Split operation in two work centers?

Hello SAP gurus,
I have a scenario where I need to split one operation in two work centers, by doing this I can reduce the operation time by half.
Here is an example:
WC A
WC B
Operation 0010 - 10 UN - 1 H Machine Time
Currently I have:
   WC A - 10 UN - 1 H
I want to split the operation by the work center A and B:
   WC A - 5 UN - 30 MIN
   WC B - 5 UN - 30 MIN
I have tried to use sequences but, the system puts the total tima (1 H) in the two operations, wich is wrong!!!
Can someone help me with this?
Thanks in advance,
Adelmo

Dear,
You need to create this as a single work center with 2 Individual Capacities, and you can use the capacity leveling/dispatching option to allocate the right workcenter to the individual machine. Or also note in routing select the opn & double click. enter no. capacity splitting is 2 Make tick mark in required splitting.
If you want to do in order then go to an operation screen double click on operation no go to Splitting tap enter here the splitting is 2 Make tick mark in required splitting then click on scheduling icon and check the timing
Please refer this thread,
Re: Parallel sequence with % split quantity
Hope it will solve your issue.
Regards,
R.Brahmankar

Similar Messages

  • COOIS report: not able to select operations based on work centers

    Hi All,
    When accessing the COOIS report using operation listv& selecting the std profile.I need to get the operation perfomred on specific work center.
    I enter the work center & plant code in the selection fields available in the "select at operarion level" & i get the all the work center.
    Need to get list of operation performed at the entered work center.
    The requirement is due to the reason that a order is performed in two or three production facilities & production guys needs to look at operation list for given work centers.
    Regards
    Vineet

    Hi,
    This one of the options we had explored, but it would be better if we can get  the report by work center. The focus is to reduce the effort to get the report as there is need to get the same report for atleasr 8to 10 different group of work centers ( which are not in serial nos).
    We would then need to put the work centers in the filters & save the layout.
    Regards
    Vineet

  • Split Individual Capacity for Work Centers

    In Capacity Leveling for Individual Capacity (CM27 & CM28), what is the process in setting up individual "persons"?
    What I would like to do is take an individual work center and divide it up into several different areas.  I would like to treat the individual 'persons' as listed in Individual Capacity as those different areas I would divide my work center up into.
    However, I have no current setup for personel available and when I go to assign a 'Person' to a specific quantity for my work center, there is "no persons found for the work center".
    Where do I go to setup individual "persons" for my work center, and is this a realistic way to divide my work center up?
    If not realistic, what method would you recommend to split up the work centers?
    Edited by: Cameron on Sep 21, 2009 3:06 PM

    Hi,
    The best way to learn all these settings is studying the documentation in the IMG itself.
    Still id you need the link or documents to read
    "http://help.sap.com/saphelp_47x200/helpdata/en/b1/c03e4a439a11d189410000e829fbbd/frameset.htm"
    Read the documentation step by step....
    I hope this will help you.
    Thanks
    Raja

  • To split an operation quantity in a single production order into different work centers.

    Detailed Process:
       Our client have 17 factories. Inside each factory there are 15-20 Sewing lines (Work Centers). In each line 15-20 machines (individual capacities) are there. The standard manufacturing scenario practiced here is MTO. Merchandisers create sales order and allot it to a particular plant. Now line level planning happens inside the factory. Based on the order delivery date to meet the requirements they split the production order and allot it to several sewing lines (work centers).  In SAP we can have work around solution to partially convert planned order to production order and allot it to particular line. The challenge here is to have same production order number which can be allotted to several sewing lines with a mandatory option to enter the quantity for each sewing line
    We have proposed alternative and multiple routing for converting planned order into number of production orders but the solution was not meeting their requirements.
    Please provide your valuable opinions on this issue.

