

    Hi,
    I'm afraid, it's not possible via Report Painter (to have different columns calculated by different rate); you'll have to develop a report in ABAP for this.
    Regards,
    Eli

  • Cost Center Plan/Actual/Commitment

    Hi
    Want to Devlop a customized report for Cost Center where I need to display Plan/Actual/Commitments vaues for a cost center fiscal Year per period year wise.
    Let me know which, tables I can use to get these values as COSS and COSP not shows values Period wise.
    regards,
    Atul Rajmane

    Hi,
    I am able to get required the data from COSS and COSP tabel.
    While going through COSS-OBJNR number I am getting my required cost center have Object number as KLZPG1F010000105CR0021 where ZPG is my Controlling area and 1F010000105 is a cost center.
    But, I unable to get it meaning of KL and CR0021 in this string.
    Let me know what it means so that I can form my object as required above to get deatils from COSS table.
    regards,
    Atul Rajmane

  • Plan actual consumption report

    Dear All,
    The client want to see a report
    where the planned consumption of quantity mentioned in the BOM and the actula consumption at conformation along with the standard price of sfg.
    he wants to get the difference per unit of standard& actual.
    this is basically he wants without overhead .
    any suggestion

    Hi,
    Plz chk the t.code:KOB1,Before That create consumtion cost element group.So u can get plan and actuval consumtion and quantity at each production order wise.
    Regards
    Nagaraju sami

  • Planned & Actual Production  report

    Hello all
    MY requirement is ,  i need to add this two req in the one report   ( Z transaction ),
    Planned Production - This must show the  production plan for the current week only. We should be able to drill in further and see the actual day of planned production, we should also be able to see forward plans for the next 3/4 weeks by day.                                                                           
    Actual Production - This should show the amount of stock physically produced against the planned qty
    How can i get this all information ?, what logic  i need to tell the developer? , In which table i will get all the inforamation?.
    Please help me out in this.
    Piyush

    Dear ,
    SAP has given a fabulous report called -Order Information System -COOIS where you can play around your every requirement which you are looking for .Here , you various selection criteria .Let me explain based on your rquirement :
    1.Select Item -Select Standard Profile and Enter Plant  , Order Type , ( Optional -Material /Production Order ) execute  which will display all the related information .Now you have to goto -Change Lay out option in the top and drag and drop all of your filed like
    Like wise , you can get as many infoamrion as you can  based on selection procedure .
    However , I have developed another report which is based on COOIS  for different busness requirement and sharing you the few field mapping : All the field will based on AFKO /AFRU/AUFNR
         WERKS        AUFK-WERKS,              "Plant
          AUFNR       AFKO-AUFNR,              " Prod. Order No.
          PLNBEZ      AFKO-PLNBEZ,             " Header Material No.
          GSTRI         AFKO-GSTRI,                "Actual Start Date
          GLTRI         AFKO-GLTRI,                "Actual Finish Date
          GAMNG      AFKO-GAMNG,              Prod. Order Qty.
          AUFPL        AFKO-AUFPL,              "Planned No. Of Operation
          AUART       AUFK-AUART,              Order Type
           ISM01        AFRU-ISM01,              "Required Qty.
          VGW01     AFVV-VGW01,           "Quantity Withdrawn
          VGE01       AFVV-VGE01,              "Unit Of Measure
          EFFPERC   AFVV-VGW01,              "Eficiency %age
          MAKTX     MAKT-MAKTX,              "Material Description
    Try and let us know if you need farther help
    Regards
    JH

  • Planned /actual cost report in iw31

    Hi Gurus
    Is there any method to see individual component cost while creating order (IW31)  in pm. I tried with planned/cost report button on the cost tab by including material and material text  in the layout, but when I execute the material and text is blank and I am unable to see individual material wise cost.
    Kindly help.
    Regards
    Vidhyadharan

