[Project Pro 2013] User Custom Field w/ Formula does not calculates on Group Tasks

This issue happens only on Project 2013. When I make a formula (using Duration, Cost, Number, etc...) on a custom field and set "Use formula" option in "Calculation for task and group summary rows",
works fine without groups, on resume tasks. But when I Group the tasks, the group tasks values disappear.
When I open the same file on Project 2010, it works correctly.
Thanks in advance.

Thank you for the effort. This problem is a bit tricky and hard to explain without images or files.
I'll try to explain using your example:
- I do not coded my summary tasks with the value in the "Text1" field and
- I do not want to maintain hierarchy on groups like you show.
1. On "No Group" mode, the summary tasks works fine. All summary tasks shows the values calculated by the formula. Summary tasks are not the problem.
2. However, when you group the tasks by Text1, the Group Tasks (the colored ones that appear on group mode: Group: a, b and c) do not show the values calculated by the formula, even if you set to "use formula" on summary and group tasks.
3. When you open the same file on Project 2010 (default configs), group tasks values appears (values calculated for the groups of the detail tasks: a, b, c). If your Duration1 field stays the same or disappear, change some values and refresh the field to check
the formula is working.
4. If you see that everything are working correctly so far, try this on your file:
4.1. Maintain your tasks grouped by Text1.
4.2. Add three Fields: "Duration2", "Duration3" and "Duration4".
4.3. On every detail tasks, enter 2 days for Duration2, 3 days for Duration3.
4.4 Set Duration2 and Duration3 to "show Average" value on the resume and group tasks. Set the Duration4 to "use formula".
4.5. Create on Duration4 field a simple formula, like [Duration2]+[Duration3], or [Duration2]/[Duration3].
4.6. See that the formula works fine the detail tasks (Duration4 = 5 days).
4.7. Now the problem: The group tasks shows nothing. Duration4 should be calculated (average duration2: 2 days + avg duration3: 3 days = 5 days).
4.8. Save the file and open on Project 2010. If the resume tasks on Duration4 continues to show nothing. Refresh the field by clicking right button on field and going to "Custom field" and pressing OK.
See that Duration4 are calculated on Project 2010 correctly, but not on 2013 version. That is the problem
Thanks again. I hope it helps.

Similar Messages

  • Error in formula field: Column 'TASK_BCWP' does not belong to table Task

    Hi,
    We have a formula field to calculate the a cost KPI and that field throws an error in the ULS logs. The error is: PWA:PWA, ServiceApp:Project Server Service Application, User:GDFN\IPL_Content, PSI: SSP: Formula Evaluation Failed! - trying to continue - (System.ArgumentException:
    Column 'TASK_BCWP' does not belong to table Task.
    We are running EPM 2010. Recreating of the custom field did not work. We are not running with the latest CU yet.
    The formula that we use is:
    IIf([BCWP] > 0; [ACWP] / [BCWP]; 1)
    The stack trace from the ULS log is:
    PWA:http://gdfn-ipl-14/PWA, ServiceApp:Project Server Service Application, User:GDFN\IPL_Content, PSI: SSP: Formula Evaluation Failed! - trying to continue - (System.ArgumentException: Column 'TASK_BCWP' does not belong to table Task.
    at System.Data.DataRow.GetDataColumn(String columnName)
    at System.Data.DataRow.get_Item(String columnName)
    at Microsoft.Office.Project.Server.BusinessLayer.FormulaDataProvider.HaveColumn(DataRow row, String columnName)
    at Microsoft.Office.Project.Server.BusinessLayer.FormulaDataProvider.GetTaskData(Guid nodeId, Int32 fieldId)
    at Microsoft.Office.Project.Server.BusinessLayer.FormulaDataProvider.GetDataInternal(Int32 entityId, Guid nodeId, Int32 fieldId, Boolean canChangeEntity)
    at Microsoft.Office.Project.Server.BusinessLayer.FormulaDataProvider.GetData(Int32 entityId, Guid nodeId, Int32 fieldId)
    at Microsoft.Office.Project.Server.BusinessLayer.Formula.FieldExpression.Evaluate(IFieldEvaluator context, Guid nodeId)
    at Microsoft.Office.Project.Server.BusinessLayer.Formula.GreaterExpression.Evaluate(IFieldEvaluator context, Guid nodeId)
    at Microsoft.Office.Project.Server.BusinessLayer.Formula.ConditionalExpression.Evaluate(IFieldEvaluator context, Guid nodeId)
    at Microsoft.Office.Project.Server.BusinessLayer.Formula.FormulaEvaluator.Evaluate(PlatformContext context, Expression formula, Int32 entityId, Int32 fieldId, Guid nodeId, Dictionary`2 entityFormulaFields)) + -- FieldId = 188776525 -- NodeId = 1b1149c1-52c2-4f7f-ba60-6d65effdb6b3
    -- Formula = IIf(Greater([MSPJ188743691], 0), Divide([MSPJ188743800], [MSPJ188743691]), 1)
    I have no clue where to start looking for the cause of this error. Any help would be appreciated.
    Thanks,
    Quint Mouthaan

