Reason for delay on the DS planning board grafic

Dear SAP Fans
Have you done any development on the DS planning board to show reason of the delay of a planned order?
We are implementing PP/DS and this is a hard requirement for the acceptance. The users have another schedule system with this functionality, when an order is delayed you can see the reason in the chart by clicking on the delayed order. When they see the reason they can see all the constraints that prevent the optimizer to schedule the planned order in an early date, for example:
- Order 0001 is delayed to 15.04.2011 because;
         - Reason 1:  Machine A is unavailable up to 30.03.2011
         - Reason 2 : Componente 0001-01 have purchase order scheduled to 15.04.2011
         - Reason 3 : PRT is under maintenance up to 10.04.2011
With this information on hand the user can take some actions to antecipate the order in case this order is causing delay on a priority A customer order. For example the actions could be:
          - For reason 1, rearrange orders in the machine to schedule the order in an early date.
          - For reason 2, negotiate with supplier an early delivery date.
          - For reason 3, negotiate with plant maintenance to accelerate it.
Maybe something related to look for the delay log of a specific order.
Appreciate any insight.
Thanks and BR

hello,
first check the operations of the order.
right click on the produce operation and navigate to Order Processing.
In the order tree open all nodes for operations.
Is the set up activity visible there?
If yes doble click on the activity.
does the set up activity have a duration?
If yes check the status of the set up activity.
go back to the planning board.
in the menue select extras-> Legend
a pop-up with the graphical objects is displayed.
Check the graphic objects for the activity status you read before.
did you change the customizing settings for the graphic object?
If yes check them again or reset them to the default SAP settings.
I had a similar problem with a set up activity when I wanted to change the color of the activity according to the set up group. I  changed the settings in the customizing Maintain Planning Board Profiles.
It is very difficult to maintain the decision table for graphical objects.
If you did this recheck the decision table.
Go back to the SAP default settings and check the planning board again.
Are the set up acitvities displayed now?
Then the porblem is with the decision table.
rethink every step again.

Similar Messages

  • Default print settings in the Project Planning Board CJ02N CJ2C

    Hello
    When you print the Project Planning Board CJ02N/CJ2C - there is an option to change the page setup.
    I would like to change the default settings for left,right, top and bottom margins for all users.
    Can anyone suggest where this would be done ?
    Thankyou
    Ros

    Hi Varun,
    Thanks for the fast repply!
    Please see below the CJ2C and CNE5 screen shots:
    Thanks and Regards
    James

  • I want to know Reason for delay in activation of ODS

    Hi,
    I am using 3.x ver. normally ODS activation took 21 - 30 mins to activate but sometimes it took 6-8 hrs to activate.
    for eg.
    Yesterday it took 21 mins to activate 9,24,033 records and it added records were u201C1847245u201D but to day it took 8 hrs 13 sec to activate 877,560 records and it added  u201C3507974u201D.
    I checked the server also at that time server had not too much load.
    This job started at 07:13 and finished at 15:26.I checked job log also.
    07:13   SQL-END:22:08:2009 07:13:40:00:00:27
    15:26   Activation start at 07:13:40
    15:26  Activation finished at 15:26
    15:26 Request.......
    15:26 Request.....
    15:26 Data pkgs.......
    could you please help me to findout the reason for delay in activation of ODS. I am not able to findout what happened in first two lines in above job log.
    Thanks,
    Manish

    Hi Manish,
    When you want the resolution, you should have answered the quetion made by Markus Doehr, He such a qualified consultant you did care to follow up your issue.
    Thank you,
    Prasaad

  • Network Header at  the Project Planning Board gantt chart

    Hi again,
    Does anyone knows a configuration to allow the network header to appear in the project planning board gantt chart?
    Tks
    James

    Try transaction OPT7
    Double click on the appropriate Profile
    On the Table Area Tab, select the flag for the field "Display Network"
    Hope this helps
    Regards
    Steve

  • EM Jobs Service is down (fatal).  Reason - "Reason for delay could not be determined"