    Yes it a business requirement.
    while creating reservation, the user should be aware that he is drawing a high value item.
    for eg. One of the component  of the Assembly has failed, and it has to be replaced, the stores does not have the stock, it takes time for that component to get reparied, since it is time consuming,and the production been affected,  the engg replaces the entire assembly by drawing from the stores.  Since the engg does not know the cost, he  should be made aware that he is drawing a high value item from the stores , which he has to take an oral approval from the higher authority.
    Regards
    Vidhyadharan

  • Budget/Actual/Commitment report-S_ALR_87013558

    Hello Experts,
                          Is it possible to get the get this report (S_ALR_87013558) on day basis? I mean to say if i want to see the balances between two particular dates WBS/Project wise, so can i get the same?
    Please suggest..
    Thanks
    Ankur

    Hi,
    Use CJI3 or go to Call Up report from S_ALR_87013558 and filter the report as per Date.
    Regards,
    Nitin

  • Plan / Actual Comparison Report - S_PL0_86000029 is not showing one month

    Gurus,
    The TCode, S_PL0_86000029 when being run for just one month, e.g. August (08.2008), it shows the figures for the whole year.
    Being the first year on SAP; the month this went GO-LIVE was October.
    Data before that since 01.01.2008 till 30.09.2008 was uploaded.
    How do we just break it down to one month?
    This is quite important.
    Thanks.
    Edited by: Bhatia on Oct 16, 2008 10:34 PM

    Hi Rau,
    Could you please me How to Upload the GL or Open Item Balances on Month to Month Basis? for this we still use FB01 for Initial Upload?
    My Client is giving the balance for last year Monthly with daily Transactions with past Posting dates obviously,do I need to Upload with same Posting dates or with Current Posting date?
    For reporting Purpose My Client would like to see Monthly Balances of Open items for Initial Upload,"is this same as Month to Month Upload you advised above"?
    What is the Difference b/w Month to Month ORr Just one Amount as total balance uploaded to SAP? which is Best Practice before Initial Upload?
    Thank you ,
    Paarthaa...

  • Commitments at activity level in report S_ALR_87013533 - Plan/Actual/Commit

    Hi All,
    When i executed the report S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned, the commitments are shown at WBS level but not at activity level. Is there any setting required to see the commitments at the activity level?
    Where as the planned costs are shown against the activity in the same report.
    Please suggest the required settings if any?
    Regards,
    Ramana.

    HI Rifaee/Martina,
    In CJI5 the line items are shown under the WBS. But i would like to see the line items in the report.
    Even after running the report cjen the database is not updated for line itemwise commitment in the report.
    How to assign the PR/PO as account assignments to activity? Where do i need to do this setting? Please inform.
    Regards,
    Ramana

  • S_ALR_87013611 - Cost center: Actual/Plan/Variance selection report - outpu

    Hello all,
    when running the report,it can be seen in SAP screen by cost groups and by cost elements.
    The problem is that when user tries to save report in local file, then it is not able to see cost center distribution. User can only see cost elements amounts.
    is there a way we can save on a local file cost groups as well?
    Thanks in advance for letting me know
    regards
    Hana

    Hi,
    Look for data source 0CO_OM_CCA_1 ( Cost Centers: Costs and Allocations ) ..it will give you the plan / actual /commitment amounts & qty.
    Link is http://help.sap.com/saphelp_nw04/helpdata/en/8d/1f383fe58d5900e10000000a114084/frameset.htm
    Hope that helps.
    Regards
    Mr Kapadia

  • Problem while running the Profit center Plan/Actual Report in Background

    Hi
    While executing the T.Code s_alr_87009722 (Profit Centre plan/Actual Comparision Report) on fourground it is giving all the profit centers/groups in the particular profit center group. But when i run the same report in back ground mode it is picking only the last profit center in that group. Please help me regarding the same.
    Regards
    Surya

    hi prakash ramu,
    even it is not working. it is directly talking me to spool request..
    i think it is not possible, while ur running the report in background.,
    any how if possible could u pls send me the code...
    thanks
    ramu

  • Abap report for budget/actual/commitment

    Hi Guru..
    Please help me.
    Im in urgent
    I wanna write an abap program for budget/actual/commitment.
    I try to trace prgram s_alr_87013019, but only one table found.
    Please let me know which table is using for budget/actual/commitment
    report..
    Please guru..