    Hi Quint,
    This can because of database fragmentation. I would recommend you to re-index the databases and perform a de-fragmentation and can check the behavior.
    On the other hand when you receive this message, you can try an IISRESET and check. Additionally you can use refer to following link for de-fragmenting queries.
    http://support.microsoft.com/kb/943345
    Happy troubleshooting.
    Vikram Daruru - MSFT

  • Project server 2013----new custom field value is not synced between my work assignment view and project professional

    Hi All,
    I would like to add a new custom enterprise field in project server to caculate the effective work. I hope it can work as the default field "work" and "overtime work". And I add my custome enterprise field to my work assignment and the
    related details view. User can update the values in "my task" but after PM accept the updates, these values are not synced to the project center as well as project professional. Any idea?
    Regards,
    Anna

    Yes, I am saying that the PM cannot see the updated values in the enterprise project in Microsoft Project 2013. It is a task custom field. No errors for it. Would you please help create a task custom field on your side to see whether you can reproduce
    this issue? After creating the field, please add it to the "My task" related views so that project members can update the value for the task when they update the task information under "my tasK" page. After that, open the project plan as
    project manager to see whether you get the updated value. Thanks a lot!
    Regards,
    Anna

  • FOX Formula does not calculate ratio

    Dear guys,
    We are customizing the process for calculation of data which will be used for elimination of profit/loss in stock and revenue and expenses during consolidation of manufacturing companies group's financials.
    At the moment we're customizing a FOX Formula for calculation of share of revenue from (source) materials sold to other companies inside the group and used for production of other (target) materials and total revenue received for each of these source products.
    We use the following key figures and characteristics in the level:
    0CS_VERSION     Consolidation (End-Result) Version
    0CURKEY_GC     Currency Key for Group Currency
    0FISCPER3     Posting period
    0FISCVARNT     Fiscal year variant
    0FISCYEAR     Fiscal year
    0MOVE_TYPE     Movement Type
    MPZZFKOD     Source Material Consolidation Code
    PRODUCER     Company - Producer
    SL_TYPE          Sales Location Type: Export/Domestic
    TRG_COMP     Target Company
    ZZFKOD          Target Material Consolidation Code
    COGSGGC     COGS Gross GC
    SREVENGC     Revenue Statistical GC
    VS_SUPSH     VS Supplier Share
    MPZZFKOD ZZFKOD     TRG_COMP  COGSGGC    SREVENGC      VS_SUPSH
    2651     #      #           0             10.070.099     0,00000
    2651     2703      3           21.000              0                     0,00000
    2651     2704      3           19.116              0                     0,00000
    We need to calculate a ratio of COGSGGC for each ZZFKOD and total SREVENGC. (21.000/10.070.099 and 19.116/10.070.099).
    Below is a program code:
    DATA SUM_KF TYPE F.
    DATA SHARE  TYPE F.
    DATA FLAG   TYPE I.
    DATA KEYFIG TYPE F.
    DATA L_ENTRIES TYPE I.
    *DATA L_ZZFKOD TYPE  ZZFKOD.
    *L_ZZFKOD = VARV(TMCONSCD).
    *DATA L_MPZZFKOD TYPE MPZZFKOD.
    DO.
    IF FLAG > 1.
    EXIT.
    ENDIF.
    ENDDO.
    L_ENTRIES = VARC(VERSION).
    *SUM_KF = 0.
    *FOREACH L_MPZZFKOD.
    SUM_KF = SUM_KF +
    *{SREVENGC,'#','#'}.
    *ENDFOR.
    *SUM_KF = SUM_KF + {SREVENGC,'#','#'}.
    *FOREACH L_MPZZFKOD.
    SHARE = {COGSGGC,L_MPZZFKOD,'#'} / SUM_KF.
    {VS_SUPSH,L_MPZZFKOD,'#'} = SHARE.
    *ENDFOR.
    *SUM_KF = SUM_KF + {SREVENGC,'#'}.
    *FOREACH L_ZZFKOD.
    *SUM_KF = SUM_KF + {SREVENGC,L_ZZFKOD}.
    *ENDFOR.
    *DO.
    *IF FLAG > 1.
    *EXIT.
    *ENDIF.
    *ENDDO.
    *FOREACH L_ZZFKOD.
    *SHARE = {COGSGGC,L_ZZFKOD} / SUM_KF.
    *{VS_SUPSH,L_ZZFKOD} = SHARE.
    *ENDFOR.
    Could you help us to understand the reason the program does not work?
    Mila