    Hi,
    Please explore the option of using the concept called Parallel sequence in routing...
    Check the below thread...
    parallel sequence in Routing
    Routing - Parallel Sequence
    Hope this helps
    Thanks
    Kumar

  • I want to have two different operations on two analog output terminals of DAQ. When I work

    with AO0, it works. But after I add in another channel, AO1, there is an error saying that 'specified group is in use'. Actually, I assigned different group number for AO0 and AO1 when configuing the device using AO Config.vi. How to deal with this error?I want to have two different operations on two analog output terminals of DAQ. When I work with AO0, it works. But after I add in another channel, AO1, there is an error saying that 'specified group is in use'. Actually, I assigned different group number for AO0 and AO1 when configuing the device using AO Config.vi. How to deal with this error?

    with AO0, it works. But after I add in another channel, AO1, there is an error saying that 'specified group is in use'. Actually, I assigned different group number for AO0 and AO1 when configuing the device using AO Config.vi. How to deal with this error?Hey Steve,
    Doug is correct. Both analog outputs have a shared clock. If you want to write to both outputs simultaneously, you will need to include both of them in the same operation (group).
    You can write a 2-D array to the AO Write VI in which you can include data for both channels. In the 2-D array, column 1 will be for the first channel in the channel list and column 2 will be for the second channel.
    I hope this helps.
    Regards,
    Todd D.
    NI Applications Engineer

  • How can I use capacity splits in Machines "001" using PS work centers ?

    Hello Experts
    I want to manage capacity splits for machines in PS using work centers.
    I create work center CNR1 "Capacity Category 001 <Machine>", maintain the capacity header and maintain the rest of the work center as usual.
    If I create a pooled capacity CR11, I can only assign one pooled capacity for a work center. however I added 3 individual capacities in the capacity header.
    when I create an internal activity and assign the work center, work, activity type and number of individual capacities, I go to "Personnel Assignment" tab. I find the capacity category "001" Machine, and the fields down there are capacities not persons.
    I try to open the possible values for the field "Capacity" and no values found.
    Even the pooled capacity I assigned does not appear in F4.
    How can I assign multiple capacities to a work center so that I can choose between them in the capacity split tab "Person assignment" in an internal activity in PS???
    FYI: everything else in the internal activity is working perfectly fine, even personnel assignment. But we haven't activated personnel availability management in HR module.
    Please help
    Regards
    A.Kholy

    Hi Ahmed,
    You can achieve this by using creating individual capacity for category type.
    Steps:-
    1.Go to Cr02 define capacity category 001 .
    2.Now double click on capacity category it will open its header details.
    3.Now assign individual capacity this will appear in project. as shown
    5.In project u can assign same in capacity.
    Reward if helpfull.
    Thanks
    Suraj Prakash

  • I have a split screen with two site. All the suggestions are not working.

    Everytime I load Firefox, I get a split screen with two sites on it.
    I have tried the resetting of home page and clicking off the icon to not show the site selection page.
    I have facebook on the left and it cannot be expanded bigger than a panel. I have a 3/4 screen of what ever web site I wanted to load.
    How do I turn this off?
    Nothing is working and I cannot imagine how it happened.

    Can you attach a screenshot?
    *http://en.wikipedia.org/wiki/Screenshot
    *https://support.mozilla.org/kb/how-do-i-create-screenshot-my-problem
    Use a compressed image type like PNG or JPG to save the screenshot.
    Opening in the sidebar is the default for bookmarks that are created via a link or button on a website.<br />
    You can check the Properties of a bookmark via the right-click context menu in the sidebar (Ctrl+B; Cmd+B on Mac).<br />
    In the Bookmarks Manager (Bookmarks > Show All Bookmarks) you can click the More button in the Details pane at the bottom right.<br />
    Make sure that "Load this bookmark in the sidebar" is not selected.<br />

  • Scheduling issue for splitted operations in process order

    Hello All,
    I am facing problem after scheduling splitted operation in process order. The scenario is as follows.
    In process order there are 5 operations. 10, 20, 30, 40 and 50. Out of the above operations 30 is splitted and two different resources are assigned to it. Control key assigned to splitted operation (30) is also scheduling relevant. Now the flow of operations will be as below.
    1. Operation 10
    2. Operation 20
    3. Operation 30 - Operations is splitted (Resource used is A), qty to be produced - 10 kg.
    a. Operation 32 - Quantity of operation 32 is changed to 5 kg. Resource used is B.
    b. Operation 34 - Quantity of operation 34 is changed to 5 kg. Resource used is C.
    4. Operation 40
    5. Operation 50
    Relationship exists between opearion 10-20, 20-30, 40-50 and between 30,32, 34 with 40. But there is no relationship exists between splitted operations 32 and 34 with any of the previous operations for eg. 10 & 20.
    Issue is after scheduling all operations relationship remains maintained between operations 32, 34, 40 & 50. As operation 30 is splitted to two different operations equally total time for scheduling gets reduced but after scheduling of all operations all previous operations before operations 30 does not get resceduled? Scheduling type maintained for order is Backward Scheduling.
    Please check this and guide me how all operations before operation 30 can be rescheduled as per changed timing of operations 32 and 34.
    Best Regards.
    Edited by: Avinash Mohite on Mar 19, 2010 12:43 PM
    Edited by: Avinash Mohite on Mar 19, 2010 3:14 PM