    Hello Mohd,
    The actual,budget and commitment values are stored in the one table COSP.
    The values differentiate with field <b>VRGNG</b> - "CO Business Transaction".
    If the record has in this field text '<b>COIN</b>' it means that values are "actual".
    For example:
    OBJNR     PR00000101
    GJAHR     2005
    KSTAR   101101
    VRGNG     <b>COIN</b>
    TWEAR   USD
    WTG001     100,00
    WTG002  200,00
    It means that the element PR0000101 has the '<b>actual'</b> operations refering
    the cost element 101101, with values: 100,00 USD in january 2005 and
    200,00 USD in february 2005.
    The next row in the table COSP, clould look like this:
    OBJNR     PR00000101
    GJAHR     2005
    KSTAR   101101
    VRGNG     <b>RMBA</b>
    TWEAR   USD
    WTG001     100,00
    WTG002  0,00
    This means that there was a <b>'Purchase requisition'</b> in january 2005
    with decretation on object PR0000101.
    And the next row, could be:
    OBJNR     PR00000101
    GJAHR     2005
    KSTAR   101101
    VRGNG     <b>RMBE</b>
    TWEAR   USD
    WTG001     0,00
    WTG002  150,00
    And that means that in february 2005 there was a <b>'Purchase order'</b>
    with value 150,00 USD decretated on this object.
    I hope, that my explanation is now clear and accurate.
    - Marta

  • Staff Budget / Actual Variance report

    Hi,
    What is 'Staff Budget / Actual Variance report'.
    Is there any Business Content Reports avaliable for this purpose.
    Please provide me information on Which Data Target 9Technical Name) i can do this report.
    Thanks