    Mila,
    I see some issues with your logic:
    1. you are not using fiscal period at all but you declared it.  Is it in your field to be changed or just in your field for condition or package / filter?  Also version 0CS_VERSION?
    2. What is the purpose of Flag > 1?
    3. You are very confused in your looping logic...  You need to think more logically about what you want to do
    4. What is the 3rd items in your fields to be changed?  If you don't use it or change based on it in the FOX, remove it from fields to be changed.
    You want to process for each source material MPZZFKOD (I persume for each fiscal period) and within each source material MPZZFKOD, you want to loop through each target material ZZFKOD.
    Note: the items in the {} depends on the order of your to be changed characteristics
    Give this (or a similar version to this) a whirl.
    DATA SUM_KF TYPE F.
    DATA SHARE TYPE F.
    DATA L_MPZZFKOD TYPE MPZZFKOD.
    DATA L_ZZFKOD TYPE ZZFKOD.
    FOREACH L_MPZZFKOD.
      SUM_KF = {SREVENGC,L_MPZZFKOD,'#'}.
      FOREACH L_ZZFKOD.
         SHARE = {COGSGGC,L_MPZZFKOD,L_ZZFKOD} / SUM_KF.
         {VS_SUPSH,L_MPZZFKOD,L_ZZFKOD} = SHARE.
      ENDFOR.
    ENDFOR.
    You can even do without the share if you map it directly.
         {VS_SUPSH,L_MPZZFKOD,L_ZZFKOD}
                = {COGSGGC,L_MPZZFKOD,L_ZZFKOD} / SUM_KF.
    Hope this helps.  Sounds like you need to read up on some documents on FOX and/or practice with it.
    Mary

  • Date and Time Submitted in Task Notes to show in Project Pro 2013

    I wonder if anybody could assist.
    I am running PWA 2013 and Project Pro 2013
    When a resource updates a task on PWA and creates/updates the notes on the task, it pulls to the notes section for the task in Project Professional.  This is great but…
    Is there a way to pull the Date and Time Submitted next to the resources’ name in the note too?
    I would appreciate any assistance.
    Many Thanks :)

    Hi,
    I don't think this is feasible out-of-the-box. Note that the information is available in the task details when you click on the task (either in the task update page or in the approval center).
    A workaround would be to train the users to start their comments by typing their initials and the date-time.
    Another way more complex would be to do some custom code.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Server 2013 - Graphical Indicators - Not showing until the project is published via Project Pro 2013

    Greetings -
    I have a custom field on a PDP that is used to manually flag a project for review.  Once the field is set to "Flag" a red flag should show on the Project Summary page prompting the Portfolio Manager to follow up.  The red flag only appears
    after publishing the project via Project Pro 2013 not by just editing the PDP via Explorer (Save and Check in).
    This occurs on both projects that were created prior to the graphical indicator being added to the PDP and new projects.
    Now if instead of using the red flag graphical indicator I just used the text "FLAGGED" that would work fine.
    So is this a bug?  Or is something setup incorrectly?  Or is this how PWA is supposed to handle graphical indicators on the project summary page?
    Any help would be much appreciated.

