Procurement Without MRP Run

Hello,
Can anybody explain how the procurement process is done where company is not running MRP periodicaly?

Hi,
Basically MRP is the process which compares the requirement with the available stock and if there exists any shortfall will raise the procurement proposals.
How ever based upon the requirement for the material one go for manual creation of the PO based upon the PR created and procuring the material using the PO and made available this material by making the GR.This is the usual normal process.
Regards,

Similar Messages

  • Automatic Purchase Requisition using Reorder Point without MRP Run

    Dear Freinds,
    My client wants Purchase Requisition should be automatically created as soon as the stock falls below reorder level without MRP run.
    Is this possible? if possible then what are the settings required.
    Thanks
    Prashant Atri

    Dear,
    It is not possible in standard SAP.
    What is the problem to take MRP run?
    You can take the MRP run in background through MDBT so system will create automatic Purchase Requisition using Reorder Point.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Generating a production order through projects, without MRP run?

    Hi to all
    Is it possible to generate planned orders and further proceed to production order through projects  WITHOUT MRP run?
    Regards
    surya

    create the production order in CO01 and assign WBS element in the assignment tab of the order.
    whether it ll solve ur purpose....
    ashis

  • Secondary packing material procurement through MRP Run

    Hi
    Is it possible to procure Secondary packing material through MRP Run. Material type of Secondary packing material is VERP. In MRP view we defined MRP type as VB and reorder point also set.

    Hi
    the MRP run would create a procurement proposal if the stock has fallen below the re-order point. The procurement proposal needs to be a purchase requisition if procurement should start immediately (see Creation indicators for the MRP group). Further, you need to set the "automatic purchase order" indicator both on the material (purchasing view) and on the vendor. In the MRP run, the system also needs to be able to assign a vendor (i.e. through a source list). Then a purchase requisition is automatically converted into a purchase order on creation.
    Good luck
    Eivind

  • Process order required for each sales order without mrp run

    Hi, it is mto scenario. wants system to create a process order for each sales order without running mrp. please advise is it possible? if possible please guide what settings need to be done. Thabk you.

    HI
    You can create production order with reference  to sales order using t code CO08.
    Check and revert
    Regards
    Anupam Sharma

  • MRP run without one storage location

    Dear All,
    My client's requirement is they need to run MRP on plant level without considering one storage location stock
    e.g if a material is having stock of 10 in unrestricted with storage location 1104. Now when mrp is run for 100 quantity planned order is created for 90 only planning strategy is 40....they want the MRP should not consider the stock in storage location 1104.....how this can be made possibe?
    Please Suggest...
    Regards,
    Pawan Shetty

    Dear all,
    Pl. help me which user exit implemented  for MRP RUN without Storage location ,b'coz. from slandered setting we are not able to  do the same
    Regards
    Sandeep

  • Reg.MRP Run without sale order

    Dear Experts
    We are in need of MRP run without sale order. I have created Finished product material (T-Shirt) and assigned components to that and then I ran MRP, If I do so, MRP is exploded but result is not satisfied some non components are displayed.
    What is my requirement is ,when I run MRP if there is stock availble production order should be created otherwise Material requirement has to created.
    Pls help what is the configuration for MRP run,
    Thanks
    Rajakumar.K

    Hi Raja,
    One of your requirements isn't available in R/3.
    What is my requirement is ,when I run MRP if there is stock availble production order should be created otherwise Material requirement has to created.
    Standard MRP will create Dependent requirements (demand elements).  MRP will create order PROPOSALs (purchase reqs or planned orders)(supply elements).  MRP can be immediately followed by an additional program that will convert planned orders to Production orders.  All these things are possible.
    However, MRP will not check for the availability of components, and then selectively create production orders.  Availability check, which is not part of MRP, is usually performed at a later part of the production order cycle.
    Regards,
    DB49

  • Parallel MRP run for Internally and Externally procured materials

    Hello all,
    we want to run MRP with different settings for externally procured materials (create purchase Requisition) and internally produced materials. The choices provided my MRP run is either create planed order or Requisitions when run background. Is the activation of user exit M61X0001 the solution to this issue?  I can recall that we had done this is some project in the past, not 100% sure to be sincere. Can anyone help on this?
    Thank you for any help.
    Edited by: Ioannis Salichos on Aug 11, 2010 11:51 PM
    Edited by: Ioannis Salichos on Aug 11, 2010 11:57 PM

    you are right, this is the user exit that can be used to control this.
    see an excellent "how to use"  from R Brahmankar
    in this thread:
    Re: mass MRP run

  • Schedule Lines are not getting generated after MRP run.

