View Setup time in the DS planning board

Hello Everyone. I maintained setup time for a resource but it is not displaying in DS planning board. What could have I missed? Thanks.
Michelle

hello,
first check the operations of the order.
right click on the produce operation and navigate to Order Processing.
In the order tree open all nodes for operations.
Is the set up activity visible there?
If yes doble click on the activity.
does the set up activity have a duration?
If yes check the status of the set up activity.
go back to the planning board.
in the menue select extras-> Legend
a pop-up with the graphical objects is displayed.
Check the graphic objects for the activity status you read before.
did you change the customizing settings for the graphic object?
If yes check them again or reset them to the default SAP settings.
I had a similar problem with a set up activity when I wanted to change the color of the activity according to the set up group. I  changed the settings in the customizing Maintain Planning Board Profiles.
It is very difficult to maintain the decision table for graphical objects.
If you did this recheck the decision table.
Go back to the SAP default settings and check the planning board again.
Are the set up acitvities displayed now?
Then the porblem is with the decision table.
rethink every step again.

Similar Messages

  • Setup time not seen for Planned Orders/ Man Orders in GPB

    Hi all,
    I'm facing an issue where I'm unable to see the Setup activity(green bar) in the Graphical Planning Board for Planned Orders and Manufacturing Orders.
    At first I thought this was only happening for Planned Orders in Released status. However this behavior seems to be erratic with some orders on the same Product showing Setup whereas others are not.
    Any ideas?
    ~Rishi

    Hi,
    I am assuming you are using setup matrix .
    In case of setup matrix system will take setup time from setup matrix.
    If two planned order are created for the same product, system will consider the setup time for the first. For the second it will not show setup time (becasue most probably you have maintained product x to product x - o times).
    Regards
    Amlan

  • Default print settings in the Project Planning Board CJ02N CJ2C

    Hello
    When you print the Project Planning Board CJ02N/CJ2C - there is an option to change the page setup.
    I would like to change the default settings for left,right, top and bottom margins for all users.
    Can anyone suggest where this would be done ?
    Thankyou
    Ros

    Hi Varun,
    Thanks for the fast repply!
    Please see below the CJ2C and CNE5 screen shots:
    Thanks and Regards
    James

  • Hiding the Optimizer button from the DS planning board

    Hi
    How to hide the optimizer button from the DS planning board ..
    Thanks

    Hi Chak
    I think the problem may be with a livecache inconsistency. The Planning Board should be reading it's information from the livecache, whereby the Product View may be getting it's situation from the database. Try running the livecache consistency checks if it occurs again.
    Regards

  • Reason for delay on the DS planning board grafic

    Dear SAP Fans
    Have you done any development on the DS planning board to show reason of the delay of a planned order?
    We are implementing PP/DS and this is a hard requirement for the acceptance. The users have another schedule system with this functionality, when an order is delayed you can see the reason in the chart by clicking on the delayed order. When they see the reason they can see all the constraints that prevent the optimizer to schedule the planned order in an early date, for example:
    - Order 0001 is delayed to 15.04.2011 because;
             - Reason 1:  Machine A is unavailable up to 30.03.2011
             - Reason 2 : Componente 0001-01 have purchase order scheduled to 15.04.2011
             - Reason 3 : PRT is under maintenance up to 10.04.2011
    With this information on hand the user can take some actions to antecipate the order in case this order is causing delay on a priority A customer order. For example the actions could be:
              - For reason 1, rearrange orders in the machine to schedule the order in an early date.
              - For reason 2, negotiate with supplier an early delivery date.
              - For reason 3, negotiate with plant maintenance to accelerate it.
    Maybe something related to look for the delay log of a specific order.
    Appreciate any insight.
    Thanks and BR

    hello,
    first check the operations of the order.
    right click on the produce operation and navigate to Order Processing.
    In the order tree open all nodes for operations.
    Is the set up activity visible there?
    If yes doble click on the activity.
    does the set up activity have a duration?
    If yes check the status of the set up activity.
    go back to the planning board.
    in the menue select extras-> Legend
    a pop-up with the graphical objects is displayed.
    Check the graphic objects for the activity status you read before.
    did you change the customizing settings for the graphic object?
    If yes check them again or reset them to the default SAP settings.
    I had a similar problem with a set up activity when I wanted to change the color of the activity according to the set up group. I  changed the settings in the customizing Maintain Planning Board Profiles.
    It is very difficult to maintain the decision table for graphical objects.
    If you did this recheck the decision table.
    Go back to the SAP default settings and check the planning board again.
    Are the set up acitvities displayed now?
    Then the porblem is with the decision table.
    rethink every step again.