    Hi all -
    I'm having a problem with my em jobs service.  It's listed as down.  Severity is "Fatal".   For the incident creation DATE it has the following:
    "Reason for delay could not be established."
    Note that it's the DATE column where it ways that the reason could not be established.    Under "message" it has Dec 28, 2013 8:46:29 PM. 
    Target Name
    Target Type
    Severity
    Message
    Incident Creation Date
    Incident Last updated Date
    Escalation Level
    EM Jobs Service
    EM Service
    Dec 28, 2013 8:46:29 PM
    Reason for delay could not be established.
    Jan 27, 2014 7:48:44 PM
    None
    Does anyone have any clue as to why this is happening and/or how to fix it?
    Thanks,
    Tom

    Hi,
    Follow the below steps
    1. Click on Repository Database Target in Cloud Control
    2. Navigate to : Administration -> "Oracle Scheduler" -> Home -> click on "Oracle Scheduler" it will return, "Scheduler Jobs"
    3. Check that the scheduled jobs are running at their correct schedules.  Check if the "EM_JOBS_STEP_SCHED" job is disabled.
    4. Select "EM_JOBS_STEP_SCHED" and click on "Edit job Definition" ensure that the job status is "enabled". Then click apply.
    5. Check the "EM Jobs Service" status , it should now be shown as UP.
    Also
    1. Login to 12c Console, Targets --> All Targets --> EM Jobs Service
    2, click on Monitoring Configuration tab
    3. click on System Configuration
    In the Availability Definition screen, under Key Component column, check all the check boxes
    4. Similarly, in the System Configuration screen, under Key Component column, check all the check boxes
    Wait for 5 minutes and then check the status of the target again.
    Regards,
    Rahul

  • Mandatory field 'Reason for Delay" required in VKM3 Tcode application

    Hi to all
    We use tcode VKM3 to release the sales order for which credit limit check does not required.
    Our requirement is to add a mandatory field 'Reason for delay" so that we can write in that field what's the reason to releasing it through VKM3.
    Please guide me how to fullfill that requirement.
    Thanks & Regards
    Anubhav Gupta

    Hi Anubhav,
    Refer to the following very useful link:
    Re: Add new fields to VKM3 transaction
    Hope it helps.

  • Hiding the Optimizer button from the DS planning board

    Hi
    How to hide the optimizer button from the DS planning board ..
    Thanks

    Hi Chak
    I think the problem may be with a livecache inconsistency. The Planning Board should be reading it's information from the livecache, whereby the Product View may be getting it's situation from the database. Try running the livecache consistency checks if it occurs again.
    Regards

  • How to sets the Reason for Rejection of the Open Sales Order Lines

    Hello gurus,
              I want to set the Reason for Rejection of the Open Sales Order Lines, Case is like :
    If current date is exeed the Auto Void Confirmed Back Order Days(for item level) +  date (last responding from customer), then reason for rejection should be set, So i want the logic to find out the date is exceed or not.
    Thanks
    Anjana