    Hi,
    I have an issue where a SA exists for the parent material with item category L (subcontracting). The parent material has a valid BOM and some sub components as well. I see in CS03 that BOM is fine with validity dates for the parent material. A valid source list also exists for the parent material where SA is present as the source of supply with MRP indicator as 2. Now when i run MRP for the parent material using MD02 (NETCH), with indicators as below:
    Create pur.req.  2
    Schedule lines   3
    Create MRP list  1
    Planning mode   1
    i don't see any schedule lines in MD04. Instead it creates a PR that too without any source of supply.
    In master data for the parent material MRP type is PD with Procurement type F and special procurement key 30. I have checked and every thing seems to be fine still MRP run doesn't create schedule lines.
    Any help is appreciated. I can give more info if required.
    Thanks.

    Dear Rakesh,
    Scheduling agreement:An outline agreement against which materials are procured at a series of
    predefined points in time over a certain period.
    1.For this you have to first use ME31L for creating scheduling agreement and then ME38 for maintaining scheduling agreemnet
    schedule.
    2.Ensure in the source list after maintaining the material,vendor combination the setting for MRP relevancy is set to 2 - Record
    relevant to MRP,Schedule line generated automatically.
    Moreover you have to use value 3 for delivery schedule line which is one of the MRP control parameter while taking MRP run.
    So for the materials for which scheduling agreement exists,schedule lines will be generated.
    Check and revert back.
    Regards
    Mangalraj.S

  • MRP Run in an excluded Storage Location

    Hello all. I have this situation.
    I have material X with two storage locations: SL01 and SL02. Storage location SL01 has 15 pieces and SL02 has 5 pieces. In MD04, I can see a total of 20 pieces under the "Stock" MRP Element.
    Material X also has five Order Reservations (OrdRes), for 5 pieces each. These Order Reservations are assigned to Storage Location SL02, because stock is procured from there.
    What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
    I tried deactivating SL02 in Material Master MRP4 for material X, but then the MRP Run doesn't generate any proposals because my reservations are in SL02, and it's deactivated. Even if my Availability Check is set not to look at "storage location", if I the requirement is in SL02, it won't propose anything.
    Is there any other solution to my problem? How can I have the system ignore the stock in SL02, but still propose those 5 pieces I'm missing in SL01?

    I have material X with two storage locations: SL01 and SL02. Storage location SL01 has 15 pieces and SL02 has 5 pieces. In MD04, I can see a total of 20 pieces under the "Stock" MRP Element.
    Material X also has five Order Reservations (OrdRes), for 5 pieces each. These Order Reservations are assigned to Storage Location SL02, because stock is procured from there.
    What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
    Sorry, but your logic is not clear to me...
    your stock:
    5 pcs (SL02) + 15 (SL01) = 20 pcs
    your requirements
    5 x 5 pcs (SL02) = 25 pcs
    Procurment proposal (w/o excluding SLoc):
    20 pcs (stock) - 25 pcs (requirements) = -5 pcs > procurement proposal 5 pcs
    You are saying:
    What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
    So, you can see MRP will give a procurement proposal of 5 pcs without any SLoc exclusion...
    Please clarify your requirement / business process. Why don't you want to consider the stock in Sloc2? What is your process?
    You can see that you cannot exclude a SLoc with Sloc MRP and still consider the requirements relevant to that SLoc (unless you use reorder point planning in that SLoc).
    Thanks,
    Csaba

  • Schedule line date changes after each MRP run

    Dear Experts,
    Clarification needed on how the system plans the MM schedule lines.
    Setting: Start in the past not allowed.
                  3 days for processing of order
    The issue is after each MRP run the system is moving the schedule line to the current date + 3 days for processing + the planned delivery time.
    If the schedule line is not firmed, after each MRP run ( which happens everyday) the system is moving the schedule line and then giving an alert saying the " order has to be rescheduled to the previous day"
    on the second day after the mrp run the system moves the schedule line again by one more day and gives the rescheduling date as " -2 days from today"
    this change is happening every day after the planning run. - because of this there are really no backorders ( schedule line in the past ) in the system. we were not able to know if the vendor is actually delayed in this case.
    can you kindly suggest what went wrong here ??
    we are using strategy 10 for the planning of procured parts. Let me know if more info is needed.
    Note: we are also using stock transfer process for some procured parts. there too the PR date gets changed after each MRP run. There there is no lead time in this case. the order is placed on the same day as the requirement as both plants are nearby. There the PR date is changing everyday to the current date.
    your advice would be of great help
    thanks
    Nagendra Kumar