  • Network Header at  the Project Planning Board gantt chart

    Hi again,
    Does anyone knows a configuration to allow the network header to appear in the project planning board gantt chart?
    Tks
    James

    Try transaction OPT7
    Double click on the appropriate Profile
    On the Table Area Tab, select the flag for the field "Display Network"
    Hope this helps
    Regards
    Steve

  • Time Specification Button in Planning board for MRS

    Is it possible to remove the time specification in the planning board for MRS?  I have disabled all the time type but we want to remove the time specification button?

    The clients wanted to remove it but if it not possible then there is nothing I can do ..
    Since we are the top of MRS, Do you know what the "Time Allocation from HR cannot be changed" mean and how do I get rid of it?

  • First Time To the Windows Developers Board? Start Here

    Welcome to the (Windows, Android, Innovation) Forum for Lenovo Developers
    First, let’s make sure you’re in the right place.
    Want to create or modify an app for Lenovo devices and innovation technologies, and work through any challenges which may arise?
    You’re in the right place. Post your discussion topic or question here.
    Need help getting something to work as shipped, or reporting bugs with configs as shipped?
    That’s a support discussion that belongs on the main hardware boards. We’ll be super-happy to help you, so please post those there. 
    You good?
    Okay let’s continue:
    What the Developer Boards are For:
    We’re striving to build a global community of developers who are stoked about creating apps for Lenovo PC+ devices and Lenovo Innovation Technologies.
    Peer to peer support is king. As with the main hardware boards, support, info, and moderation comes from the community, not Lenovo staff.
    Sharing  any "knowledge base" types of content you have created that would help the community.  
    What the Windows Developers Board Is For. We are obviously looking for Windows desktop and Win8 metro development conversations(duh! I know) , but here are some specific items we'd love to hear about from you:
    Transition from developing Windows desktop apps to Windows 8 "metro style" apps. What has that been like, how have your workflows changed, etc.
    Okay, so game developers, we love love love you! Fist bump, you rock,keep it coming... That said  Win 8 videa, music, business, productivity, social media, developers, STAND UP!  Lenovo wants YOU participating in this community!  Post here and let us know what you are working on, how we can help, etc.
    What it is not for: 
    Transacting business of any kind. We have several channels available to help sell and promote your app, but this forum isn't’t the right place. Mods get an 80% cut off the top of any business transactions posted here. 
    Hate speech, personal agendas, personal attacks, threats, antagonizing members, inappropriate content, and any generally knucklehead behavior will get you banned. (you'll also be subject to being forced to write code for an IBM PC Jr. until you’re rocking back and forth in a corner. ) In other words, the same rules that apply to Lenovo Forums apply to these boards. If you aren’t already familiar with the Lenovo Forums rules, get familiar here
     How We Roll Here…
    In general ,the vibe on these boards will be transparent, useful, challenging, and non-marketing-speak-ish.  We try to save the “unique selling propositions” and “corporate-speak” to the marketing crowd.  We try not to take ourselves too-too seriously as well. 
    LenovoDev.com Manager

    Krista,
    Great - this sounds really exciting!
    Here are a few links to Lenovo developer resources related to Windows ecosystem...
    Lenovo Developer main site - www.lenovodev.com
    Win8 App Store Overview lenovodev.com/deploy/lenovo-windows-8-store
    Lenovo Picks App Marketing Page www.lenovopicks.com
    ThinkPads: S30, T43, X60t, X1, W700ds, IdeaPad Y710, IdeaCentre: A300, IdeaPad K1
    Mark Hopkins
    Program Manager, Lenovo Social Media (Services)
    twitter @lenovoforums
    English Community   Deutsche Community   Comunidad en Español   Русскоязычное Сообщество