    Hi,
    This InfoCube contains all costs and quantities on WBS elements (plan and actual using delta extraction, commitment, budget, accruals) that were transferred from the source system(s).
    You can also use this InfoCube to access your own fields. For more information, see Customer-Defined Fields.
    For background information on the concept of InfoCubes, see InfoCubes in Controlling.
    Higher-Level Objects
    Queries
    The following queries can access this InfoCube:
    ·         0WBS_C11_Q0001: WBS Element (Detail): Plan/Actual
    ·         0WBS_C11_Q0002: WBS Elements (List): Budget/Actual/Commitment
    ·         0WBS_C11_Q0003: WBS Elements (List): Overall Planning/Actual/Commitment
    ·         0WBS_C11_Q0301: PSM: WBS Element (Detail): Plan/Actual
    ·         0WBS_C11_Q0002: PSM: WBS Elements (List): Budget/Actual/Commitment
    Notes on Query Definition
    If you attempt to sum across different valuation views and currency types, your query results will be incorrect. Summing across different values of these characteristics does not provide useful information.
    InfoSources
    ·         0CO_OM_WBS_1: WBS Elements: Costs
    ·         0CO_OM_WBS_2: WBS Elements: Budget
    ·         0CO_OM_WBS_3: WBS Elements: Overall Plan
    ·         0CO_OM_WBS_6: WBS Elements: Actual Costs Using Delta Extraction
    Characteristics
    InfoObject
    Description
    0WBS_ELEMT
    PSP element
    0COSTELMNT
    Cost element
    0CO_AREA
    Controlling area
    0CURTYPE
    Currency type
    0PIOBJSV
    Partner object type
    0PIOVALUE
    Partner object
    0METYPE
    Key figure category
    0VERSION
    Version
    0VTDETAIL
    Details of value type
    0VTYPE
    Value type for reporting
    0DB_CR_IND
    Sender/receiver indicator
    0VALUATION
    Valuation view
    0VTSTAT
    Statistics indicator for value type
    0FM_AREA
    FM area
    0FUND
    Fund
    0FUNC_AREA
    Functional area
    0GRANT_NBR
    Grant
    0PFUND
    Partner fund
    0PFUNC_AREA
    Partner functional area
    0PGRANT_NBR
    Partner grant
    Navigation Attributes
    The following navigation attributes have been activated. This is a sample selection. You are free to activate additional attributes, or deactivate attributes to improve performance.
    InfoObject
    Description
    0WBS_ELEMT__0CO_AREA
    Controlling area
    0WBS_ELEMT__0PROFIT_CTR
    Profit center
    Time Characteristics
    InfoObject
    Description
    0FISCPER
    Fiscal year/period
    0FISCVARNT
    Fiscal year variant
    0FISCPER3
    Posting period
    0FISCYEAR
    Fiscal year
    ·        The characteristics fiscal year (0FISCYEAR) and posting period (0FISCPER3) are filled by the fiscal year period field (0FISCPER) in the InfoSource.
    ·        The characteristics and the cost element are not filled for overall budgets or overall plan values. The posting period and the cost element characteristic are not filled for annual budgets or annual plan values. This provides values with the format 000.YYYY (where YYYY is the fiscal year), particularly for the 0FISCPER characteristic.
    Key Figures
    InfoObject
    Description
    0AMOUNT
    Amount
    0QUANTITY
    Consumption quantity
    Restricted Key Figures
    The restricted key figures are divided into several groups.
    The basic key figures cannot be used without restricting some of the characteristics. For this reason you should use only the supplied restricted key figures in queries you have defined yourself, or analyze the supplied restricted key figures and modify them to suit your requirements.
    InfoObject
    Restriction
    “Costs” Group
    Data for all restricted key figures of the group
    Key figure category = 1000 (costs and associated quantities)
    Valuation view = 0 (legal valuation)
    Version = 0 (current variant)
    Key figure = 0AMOUNT (amount)
    0WBS_C11_RK0002 Actual costs
    Sender/receiver = S (debit posting or receiver debit)
    Value type = 10 (actual)
    0WBS_C11_RK0001 Planned costs
    Sender/receiver = S (debit posting or receiver debit)
    Value type = 20 (plan)
    0WBS_C11_RK0006 Settled costs
    Sender/receiver = H (credit posting or sender debit)
    Value type = 10 (actual)
    0WBS_C11_RK0003 Commitments
    Sender/receiver = S (debit posting or receiver debit)
    Value type = 40 (commitment)
    0WBS_C11_RK0004 Budget (per fiscal year)
    Value type = 50 (budget)
    0WBS_C11_RK0005 overall planning (per fiscal year)
    Value type = 20 (plan)
    “Revenues” Group
    Data for all restricted key figures of the group
    Sender/receiver = H (credit posting or sender debit)
    Key figure category = 1001 (costs and associated quantities)
    Valuation view = 0 (legal valuation)
    Version = 0 (current variant)
    Key figure = 0QUANTITY (quantity)
    0WBS_C11_RK0008 Actual revenue
    Value type = 10 (actual)
    0WBS_C11_RK0007 Planned revenue
    Value type = 20 (plan)
    “Quantities” Group
    Data for all restricted key figures of the group
    Sender/receiver = S (debit posting or receiver debit)
    Key figure category = 1000 (costs and associated quantities)
    Valuation view = 0 (legal valuation)
    Version = 0 (current variant)
    Key figure = 0QUANTITY (quantity)
    0WBS_C11_RK0021 Actual consumption quantity
    Value type = 10 (actual)
    0WBS_C11_RK0022 Plan consumption quantity
    Value type = 20 (plan)
    “WIP” Group
    Data for all restricted key figures of the group
    Sender/receiver = S (debit posting or receiver debit)
    Key figure category = 1410 (inventory (WIP))
    Valuation view = 0 (legal valuation), version = results analysis version
    Value type = 80 (results analysis)
    Key figure = 0AMOUNT (amount)
    0WBS_C11_RK0011 WIP: Revenue in excess of billings
    Detail for value type = 10
    0WBS_C11_RK0009 WIP: Work in process
    Detail for value type = 1, 2
    0WBS_C11_RK0010 WIP: Cannot be activated
    Detail for value type = 3
    “Results” Group
    Data for all restricted key figures of the group
    Sender/receiver = S (debit posting or receiver debit)
    Key figure category = 1400 (accrual calculation)
    Valuation view = 0 (legal valuation)
    Version = accrual version
    Value type = 80 (results analysis)
    Key figure = 0QUANTITY (quantity)
    0WBS_C11_RK0018 Revenue affecting net income
    Detail for value type = 12
    0WBS_C11_RK0014 Cost of sales
    Detail for value type = 3, 4
    0WBS_C11_RK0015 Cost of sales (cannot be capitalized)
    Detail for value type = 5
    0WBS_C11_RK0017 Realized loss
    Detail for value type = 11
    0WBS_C11_RK0012 Reserves for imminent losses
    Detail for value type = 1
    0WBS_C11_RK0013 Reserves for imminent losses - inclusion cannot be capitalized
    Detail for value type = 2
    0WBS_C11_RK0016 Loss
    Detail for value type = 10
    “Reserves” Group
    Data for all restricted key figures of the group
    Sender/receiver = S (debit posting or receiver debit)
    Key figure category = 1420 (reserves)
    Valuation view = 0 (legal valuation), version = results analysis version
    Value type = 80 (results analysis)
    Key figure = 0AMOUNT (amount)
    0WBS_C11_RK0019 Reserve: unrealized costs
    Detail for value type = 1, 2
    0WBS_C11_RK0020 Reserve: unrealized costs, not capitalized
    Detail for value type = 3
    Units
    InfoObject
    Description
    0CURRENCY
    Currency key
    0UNIT
    Unit of measure
    Hareesh