    Hi Gunnery,
    I made the following test: I create 2 project ECF both inserted in the Project details PDP:
    for review: flag type field with graphical indicator in case value = yes
    for review_2: text type field (with a yes/no look-up table) with graphical indicator in case value = yes
    Whitout going to Project Pro, I'm able to modify the 2 fields for any project (created before or after the ECFs creation) and the graphical indicators are instantaneously shown in the summary project center view (just pressing F5).
    Note that the graphical indicator is not shown in the PDP, just the text value. Note also that I've not been to Project Pro neither to PWA/schedule PDP to publish the project plan.
    Then
    Does that correspond to your need? Can you reproduce this example and validate wheither or not it works.
    Guillaume Rouyre - MBA, MCP, MCTS

  • MS Project Pro 2013 won't activate on Win 8.1 Pro

    Hi there. I'm trying to install Project Pro 2013 and Visio Pro 2013 (both MAPS apps) to a Windows 8.1 Pro machine. It has a copy of Office 365 installed just in case that makes a difference. It's also using a domain login.
    Anyway, If I try to activate, the key seems to be accepted but it doesn't 'stick' and once the app closes down I need to reactivate again.
    Using the product key, I've tried activating at...
    The First dialog when opening the app
    At the "PRODUCT NOTICE. Project hasn't been activated..." bar
    Programs and Features > MS Project Pro 2013 > Change > "Enter a product Key"
    None of which work.
    I've also tried
    Uninstalling and reinstalling
    Using our MAPS account login (something I'm trying to avoid)
    Attempting the above activation in Administrator mode where possible
    Is there anything else I can try?

    Hello Daleos
    That is very weird indeed. I don't have a good answer. Make sure that Office and Project are using the same bit version.  Don't mix.  For example if office is running 64-bit then make sure that Project is 64-bit.
    Cheers!
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • Project Pro 2013 60 Day Trial....didn't last 60 days

    I download and installed the Project Pro 2013 60 day trial and it disabled most of the features after about 7 days. Does anyone know if this can be fixed so that I can use the entire 60 days?
    Many thanks in advance if you know the answer.

    Soloanom, I anticipate you might be bounced around with a problem like this, but I think that what you're experiencing is due to the design or a problem with the project product itself, and so you'll need to ask the office experts over in the office-related
    forums for assistance.  
    Unfortunately your post is off topic here, in the TechNet Site Feedback forum, because it is not Feedback about the TechNet Website or Subscription.  This is a standard response I’ve written up in advance to help many people (thousands, really.)
    who post their question in this forum in error, but please don’t ignore it.  The links I share below I’ve collected to help you get right where you need to go with your issue.
    Soloanom, the two links in this paragraph are your best bet: For technical issues with Microsoft products that you would run into as an
    end user of those products, one great source of info and help is
    http://answers.microsoft.com, which has sections for Windows, Hotmail,
    Office, IE, and other products. Office related forums are also here:
    http://office.microsoft.com/en-us/support/contact-us-FX103894077.aspx. 
    For Technical issues with Microsoft products that you might have as an
    IT professional (like technical installation issues, or other IT issues), you should head to the TechNet Discussion forums at
    http://social.technet.microsoft.com/forums/en-us, and search for your product name.
    For issues with products you might have as a Developer (like how to talk to APIs, what version of software do what, or other developer issues), you should head to the MSDN discussion forums at
    http://social.msdn.microsoft.com/forums/en-us, and search for your product or issue.
    If you’re asking a question particularly about one of the Microsoft Dynamics products, a great place to start is here:
    http://community.dynamics.com/
    If you really think your issue is related to the subscription or the TechNet Website, and I screwed up, I apologize!  Please repost your question to the discussion forum and include much more detail about your problem, that could include screenshots
    of the issue (do not include subscription information or product keys in your screenshots!), and/or links to the problem you’re seeing. 
    If you really had no idea where to post this question but you still posted it here, you still shouldn’t have because we have a forum just for you!  It’s called the Where is the forum for…? forum and it’s here:
    http://social.msdn.microsoft.com/forums/en-us/whatforum/
    Moving to off topic. 
    Thanks, Mike
    MSDN and TechNet Subscriptions Support <br/> Read the Subscriptions <a href="http://blogs.msdn.com/msdnsubscriptions">Blog! </a>

  • MS Project Pro 2013 - Auto Level (Not responding)