  • MRS - Resources and demands are not visible in the Planning Board

    Hi Friends - I am working on the the MRSS 610. We have installed it on the our ECC 6.0 as an add-on. We have configured the system as per the configuration guide.
    But when I am accessing Manageru2019s Planning Board -  /MRSS/PLBOMGR , using the Organization unit, I am getting Notification saying that the resources assigned to the Organization unit are not available in the MRS.
    "Resource 00000000010000000000000000000000 not yet created in the WFM Core"
    The details of the Error message
    "Resource 00000000010000000000000000000000 not yet created in the WFM Core
    Message no. /MRSS/SGE034
    Diagnosis
    Resource 00000000010000000000000000000000 has not yet been created in MRS.
    System Response
    No assignments have been created for resource 00000000010000000000000000000000, even though, according to the organizational model, this resource is to be taken into consideration in the planning board.
    Procedure
    Contact technical support.
    Procedure for System Administration
    Create the resource in question in MRS."
    I have run the Report
    /MRSS/HCM_RPTWFMIF : Transfers the HR data (availability times, qualifications and the resources itself) into the MRS Basis
    But even after that I am not getting the resources in the planning board.
    Also I am not able to view the Demands from PM/CS orders.
    I have created PM Orders and
    Assigned Work centres to the operations and
    assigned the Resources to the Operations.
    The HR assignment to the work center is also done.
    I have tried T Code   /MRSS/PLBOSRV - Enter the MRS planning board using a specified order
    to pull the order demand. But it is not working
    Its giving following message
    1004280 is not a valid demand
    Message no. /MRSS/SGU139
    Diagnosis
    The order does not exist in MRS.
    This may be because:
    The order number has an invalid format.
    The order does not exist.
    The order is not relevant for planning and has therefore not been transferred to MRS.
    The order has been deleted from MRS.
    Pls help me on this.
    Thanks in advance and warm regards
    Purnendu

    Hi Anil/Saurabh - Thanks a lot for your replies.
    I have checked the MRS configuration as per your suggestion.
    It looks fine as per the configuration guide. I have done the PM/CS integration for Orders as demand.
    But the Demands are not visible on the Planning Board.
    I have checked in the debugging mode what is causing the problem - It looks like
    "The Database Table: /mrss/d_dem_h  needs entry"
    But there are no entries in this table.
    I could not find any Customizing transactions or Application transactions for maintaining this table. This is an Application Table for Master and Transaction Data and its Display and Maintenance allowed with Restriction.
    I could not also find any transaction for transferring Demand from ECC(R/3) to MRS.
    How do I maintain entries in this table?
    How do I transfer Demand from ECC to MRS?
    Saurabh - I have also been not able to transfer HR Resources from ECC to MRS.
    We don't have WFM Core installed in our instance. But MRS should work fine without WFM. MRS Basis should take care of it.
    To transfer Employee resources i have run the Program " /MRSS/HCM_RPTWFMIF". But when I execute the transaction with the selection parameters system shows that it is processing (Clock at the bottom Status bar) but it does not shows any result or status.
    So I am not sure whether it is executing the program properly.
    Pls help me resolve these issues.
    Thanks and warm regards
    Purnendu

  • DEtailed scheduling planning board - scalling of objects in the charts

    Hi,
    I am wandering if there is a possibility of changing the scale in the graphical planning board in APO PPDS, eg. in the resource chart. in the way that I could change the scale just for a certain period of time or one object.
    for example:
    the planning period choosen is 10.09.14 to 01.10.14., scale unit is hour, but the duration of some orders or operations is less than a minute. Woud it be possible to somehow change the scale just for 1 day or 1 hour within the shown period? zooming in does not help as then I cannot see the other lines that I need to look at when scheduling that specific order or operation.
    thank's for any helpful hint!
    br,
    Wojtek

    Hi Mike,
    thank you for responding to my query.
    I know the functionality with the right-click. this unfortunately does not help as the whole time frame is stretched-out => they cannot seen some objects, while the planners would like to strech-out only part of the shown period.
    I also checked the possibility of changing the scale down to seconds cause some operations have a duration of less than a minute (timescale editor = double left-click on the scale). But the production is still unhappy. They have seen in some software such a possibility and wish the same in the graphical planning board. they want to see just part of the time frame in another scale so that the objects outside the scale remain in the same time unit but the objects within the considered time frame would be displayed in another time unit.
    In the resource chart if you right-click an operation you can select the option shrink/stretch operation => I am not sure if there is sth wrong with my connection but most of the time when I click this option nothing happens. Just a couple of times while clicking on the same operation I manged to get a pop up "change operation duration" where you can define in % the new duration. but have to choose a new duration between "min and max duration" that are in this pop up zero => so I cannot change anything and have no clue where this zeros for min and max come from and in the end if that might solve my problem.
    br,
    Wojtek

  • Viewing CO versions in project planning board

    Hello,
    I have saved two CO versions of my project. When i go to the project planning board the approved plan column is full of data and looks great but the other version as no information. I have SAPALL so this isn't an authorization issue. Can someone please help me work out was is wrong?
    Thanks a lot
    Jason