    Hello anjana,
       Actually your question is some confusing, but if u want to get eldest change as active sales order then logic is as follows:
    1.  On base of OBJNR u have to get UDATE from JCDS table
    2. then write logic as:
    SORT i_jcds BY objnr stat chgnr DESCENDING.
          LOOP AT i_jcds INTO wa_jcds1.
            CLEAR lv_stat.
            lv_stat = wa_jcds1-stat.
            AT NEW objnr.
              AT NEW stat.
                CLEAR: wa_tab.
                wa_tab-objnr = wa_jcds1-objnr.
                wa_tab-stat = lv_stat.
              ENDAT.
            ENDAT.
            IF wa_jcds1-inact = 'X'.
              CLEAR lv_tabix.
              IF sy-tabix > 1.
                lv_tabix = sy-tabix - 1.
              ELSE.
                lv_tabix = 1.
              ENDIF.
              READ TABLE i_jcds INTO wa_jcds2 INDEX lv_tabix.
              IF sy-subrc = 0.
                wa_tab-chgnr = wa_jcds2-chgnr.
                wa_tab-udate = wa_jcds2-udate.
                wa_tab-utime = wa_jcds2-utime.
                APPEND wa_tab TO i_tab.
              ENDIF.
              CONTINUE.
            ELSE.
              wa_tab-chgnr = wa_jcds1-chgnr.
              wa_tab-udate = wa_jcds1-udate.
              wa_tab-utime = wa_jcds1-utime.
            ENDIF.
            AT END OF objnr .
              AT END OF stat.
                APPEND wa_tab TO i_tab.
              ENDAT.
            ENDAT.
          ENDLOOP.
          DELETE ADJACENT DUPLICATES FROM i_tab COMPARING objnr stat.
          SORT i_tab BY objnr stat udate utime.
          DELETE ADJACENT DUPLICATES FROM i_tab COMPARING objnr.
    3. now in i_tab table u'll get eldest UDATE
    Hope its work for u.
    Thanks & Regards,
    Sumit Joshi

  • View Setup time in the DS planning board

    Hello Everyone. I maintained setup time for a resource but it is not displaying in DS planning board. What could have I missed? Thanks.
    Michelle

    hello,
    first check the operations of the order.
    right click on the produce operation and navigate to Order Processing.
    In the order tree open all nodes for operations.
    Is the set up activity visible there?
    If yes doble click on the activity.
    does the set up activity have a duration?
    If yes check the status of the set up activity.
    go back to the planning board.
    in the menue select extras-> Legend
    a pop-up with the graphical objects is displayed.
    Check the graphic objects for the activity status you read before.
    did you change the customizing settings for the graphic object?
    If yes check them again or reset them to the default SAP settings.
    I had a similar problem with a set up activity when I wanted to change the color of the activity according to the set up group. I  changed the settings in the customizing Maintain Planning Board Profiles.
    It is very difficult to maintain the decision table for graphical objects.
    If you did this recheck the decision table.
    Go back to the SAP default settings and check the planning board again.
    Are the set up acitvities displayed now?
    Then the porblem is with the decision table.
    rethink every step again.

  • REMOVE REASON FOR REJECTION FROM THE SALES ORDER

    Hi,
    When i am trying to change status of items 130+140 from net cancellation to "open"  (remove reason for rejection), saving is not possible because of this error message!
    Item 000130 :Target qty of reference: 1 PC (total referenced: 2 PC).
    Also an information message: Subsequent documents already exist for item 000140.

    Thanks for your help. =)
    I also realized that I forgot to add the SO Item # into the T_ORDER_ITEM_INX-ITM_NUMBER fields.
    But now it works.

  • DEtailed scheduling planning board - scalling of objects in the charts

    Hi,
    I am wandering if there is a possibility of changing the scale in the graphical planning board in APO PPDS, eg. in the resource chart. in the way that I could change the scale just for a certain period of time or one object.
    for example:
    the planning period choosen is 10.09.14 to 01.10.14., scale unit is hour, but the duration of some orders or operations is less than a minute. Woud it be possible to somehow change the scale just for 1 day or 1 hour within the shown period? zooming in does not help as then I cannot see the other lines that I need to look at when scheduling that specific order or operation.
    thank's for any helpful hint!
    br,
    Wojtek

    Hi Mike,
    thank you for responding to my query.
    I know the functionality with the right-click. this unfortunately does not help as the whole time frame is stretched-out => they cannot seen some objects, while the planners would like to strech-out only part of the shown period.
    I also checked the possibility of changing the scale down to seconds cause some operations have a duration of less than a minute (timescale editor = double left-click on the scale). But the production is still unhappy. They have seen in some software such a possibility and wish the same in the graphical planning board. they want to see just part of the time frame in another scale so that the objects outside the scale remain in the same time unit but the objects within the considered time frame would be displayed in another time unit.
    In the resource chart if you right-click an operation you can select the option shrink/stretch operation => I am not sure if there is sth wrong with my connection but most of the time when I click this option nothing happens. Just a couple of times while clicking on the same operation I manged to get a pop up "change operation duration" where you can define in % the new duration. but have to choose a new duration between "min and max duration" that are in this pop up zero => so I cannot change anything and have no clue where this zeros for min and max come from and in the end if that might solve my problem.
    br,
    Wojtek