    Hi,
    One of our users has an issue in MS Project Pro 2013 with Automatically levelling (See below). Can anyone suggest what the possible cause of this is? The user is running Windows 8.1 Pro and more than enough RAM + Graphics card is fine.
    I would start with the both the Resource Pool and Sharer projects open (as I’m supposed to).  When I select ‘Auto Level’, MS Project would then turn the mouse
    into a swirl circle and state (Not Responding) at the top of the page.  If I hovered over the MS Project symbol pinned to my task bar, I would notice that it had opened a third window, though I couldn’t see what that project was as it was greyed out. 
    I tried this a number of times and had the same result.
    Thank you

    Intellitrain --
    Given the fact that no one else has replied to your post, let me just take a stab at it.  A couple things come to mind:
    Is the project in question a LARGE project with a large number of tasks and resources (maybe numbering in the thousands of tasks and resource assignments)?  If this were the case, leveling all overallocations at once would take a long time, which could
    be why the software seems to go into Not Responding mode.  By the way, I have seen Not Responding messages a lot in Project Server 2010 and 2013 when opening a very large enterprise project.  Microsoft Project shows the Not Responding message, even
    though it is actually working at opening the project.
    If the project is not a large project, but is smallish in size, then the user might try opening both the project and the shared resource pool file in Read/Write mode, disconnecting the project from the shared resource pool file, saving and closing both
    files.  Then the user should reopen both the project and the shared resource pool file, reconnect them, and save both of them again.  Then try leveling.  Does the problem still occur.
    If this does not help, there is a possibility that the project is corrupted.  If this is the case, the user should disconnect the project from the shared resource pool file and save it.  Then the user should save the file as an XML file and close
    the project.  Finally, the user should open the XML file and save it back as an MPP file.  This is how to resolve a corrupted MPP file.
    Just a few thoughts.  Hope this helps.
    Dale A. Howard [MVP]

  • MS Project 2007 - Help with custom field calculation for grouped by dates view

    Hello 
    I am trying to creat a view that counts number of students in courses (while # Students is a custom field that is filled manually and courses are tasks).
    The view should be grouped by Quarters, Months, and weeks (Calculated custom Text fields)
    The weeks groups are displayed by the start day of each week.
    For example:
    The view counts how many students are in courses in a specific week/month/quarter.
    This is the group by definition:
    Those are the fields calculations:
    “WW_Start” field calculation:
    (Year([Start]) & "  W " & Format([Start],"WW") & " " & "   [" & Datevalue(ProjDateSub([Start],CStr(Weekday([Start])-1),"Standard")) & "]")
    “MM” field calculation:
    Year([Start]) & "  M " & Format([Start],"MM")
    Basically it works but it doesn't cover a situation where a course is more then a week.  
    Lets say that the duration of the task is 12 days, the task should appear on 3 different weeks groups.
    But what i did puts the tasks only in the group that shows the first week of the task.
    How can i change my calculations or my view so that in the second, and third week of the task it will also show the task and it's attributes.
    For example:
     - "UV5 ACM" task should also be in W 45 not just W 44.
    Anyone has an idea how to do that?
    Ofir Marco , MCTS P.Z. Projects

    Hi
    First, thanks for the comment "nice neat groups" :)
    I think you understood correctly what is my issue.
    Second, about your question:  the class have the same number of students during the course period.
    It will have 10 students even if the duration is 1 day or 10 days.
    if you look at the basic gantt chart you will see a row like this:
    Task name        Duration        Num_Students     Resource names (Instructors)
    Course YYY       10d                10                       
    Instructor X
    it is an attribute on the task, not the assiment.
    When i group by dates (Weeks, months, quarters) or by another field (can be course type for example) i the students are summed in the task summary level for all tasks.
    Lets say i group by all the tasks (Classes) that are in the 1st quarter, and lets say for the example that there are 3:
    Task 1 -->  5 students
    Task 2 --> 10 students
    Task 3 --> 7 students
    Then, the group by summary should count:
    Quarter 1 - 2014:   22 (students)
    Task 1 --> 5
    Task 2 --> 10
    Task 3 --> 7
    By the way, it doesn't matter if the version is project 2007,2010, 2013, the logic is the same.
    Hope it helps and i'll be glad to have some ideas or evan get examples for solution in a project file by e-mail.
    Ofir Marco , MCTS P.Z. Projects