    Hi,
       Basically there are possibilities of creating Plan version.
    1) one you can create in CJ40 by manually feeding the Version ex:0,1,2 etc....
    2) create one version in CJ40 and copy the same to another version in CJ9BS.
    once the versions are created make the changes of values in the respective versionand save the changes.
    Please check the version comparission in S_ALR_87013539 - Project Version Comparison: Plan.
    Comming to plan board which fields did you picked up for comparission?
    Rgds
    Sudhir Reddy

  • Activity Confirmation  -  Gantt Chart  -  Planning board

    Hi
    suppose i have a activity duration from 1st february 2009 to 28th february 2009
    on 15th february i confirm 0nly 10% of the work as completed in the activity confirmation screen in the degree of processing field and also enter the start date as 1st february 2009 and the finish date as 15th february 2009.
    when we look at the planning board in CJ20n transaction subsequently (gantt chart) the activity bar shows a colouring from 1st february to 15th february instead of showing only 10% of the activity bar coloured for completion of the work
    where is it possible to see the percentage completion of an activity graphically as 10% this data is available in table format in CN48N transactio

    Hi,
    we can view in table format by selecting the fileds related to percentage of completion in the project planning board (gantt chart).
    The requirement you had explore is possible in MS projects, but in standard SAP we can't view in the graphically mode.
    Regards,

  • CM25 : remaining time at the finish of the bar

    Dear guru ,
    I execute a partial confirmation of a production order.
    After i see this production order in transaction CM25
    In the graphical planning board the capacity remaining time is displayed at the start of the bar with color red (the time already confirmed is grey).
    Can i change the graphic profile in order to display the remaining time of the operation at the finish of the bar ?
    Thanks in advance

    Hi,
       Did you check up the planned dates of that production order?
       I hope the planned date start may be in the past and hence after confirmation, as the dates are near the finish date, you get the remaining period before the start of the bar and the completed confirmation in grey at the end of the finish of the bar. Can you check if this is your case?
    -Thaila Shree

  • Project Planning Board - Customising

    Hello All,
    Do we have an option to customize project planning board.
    If yes where exactly in SPRO can we do this, and does anyone have any documentation on what all can be configured in project planning board.
    Points assured.
    Thanks in advance.
    Warm Regards,
    Jatinder Bansal

    Project planning board customization is available at IMG. path IMG>PS>Structures>Project Planning Board.
    Planning Board is based on Gannt chart. the customization includes, Define Time Profiles, Define profiles for time scales ,  Define scale for the time axis, Define Profiles for the Project Planning Board, Maintain Report Assignment from the Planning Board & Capacity Leveling/Capacity Evaluations.
    Regards
    Murali

  • DS Planning Board loads VERY SLOW; hoping a User Profile Parameter will fix

    (*Large, global company - thousands of users, hundreds of APO users).
    I've had my system working fine for a couple of years;   the DS Planning Board used to take about 10 seconds to load.
    Since a couple of months ago, it takes 10 MINUTES to load.
    Nothing was changed or updated, and the APO/SAP experts in my company have no idea what's wrong.
    Nobody else is affected.
    Other boards work as normal.  Just the Planning Board comes up slow.
    Saving data, also takes 10 minutes, regardless of 1 item or 100 to be updated - same length of time.
    It's a very stable duration, at just over 10 minutes.  It's consistent, whether early-morning, late-afternoon, weekend, etc...
    (It's ALMOST as if there's a parameter that says 'wait 10:00, and then proceed with the normal 10-second job of loading or saving the board.')
    Early-November, I switched from a desktop to a laptop - no problems for a week...
    I used the laptop from home OK for a half-day, then it just 'changed' to a 10-minute wait.
    I thought it was laptop-relevant, but it continued when I docked at work.  Now it's constant.
    I've uninstalled/reinstalled the SAP GUI completely.  No change.
    These are my settings relevant to performance (excluding custom download path, default unit of measure, etc...)
    /SAPAPO/ATP_PRREG         X
    /SAPAPO/PRR                      A
    /SAPAPO/SDP94_D_MODE  L
    /SAPAPO/SDP_GRAPH_TB  X
    /SAPAPO/SDP_XLS_FS       1
    /SAPAPO/TS_QUEUE_UPD   3
    /SAPAPO/VRSIOID               000
    Z_CDPS_PERFORMANCE    XXX
    Any suggestions?
    Edited by: DavidRTurner on Feb 28, 2011 4:28 PM for clarity

    Hi David,
    With your concerns, you can request assistance from your BASIS team for you to trace the abnormalities happening on your system. Best practice also is to clean up/frequent reprocess the blocked data (if any) into the inbound/outbound queues. Good luck man!
    Cheers