PR: Procurement w/o material from vendor with plant assignment not defined

Hi,
Getting the error message:  06806 - Procurement w/o material from vendor with plant assignment not defined
while creating the PR with account assingment (P- project) & without material no. instead entering the short text in the PR.
this issue (Error message) is getting to only one user.
question-1:  Is it possible to set the Error messages to the user specific. Because other users are able to create the PR with the above inputs, but the one user is not able to create instead getting the above E- Msg.
question-2: Is it possible to set the messages to Plant specific instead quesiton -1 or both
Or else, please let me know how to deactivate the above E-msg to the specific user.
Please do the needful asap.
Regards,
Sapsrin

Hi,
As you noticed, note 856962 has changed the system behaviour
when you are working with procurement w/o material from vendor with
plant assignment.
Items without a material master record can only be ordered from vendors
without a plant assignment.
This note will stop your users from creating service purchase orders
for a vendor who has a Plant assigned in the vendor master, issuing
the error message 06 806.
you can check the below code:-
LMEPOF23
  IF ekpo-ematn IS INITIAL AND
      (  aktyp EQ hin OR ekko-reswk NE oekko-reswk  OR      "856962
     (  aktyp EQ hin OR NOT ekko-reswk IS INITIAL OR        "856962
        ekko-bsakz NE oekko-bsakz OR
        gf_extended_check NE space ).
    PERFORM enaco_2(sapfmmex) USING '06' '806'.
regards,
Lalita

Similar Messages

  • Procurement w/o material from vendor with plant assignment not defined

    While creating  standard Framework Order (FO)   asset  PO  I am getting the below error
    "procurement w/o material from vendor with plant assignment not defined"
    Plz Help
    Regards

    Dear INDRANIL BHATTA ,
         Thanks for your reply and your soluation ,
    Finally , I found Vendor Master assignment to plant so it can't create FO PO .
    ->  XK02 -> selecting "purchasing data" >Extras>Add.Purchasing data.

  • Third-party not defined in the case of vendor with plant assignment ?

    We use a Third-Party Vendor to direct-ship some products directly to our Customers.
    When transfers third party order form's PR STO PO, prompts the following information
    Third-party not defined in the case of vendor with plant assignment
    Message no. 06769
    Diagnosis
    You are entering a purchase transaction involving a vendor to whom a plant has been assigned. Normally, this will involve the transfer of materials from one plant to another.
    This process necessitates a delivery and a billing document in the SD system. The PO appears directly in the delivery due list of the issuing plant (vendor) and therefore does not need to be transmitted.
    However, an item with the procurement form "third-party" (triangular business deal) cannot appear in the delivery due list.
    Procedure
    An item with the procurement form "third-party" can only be ordered from vendors without a plant assignment.
    how should solve?
    Many thanks,  Adny.
    Edited by: Andy Yao on Feb 8, 2010 3:58 AM

    Hi Andy
    Why u doing stock transfer order,in third party sales there is no stock transfer
    Follow below procees for third party sales( Vendor ship materials directly to customer)
    Create Sales order(Use item category TAS) >>> Purachase requisition(Automatically from order) >>> Purchase order >>> Vendor Invoice Verification >>> Invoice to customer
    Kapil

  • Vendor with plant assignmnet

    Hi All,
    I have a query,I am trying to create a PO for consumable material with vendor code as one my plant.The vendor is already maintained in correct Pur Org.
    I am getting following error-
    Procurement w/o material from vendor with plant assignment not defined.
    Can sombody tell me how we conclude that vendor is assigned to the plant.
    Thanks

    Hi
    Go to MK02 or XK02 and enter Vendor and Purchase Oranization. select purchasing. go to Extras --> additional purchasing data.YOu can find plant assignment over there.
    regards
    Srinivas

  • TRANSFER OF MATERIAL FROM VENDOR TO VENDOR

    Hi *SAP MM GUYS*  Please check my scenario .
    I have send some material to a vendor for subcontracting jobbwork.
    after as he is delaying the work I want to send the material to another vendor.The first vendor has no problem with this.So how to transfer the material from vendor to vendor.Please give me detailed explanation.
    Awaiting your reply
    Veer

    Dear,
    Case1) Process flow IF material is Excisable:
    Do 542 of material
    Reconcile the challan with that dpcument
    Complete the challan
    Do 541 for second vendor
    Raise the s/c Challan
    Case 2) Process flow if material is non excisable
    Do 542 of material
    Do 541 to the second vendor
    OR u can do
    542 in MB1B wherein u can put the vendor where u want material to be sent.
    Regards,
    SNB