  • S_ALR_87013326 - Profit Center Group: Plan/Actual/Variance

    Hi,
    I am looking to branch off from a line item in the S_ALR_87013326 - Profit Center Group: Plan/Actual/Variance report to the actual posting document. Is there a way to do this?
    Thanks,
    Ram
    Message was edited by:
            Ram R

    Hi Nadini,
    Thats cool. I have assigned points.
    Another question. S_ALR_87013326 shows balance sheet accounts as well with zero balances. Is there a way to eliminate these accounts or populate them with the relevant values.
    Thanks,
    Ram

Maybe you are looking for

  • How to solve this problem that the error message is "kPDFMErrorLaunchingAssociatedApp"?

    HI,There is a ASP.NET program that use to convent the Word to PDF. I used PDFMAKERAPI.DLL in this program.this is the code using System; using PDFMAKERAPILib; namespace test1     public partial class index : System.Web.UI.Page         protected void

  • Programmed Dialling not working

    Hi I am trying out the ZTE Open C for work, but have found a limitation that seems to be a showstopper alltogether I have a bunch of numbers coded into my SIM, which is for conference calls. The numbers are in a format like xxx-xxx-xxx,,1234567# wher

  • LOV dynamic refresh in CR2008 with BOXI3.1

    Hi, I'm in a confusion whether the LOV for the prompts refresh dynamically when the crystal report is opened. It is a universe based report. I heard, in XIR2 it is a problem and it wont behave similar to WebI. When i tried in CR 2008 with BOXI3.1 unv

  • Got new adobe id and password,trying to load library book to nook, adobe digital ed will not open???

    got a new adobe id and password,  trying to download a lib book to my nook,  adobe digital ed won't open,  why not?  JLW

  • Recovery Time of Database

    Dear All I have a database server with the following configuration: Total Storage :(1.2 Tera Bytes) Total Tablespace Size (250 GB) Type of Processor :3.1 GHz Number of Processor : 2 RAM : 8 GB I want to setup a backup policy by configuring catalog se