  • Cut and Paste with MS Project Pro 2013

    We have and issue where if we try to Copy and Paste a task in MS Project Pro 2013, the PASTE option is not highlighted and we cannot do this. We can copy and paste field in the project but not a task. The task include enterprise fields and I tried to Cut
    and Paste even in off-line mode and it does not work.
    Anybody has an idea?
    Thanks

    Hi Johan,
    This normally happens when a sort is applied to the view. Sorting by ID then solves the problem.
    Greetings,

  • Saving MPP to SharePoint 2013 site from Project Pro 2013 fails

    When syncing from MS Project Pro 2013 to SharePoint 2013 it does not save the MPP file in the Site Assets
    Have MS Project Pro 2013, SharePoint 2013, IE 9, Windows 7
    The scenario is as follows.
    1. Have a SharePoint Project site
    2. I open up the task list in the SharePoint site and added tasks just using the available default fields that are provided. NO external links
    are in the task list.
    3. Selected the Open with MS Project option in the task list ribbon. MS Project 2013 launched from my desktop with the task list opened in it.
    4. In Project selected the Sync with SharePoint option and it did sync successfully with task list but it did NOT save the project file in the
    SharePoint site.  In addition, No error or warning message appeared.
    5. Selected Save button in MS Project – again it did not save to SharePoint but instead brought up the Save As screen again.

    Karen,
    To the best of my knowledge synching a Project file with a SharePoint task list and saving the project file to a library on SharePoint are two separate processes.
    You may synch the file to the SP list and then save the Project file to a library.  Are you using Project Server?

  • Project Pro 2013 with Project online

    I want to confirm that Project Pro 2013 can connect to Project online in the same way that Project Pro for O365 does. In other words, is it largely a licensing difference in the way the two products are licensed?

    Hi,
    See my reply about a similar concern: 
    http://social.technet.microsoft.com/Forums/projectserver/en-US/85889598-c54f-4168-a662-91b77211f81f/how-to-work-with-status-date-and-option-reschedule-uncompleted-work-to-start-after-in-project?forum=projectserver2010general
    And a useful reference:
    http://blogs.technet.com/b/nitinsha/archive/2013/06/24/project-online-or-project-server-2013.aspx
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Pro for Office 365 vs. Project Pro 2013

    Hello,
    As I already have Project Pro 2013 installed on my PC (which is able to connect to Project Online) I'm not sure if the MS Project I'm using is Project Pro for Office 365 vs. Project Pro 2013.
    Is there any difference in the interface of the 2 products, as there is a noticeable difference between Word 2013 and Word Web App?
    Thanks

    Hello,
    Project Pro 2013 is the same product as Project Pro for Office 365.
    Word 2013 and Word Web App are totally different, Word Web App is web based, Word 2013 is the client tool.
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Cache directory of Project Pro 2013 connected to Project Online

    Hello,
    Where is located the local Cache directory for Project Pro 2013 connected to Project Online ?
    Thanks

    Check here
    HKey_Current_User\Software\Microsoft\Office\15.0\MS Project\Options
    once you will be in Option --> Save --> Cache Location -->Click
    on Browse 
    You can also try form Open MPP --> File --> Option --> Cache location --> Click on Browse 
    kirtesh

Maybe you are looking for

  • 1toN bpm

    hi friends, i am working on file to file scenario using 1:N BPM my design is like this in sender sidei took one output message interface ,one abstract interfce in receiver side i took two inbound interfaces and two abstract interfaces. I have done us

  • Getting error in OSB :: FATAL Alert:BAD_CERTIFICATE - A corrupt or unuseable certificate was received..

    Hi There, am getting error when invoking a webservice from OSB . "The invocation resulted in an error: FATAL Alert:BAD_CERTIFICATE - A corrupt or unuseable certificate was received..". certs were loaded to the trust store and could see certificates i

  • WSDL 1,2 supported

    Is WSDL 1.2 supported in 11g SOA? Thanks - Casey

  • Form freezing issue forms 11g

    Hi All, In Oracle forms 11g, after selecting radio button, press any key from keyboard form will goes unresponsive mode(freeze). I was tried to catch event firing while pressing a key from keyboard using debugging and Trace events , but it not showin

  • NI-5640R Labview 8.2 problem

    Hi, I just upgraded my Labview 8.0 to 8.2, and when I tried to run a program NI-5640R example, it said 'Unsupported item/ The plug-in for selected item is not isntalled to your system.' Does anybody know why it gives me this message? and I have FPGA