    Hi Caetano,
    thanks for your suggestion
    Yes, we use firm zone for few of the vendors. there the system don't change the schedule lines.
    Also for the stock transfer PR's there is no firm zone and the lead time is one day. in this case it changes everyday after the MRP run.
    the stock transfer PR's leads to the creation of Schedule lines from the source plant. Since this PR gets changed everyday. the alerts coming out of MD07 gets changed and we really did not know if this order is delayed or not.  In the source plant we use the firm zone to avoid moving the schedule line. But then the alerts are always not correct.
    is there any setting which helps in not moving the PR everyday without using " start in the past"
    thanks
    Nagendra Kumar

  • MRP RUN- KIT BOM explosion not working

    We setup one layer BOM’s for our maintenance KITs as parent material and components as child material.  For  example KIT is TS10000-K1 and components are TS10001, TS10002 etc setup as next layer with in the BOM. Both KITS and components are defined as material types ERSA (Spare parts). These one layers BOMs are setup as production BOMs and expected to create purchase requisitions for KITS and components by exploding BOMs during MRP runs. We use purchase requisitions and convert them into POs to procure both KITS and components. We DO NOT USE Panned orders and Production orders. 
    The safety stocks / reorder point are considered as demand for KITS and components as we do not have any external demand for KITS and components.  
    MRP run is creating purchase requisitions automatically for both KITS and components as per safety stocks and reorder point defined in MRP Views of Material Master. This is working as expected.  
    The issue is: KIT BOM’s are not exploding to generate purchase requisitions for the dependent components of KIT BOM. Please suggest the way to resolve this issue. 
    Split valuation: Also we plan to use split valued KITS with both new and refurbished. So we need BOM explosion for split valued KITS
    also (after the 1st issue is resolved).   
    I verified the following items to make sure the required configuration and data setup is defined correctly.
    1) Planning file activated Plant - OMDU 
    2) Executed MRP run with Total Planning - MDBT and MD02 (single item, multiple levels)
    3) BOM explosion for MRP activated- OS23 
    4) MRP type in MRP1 view- PD and VB (I tried both separately but BOM is not exploding).
    5) Procurement type “F” (MRP 2 view) and lot size “EX”  
    6) Planning strategy in MRP 3 view (tested w/o planning strategy and with strategies 10 and 40. But BOM is not exploded)
    7) BOM status and usage (status is active and usage is for production-CS02 and OS20)  
    8) BOM Validity date (Valid) 
    9) BOM structure in CS12 (BOM is exploding in CS11) 
    10) Availability check  
    11) Selection of BON ID to have BOM usage indicator assign (OS31).
    12) No alternate BOMs or production versions or work scheduling view are used.
    Please review the above 2 issues and suggest any workable solution. Thanks in advance!
    NOTE: I extensively used MRP with multi-level BOM explosion in my earlier projects without any issue. However the above issue is a  bit strange  why one layer BOM is not exploded in this case. 
    Regards
    Srini  

    Hi
    Thanks for your response. I reviewed all SAP notes and none of them are applicable to my scenario.
    1808396 - BOM changes not considered by MRP: I have not changed BOMs.
    1781324 - MD11: Valid BOM alternative is not found. We do not have alternative BOMs.
    1791009 - No BOM explosion after changing production version: We am not using production versions.
    Our Material KITS are PM spare assemblies set up as BOMs and consists of individual spare parts as components. We are creating purchase requisitions and not planned orders. We are not using PP functionality/Production orders.
    MRP is generating purchase requisitions for KITS and components as per ROP and safety stocks. In other words it is working as expected.  The issue is BOMs which are parent assemblies are not exploding to the next lower level components.
    Please note that I am not getting any error messages when MRP is executed.
    Regards
    Srini.

  • After firming planned order, new planned order is generating in MRP run

    Hi Experts,
    I am using SAP AFS. Planning strategy is 21- MTO with Project settlement. MRP type is PD. Lte size is EX. Procurement type is X.
    We are using the production versions. Individual / collective reqmts is 1. Planning time fence is not maintained.
    In sap AFS T.Code for MRP run is /n/afs/md02. After receiving the Sales order, MD04 screen gets updated accordingly and I am running the MRP.Planned orders are generated accordingly. I am firming the planned order manually through MD04. The satr mark is also appearing.
    My problem starts now. If I am running  the MRP again for the same requirements another planned order of the same qty. is getting generated. That means after the second MRP run, I am having two planned orders (one firmed plnd order) and second is the new planned order. My requirement is that MRP should not generate any new Plnd. order / PR's if there is no new Sales order.
    The parameters for MRP run are "1" for "Create PR's", '1" for "Plng Mode" and '"1" for "scheduling ".
    I have tried in all the possible ways, but of no use. Still new plnd order is generated after firming the 1st plnd. order in MRP run.