  • MRS - Resources and demands are not visible in the Planning Board

    Hi Friends - I am working on the the MRSS 610. We have installed it on the our ECC 6.0 as an add-on. We have configured the system as per the configuration guide.
    But when I am accessing Manageru2019s Planning Board -  /MRSS/PLBOMGR , using the Organization unit, I am getting Notification saying that the resources assigned to the Organization unit are not available in the MRS.
    "Resource 00000000010000000000000000000000 not yet created in the WFM Core"
    The details of the Error message
    "Resource 00000000010000000000000000000000 not yet created in the WFM Core
    Message no. /MRSS/SGE034
    Diagnosis
    Resource 00000000010000000000000000000000 has not yet been created in MRS.
    System Response
    No assignments have been created for resource 00000000010000000000000000000000, even though, according to the organizational model, this resource is to be taken into consideration in the planning board.
    Procedure
    Contact technical support.
    Procedure for System Administration
    Create the resource in question in MRS."
    I have run the Report
    /MRSS/HCM_RPTWFMIF : Transfers the HR data (availability times, qualifications and the resources itself) into the MRS Basis
    But even after that I am not getting the resources in the planning board.
    Also I am not able to view the Demands from PM/CS orders.
    I have created PM Orders and
    Assigned Work centres to the operations and
    assigned the Resources to the Operations.
    The HR assignment to the work center is also done.
    I have tried T Code   /MRSS/PLBOSRV - Enter the MRS planning board using a specified order
    to pull the order demand. But it is not working
    Its giving following message
    1004280 is not a valid demand
    Message no. /MRSS/SGU139
    Diagnosis
    The order does not exist in MRS.
    This may be because:
    The order number has an invalid format.
    The order does not exist.
    The order is not relevant for planning and has therefore not been transferred to MRS.
    The order has been deleted from MRS.
    Pls help me on this.
    Thanks in advance and warm regards
    Purnendu

    Hi Anil/Saurabh - Thanks a lot for your replies.
    I have checked the MRS configuration as per your suggestion.
    It looks fine as per the configuration guide. I have done the PM/CS integration for Orders as demand.
    But the Demands are not visible on the Planning Board.
    I have checked in the debugging mode what is causing the problem - It looks like
    "The Database Table: /mrss/d_dem_h  needs entry"
    But there are no entries in this table.
    I could not find any Customizing transactions or Application transactions for maintaining this table. This is an Application Table for Master and Transaction Data and its Display and Maintenance allowed with Restriction.
    I could not also find any transaction for transferring Demand from ECC(R/3) to MRS.
    How do I maintain entries in this table?
    How do I transfer Demand from ECC to MRS?
    Saurabh - I have also been not able to transfer HR Resources from ECC to MRS.
    We don't have WFM Core installed in our instance. But MRS should work fine without WFM. MRS Basis should take care of it.
    To transfer Employee resources i have run the Program " /MRSS/HCM_RPTWFMIF". But when I execute the transaction with the selection parameters system shows that it is processing (Clock at the bottom Status bar) but it does not shows any result or status.
    So I am not sure whether it is executing the program properly.
    Pls help me resolve these issues.
    Thanks and warm regards
    Purnendu

  • I'm no longer eligible to upgrade to the Edge plan now for 6 months???