  • Returnable Material from Vendor

    Hi,
    We are planning to implement Returnable Material from Vendor.
    The process we would like to follow is that we issue certain pallets to the vendor who would provide the RM's on the pallet. The pallets would be valuated on the Company code. We would like to track the number of pallets being issued to the vendor and also the number of pallets currently at the vendor at any point of time.
    The following are my doubts:
    1. How do we configure this process in SAP?
    2. What are the Master Data changes that need to be done? (Vendor Master, Customer Master and Material Master)
    3. How do we issue the Pallets to the vendor?
    4. How do we GR the Pallets?
    5. Should we treat the pallets as a special Material?
    6. How to track the Pallets?
    7. Can we implement WM for tracking pallets?(like can we use Storage Unit Management to track pallets)
    8. If my RM stores is WM managed how do i capture the above information?
    Please suggest.
    Regards,
    Srikanth

    Hi,
    Create Pallets material  as a material Type LEIH...
    Now create PO for your RM's...
    Do GRN for above PO ...In the GRN RM material will come in the GRN...Now you click on transport equipment button (last button) , just below the item grid table...
    It will take 501 + M mvt...
    Here you enter your pallet material and do the GRN.....check in MMBE, tracking will be done here...it wil show you the stock in sepearte line item...
    Now return the pallet to the vendor by 502 + M mvt ....
    Utsav
    Edited by: Utsav.agra on Sep 29, 2009 9:14 AM

  • Transfer Material From Vendor to Vendor

    Please can anyone  explain material can transfere from vendor to vendor....Thank you ....Raveendra

    Hi,
    What do you mean exactly by transfer material from Vendor to Vendor?
    Are these your materials provided to Vendor?
    Or are you referring to Consignment?
    Anyway, please have a look below.
    1) Go to MIGO_TR t-code
    2) Set it to Transfer Posting A08, Other R10
    3) Use movement type 542 to transfer from Vendor to our warehouse in storage location
    4) Use movement type 541 to transfer from the receiving location in step 3 and transfer it to the new Vendor.

  • Material No. Mandatory with account assignment category K

    Dear,
    Can i make Material No. Mandatory with account assignment category K
    Please advise
    Rami

    Hi,
    It is not possible to make material number mandatory for Account Assignment Category.
    But you can make Account Assignment mandatory for a material if material is non-valuated (Mat Type - UNBW) or Non-stock (Mat Type - NLAG)

  • Migration from PC with MA did not end. Had to shut down MacBookPro. After restart no new user was created. Can't find the transferred data (35 GB). Would like to delete it.

    Migration from PC with MA did not end. Had to shut down MacBookPro. After restart no new user was created. Can't find the transferred data (35 GB). Would like to delete it.

    iTunes is required to initially activate the phone. Back when the iPhone 3G was sold, you would take it out of the box and see a "Connect to iTunes" screen. She HAD to connect to a computer in order to begin using the phone. Does she remember what computer this was?

  • Regarding rejection of material from vendor

    Hi All
    My scenario is like this
    My semi finished material is come from vendor after that i put that material on production after doing all process production done the GR for that material as finished goods. This material goes into quality and here I come to know that the material is rejecting because of vendor. But the GR is done on finished material code so I have to do the material to material transfer by movement type 309. And then reject the material on vendor coz Material code for vendor material is different and material code after production is different
    I want to ask is their any other process to map this scenario
    Regards
    Sachin

    Hi,
    Sorry for replying late.
    Pl. I am not worring about points. My only concern is I should share my knowledge and improve knowledge by following the others inputs.
    Whatever the quantity you have to reject against a particular vendor, can be enterered in the complaint quantity.
    You have to enter the FG material no., in which you are rejecting in the parent material field.
    In the child material field, you have to enter the material no. which you have recd. from the vendor (refer BOM)
    After that, you have to scrap the material by using T code QM10.
    Then for Return delivery process, pl. discuss with your MM counterpart and for Debit to supplier pl. involve FI/CO counterpart.
    My suggestion is that, First write down the Business Process Procedure for material defect found out during processing. i.e your current problem process.
    Madhava

  • Procurement Of Imported Material From Trader

    hi,
        i am purchasing one imported material from a trader,in this case excise treatment is different
        *MATERIAL        QUANTITY   RATE/UNIT   RATE OF  DUTY/UNIT    EX-DUTY&CESS*       AMOUNT
                                                                         Duty%
         KP                        238                280           8%  bed             16.442          3913.19                   66640
                                                                          2%  ecs                                    79.25
                                                                           1% hecs                                   39.50
                                                                           4 % adc                 8.9             2130.57
                                                                                    total              6162.51(bedecshecs)
    now in this scenario bed and adc r charged on qty basis(duty/unit),now at the time of pur.order vendor gives u  the rate of mat including excise and tax.,i am using taxinn procedure ,system calculate excise on po value that is on 66640 due to which at the time of invoice verification vendor accounts get credit by
    (po valueexcise) also i.e (666406162.57) but  as vendor gives mi the rate of mat including excise so its account should not be hit more than  66640.  66640 amount include excise taxbase value.
       at the time of po vendor cannot give mi base value price.

    thyks

  • Authorisation for transfer of material from group of plants to another.