    Thanks all for your feedback..
    @ Vishal
    1. Yes, Both Old firmed planned order and newly generated planned order have the same grid value
    2. For both the planned orders :
    Special Stock is E u2013 Orders on hand,
    Consumption is V,
    Sales order is the same (As we are using MTO , Strategy 21) and same WBS element.
    3. First planned order is not in the assigned tab of MD04. This means that has been allocated to some object. u2013 I didu2019nt got this point. Can u please elaborate?
    @ Nikhil
    1. Quantity of sales order is not reducing after firming the sales order
    2. Account assignment category for both the planned orders is u201CZu201D - Indiv.cust./project
    I have made some more observations and found the following differences between the two planned orders
    From  MD04 , keep the cursor on corresponding planned order
    & click on upward arrow ( available on bottom side of the report).
    It will show what will be the originating requirements i e. for which requirements this planned order generated.
    For Firmed planned order it is taking me to screen u201CPegged Requirements
    u201D*And the following data is present:
    Planned dates: 04.07.2010
    MRP element No. 3100001185 (Sales Order No.)
    MRP element item 100
    Scheduling No. is 1
    MRP element indicator - VC u2013 Order
    MRP element data- 3100001185/000100/0001
    Plng segment u2013 3100001185000100000
    P.O / Order Type u2013 ZX
    Rec/reqd Quantity 10
    MRP element u2013 Order
    For new planned order generated, I am going to Screen *u201CProcurement without Requirementsu201D
    *The following data is present
    Planned date 03.07.2010
    MRP element No. 0000123522 (Planned order No. of the newly generated after MRP Run)
    MRP element Ind. u2013 PA
    MRP element data 0000123522/SO
    MRP element item 1
    Scheduling No. 1
    MRP segment 20
    Plng segment u2013 3100001185000100000
    Rec/reqd Quantity 10
    P.O/Order type- KD
    MRP element u2013 Plnd Order

  • Exclusion of Stock Transport specific MRP Elements from MRP Run

    Hi,
    How can we exclude specific MRP Elements from planning?
    I want to exclude the MRP elements like - Ord.DS, PRqRel, PlORel etc from MRP run.
    (After MRP run, they should only be displayed in MD04 and not planned)
    MRP run should treat all other MRP elements normally.
    Warm Regards,
    Madhavi.

    I think I understand what you want to do, and I think it is not possible without some major MODIFICATIONS, because it goes against the grain of what MRP is supposed to do: balance demand and supply.
    One thing you might consider as a possible work-around: create a "virtual plant" say 5000, that is a plant that isn't really used for anything. Then point your special procurement keys in plant 2000 to plant 5000. This is where you then get the purchase req releases etc, and they will not affect plant 1000.
    This doesn't require modifications... but it will also not display the elements in MD04 for plant 1000.
    Just an idea...

  • MRP RUN ON PURCHASE ORDER

    Hello
    i want to run mrp for inter plant purchase order, in this case i don't want to create sales order for the purchase order received from alternate plant, is it possilble to run mrp on all purchase order item without creating sales order to it?
    Regards
    Nishj

    Hi,
    I think a STO (Stock Transport Order) flow should meet your need.
    In OMD9 define a special procurement key for plant which is sending you the PO.
    For the special proc key maintain Proc type as F, Spl. prc type as U, then specify Plant - 2 in plant field.
    In MRP - 2 view of the mtl in Plant - 1 maintain this special procurement key.
    Now when MRP runs in plant - 1, it will generate a stock transport requisition for Plant - 2.
    In Plant - 2 maintain a procurement key say E if its in-house. Run MRP for plant - 1 first followed by Plant - 2.
    This way you wont have to follow the PO - SO flow.
    Hope it is clear.
    Regards,
    Vivek

Maybe you are looking for

  • Ipod nano 7th keeps flashing and won't turn on

    my ipod nan 7th generation is flashing on the blue screen and I can not turn it on...

  • Closing of periods

    hello,        please tell me , how can we correct the period of material document if we do post in wrong period.

  • Keyboard response issues in flash player

    Hi, When I'm playing games made with flash, every so often it won't respond to my keyboad inputs.  It happens maybe every 30 seconds, so it's pretty regular, and won't respond for a few seconds.  If I was holding a key at the time of this hanging, th

  • Problems with JRE installation 1.6.0_18 in silent mode

    Hi! I have problems with installing the JRE from the cmd line in silent mode and in a directory with spaces in the path. If I remove the spaces in the INSTALLDIR, the JRE installs in the directory I have specified but not when I use spaces in the pat

  • Ipad 2 won't update to ios 5 no matter what I try

    I've literally tried everything, I've deleted my itunes twice to make sure I had itunes 10.5. Then everytime I go a try and updat it will take almost 4 hrs and once at 3/4 of the download it will say I have a network issue and go back to zero. I just