    I made a partial payment of $200 on a past due account on a Friday night, I have 6 smartphones on 12 GB plan.  Financial Services is closed over weekend, I'm a pro at that by now, and I decided to wait until Monday.  On Monday, my phones were already shut off. I called immediately and paid the remainder of the past due and explained that it was my fault for not contacting them sooner. They pretty much dismissed my reason, charged me the additional $90 reconnection fee, and restored services.  
    Three days later, I'm in Verizon and wanting to upgrade 2 of the lines to the new Edge plan and buy 2 iPhone 5c's.  All's good and then, NO! YOU CAN"T DO THAT!!!??? What? Why?
    Your lines were temporarily interrupted and you are no longer eligible for upgrade to the EDGE plan for 6 months. I asked them to reconsider this as I have no history of service interruptions and good payment history.  They say there's nothing they can do for me, sorry. 
    I talk to AT&T about the new plans they offer and they're more than happy to set me up with 2 lines of service, bill credits, etc. so I call Verizon to see if there is any way to avoid me dropping accounts as they come due. They act surprised that I would consider switching carriers, but I explained I'm paying too much per month and it's not like it's appreciated anyway.  I'm willing to stay with Verizon, but just wanted to switch plans to save a little bit of money. 
    I'm not asking for much, maybe a free pass on failing to set up a payment arrangement, but nothing else.  They're unwilling to work with me and now I'm going to have to keep switching carriers as the contracts expire.  And all because they can't pretend to work with me. 
    Is it just me? Am I being unfair of the situation? 
    Thanks for letting me rant!

    Well, I've resolved the problem, kinda.
    I uninstalled Flash CS5 and AE CS5 last night, then reinstalled them. I then opened one of the AE files with the "junk" SWF in it, and nothing had changed.
    I then tried to import one of the questionalbe SWFs into AE on another machine and the same problem. But I could import a SWF made on that machine into AE (running on that system).
    Then I brought that SWF back to my system, and was able to successfully imported it into AE. I then imported one of the questionable SWFs made before the software reinstall, and got the 72px black square. So I opened the FLA made a new SWF and happened to move it to the desktop. I was able to successfully import that SWF.
    This is where it gets weird. I then made a new SWF and left it in the local folder with the FLA and tried to import it. black box again. I then drag-copied that SWF back to the desktop and I was able to import that.
    So at the moment, it seems to have something to do with the location of the SWF in relation to the AE file? That's the best that I can figure at the moment. Though I'm not sure why this would, or should, be a factor. I wish I had tried this before doing all the software uninstall/reinstalls… but I never would have thought that it could have been an issue.
    Thanks again for your prompt input yesterday.

  • Small Font for Date in Project Planning Board

    Hello Friends?
    Iam Using ECC 6.0 C Version in our Company. iam facing a problem in <b>CJ2B</b> that Date is displaying in very small font. i could n't solve that problem till date. Can any body help me where can we make settings for making fonts size bigger for <b>dates</b> other than zooming in Planning Board.
    Appreciable for ur kind information.
    Thanks.

    Hi Hari,
    Once you are into CJ2B, Please follow the following steps:
    1. Click on the icon " Planning board Assistant"
    2. Select the gantt Chart----Misc. in diagram Area
    3. In the Selection of the "Text" of "Date Descript."--- Select "Dates one-line " ( This is applicable if your date is on the left or right side of the date bar)
    4. Now you can change the Font colour, Font and Font Size, Bold or Italic.....
    5. To Confirm the setting Click on "Update graphics" button on the screen.
    6. Now, If you notice, the dates fonts will be as per your requirement.
    If this does'nt work.. Try to explore in this area only..Probably try selecting other "Text" in the "date Descript."
    Hope this helps.
    Warm regards,
    Srinivas Potluri

  • Tcode to view the list of orders with reason for rejection

    Hi friends,
    Can any one tell the T.code or report to view the  list of sales orders or Scheduling agreements with Reason for Rejection updated.
    Kindly help.
    Regards,
    K.Vivek

    Hi Vivek,
    Use Tcode VA05 i.e. List of Sales Order. In this Tcode you can enter sales document type, sales area and other related data. After execution, from layout you can select Reason for Rejection from the list.
    This way you can filter all the sales documents including Scheduling agreements by using sales document types.
    Hope this will help you.
    regards,
    Sagar Wagh