    Hi experts
    We need to control mvt of goods from group of plants to another group of plants by the same user. The group of plants may be combination of multiple plants or single plant also. Transaction to be checked is MB1B with 541/412 mvt. Basically this requirement is to check transfer of exempted material to Non-exempted material from the point of VAT implication. Can any body share your thought.
    rgds
    Raghu Shetty

    Hi,
    i still have some concerns about the creating new materials solution because we have to create the following relevant things:
    SD: condition record
    MM: infor record
    PP: new BoM
    we have 25 materials which will change profit center, there're a lot extra works we need to do.
    Is there any other way we can try?
    Regards

  • Print of GR without material no and with Account assignement K / Q

    Dear Freinds,
    I want make Print out of Material Document with Material text (without  Material code with account assignement K or Q Project). I made out put setting for WE03, Transaction event type WE Print version 3 and Print Item 1, Material document.
    But i am not able to print in after MIGO. In MIGO Disply, it is showing error as "The system could not create any outputs"
    But I can able to make print out for Material document with material no. i am facing this problem only for text without material no with account assignement like K and Project refernce.
    Please guide me.
    Rgds
    Madhavan

    Hi Madhavan
    Go to MN22 , put WE03 , prsee enter , if u r alrady created any condition record , that will be diplayed , now select one line item , and clik communication . then after going in second screen , u will find box as " LOGICAL DESTINATION " ,  put the logical destination ( LP01 ) and check the tick box " print immediately , and save the condition record ...
    after donig these things ur problem will be solved , as i was also facing same problem , after doing this i got solution

  • Sale wrt STO of raw material from a manufacturing plant to other plant

    Hi Gurus,
    My scenario is that, I have procured a raw material for PLANT A. At the time of procurement it  hits RG23A PART1 AND RG23A PART2 registers. Now I want to sell this raw material without any value addition to other PLANT B of the same company code.
    Here the excise requirement is that at the time of delivery it should hit RG23A PAR1 AND PART2 and should not hit RG1 register.
    i request you to pls guide me how to execute this process in SAP so that it satisfies excise requirements.
    Thanks and Regards
    ujwal

    Seems you need new mov type- ( in place of 641)
    is this requirement is only for Raw material STO??
    Generally , even when you do STO for Raw Material,as per excise it should hit RG1- Not sure,why you want it to be posted in RG23A reg.

  • Procurment of Raw Materials against MTO with account assignment category "E

    Dear Champions,
    Looking for your guindance in the following matter:-
    While creating PO with account assignment category E for MTO senario , its asking for consumption account.
    Is it possible that during PO creation it should not ask for GL account , and while doingGR ....the goods should be inventories both on quantity and value basis updates and acts as a special stock against sales Order.
    What setting are necessary ? Please advise
    Thanks In Advance
    Ashwin

    Hi,
    In a purchase order item you mension account assignment category means that it is for consumption.The stock and value are directly posted to the account assignment you mentionedat the time GR.
    And when you are assigning a account assignment catagory you need to mension which account(GL account) of the account assignment.We canot avoid assigning a GL account and maintain the material in stock and value using account assignment category.
    Regards,
    Rambhupal reddy

Maybe you are looking for

  • Thoughts on Android 4.3 update

    Since there are so many different kinds of problems being reported after the last two Android updates I am wondering if the problem lays with a conflict between the two updates. 4.2.2 supplemental security update was only released a couple of weeks b

  • Address Book sync with .Mac

    I've done my Address Book sync with my .Mac in System Preferences. But the new addresses/changes don't show up when I go to email or look up the names from a web client. Am I missing somethings?

  • How do you fix error message "There is a problem with Adobe Acrobat/Reader. (6:6)

    How does one fix error message "There is a problem with Adobe Acrobat/Reader. If it is running, please exit and try again. (6:6)

  • One of the functional groups of the Logical Database "SDF" does not appear.

    Hello, I have a problem with the logical database "SDF". It has already defined 3 functional groups. When I select the buttom "display the contents" I can see all these groups with their owns fields. The problem is that when I use a transaction which

  • Contract opportunity for flex skin developer

    Hi, I'm looking for an experienced Flex developer to help me reskin my web service. I will supply the graphic design and a fullly functional system with about six screens implemented in Flex 3.5. Good communication and teamwork is a must since we'll