    Hi,
    I hope u r doing in this way:
    In the capacity header screen enter individual capacity as 2. then click on Got( on top of same screen) and go to individual capacites. Enter the names of two individual capacities, for example 1 and 2. These are the names of two work centres where u r splitting ur operation.
    Double Click on operation 0030 and go to tab 'splitting' . Tick on ' required splitting' and enter maximum no. of splits as 2.Then go to capacity requirements assignment tab. enter the individual capacity as 1 and 2 and enter the splitted quanitites.Save and reschedule .
    Check and revert.
    Regards.

  • Work centers

    Sir,
    In equipment
    Location Tab  work center is there
    and also in organisation tab main work center is there
    what is the difference between there 2 work centers.
    and which work center we need to assign cost center.
    in order
    Main work center
    work center/ plant
    what is the difference between these two
    and which work center we need to assign cost center.
    Sai Meghana

    Hi,
    Work center in location tab is for integration with PP.
    In PP module equipment is an work center for them and to have integration the same work center has to be included there.
    Work center in organization tab is responsible for maintenance activities for that equipment.
    The same work would be copied to order to take up maintenance activities mentioned in the operation tab in order.
    What ever the cost center maintained in organization tab is cost receiver of the order by default.
    Regards,
    Sudhakar

  • Confirmation for Split operation in Production order

    Hi Experts,
    I have one production order say order no. is "100000000000" and its order qty is 100pcs and in operation no. "20", i have splitted the operation into two individual capacities and allocated 50pcs to each individual capacity. Now can any one explain me or tell me the steps required for confirming the operation quantity by individual capcity.
    Regards,
    Satya.

    Hi,
    Thanks for your response on my post.
    As you mentioned I am using T-code CO11N for Production confirmation, but in this screen if I select operation no. 20, by default, system is read work center from production order "operation overview" screen. Now I want to capture the confirmation quantity against "induvidual capacity" and want to see some reports based on "induvidual capacity" level of the same work center.
    Could you pl. advise on this.
    Regards,
    Satya.

  • RE : Drag and Drop operations between two outlinefields

    Hi,
    Has any one tried the drag and drop operations between two Outline widgets ina
    window.Any help appreciated.
    Thanks
    balsubHi Balsub,
    Here are some lines which can help you :
    First of all, your 2 OutLineFields must be in a draggable state.
    In the event loop of your window, you have to listen to the event
    ObjectDrop
    on the 2 OutLineFields :
    When Self.<MyOutLine1>.ObjectDrop(SourceX = SourceX,
    SourceY = SourceY,
    SourceField = SourceField,
    TargetX = TargetX,
    TargetY = TargetY,
    TargetField = TargetField) do
    When Self.<MyOutLine2>.ObjectDrop(SourceX = SourceX,
    SourceY = SourceY,
    SourceField = SourceField,
    TargetX = TargetX,
    TargetY = TargetY,
    TargetField = TargetField) do
    Then, when you receive this event, the LocateNode() method will give you
    the DisplayNode which is beeing dragged :
    (assume that your OutLineFields are mapped to the class named :
    ClassOutLine,
    and Col is an Integer which is not important here)
    TheSourceLine : ClassOutLine;
    Col : Integer;
    TheSourceLine = (ClassOutLine)((OutLineField)(SourceField).LocateNode(X
    = SourceX,
    Y = SourceY,
    Column = Col));
    If you want to remove this line from the Source OutLineField :
    TheSourceLine.Parent = Nil;
    TheSourceLine.UpdateFieldFromData();
    If you want to insert this line at the end of the Target OutLineField :
    TheSourceLine.Parent = (OutLineField)(TargetField);
    TheSourceLine.UpdateFieldFromData();
    And if you want to insert this line before or after the Target line of
    the Target OutLineField :
    TheTargetLine : ClassOutLine;
    TheTargetLine = (ClassOutLine)((OutLineField)(TargetField).LocateNode(X
    = TargetX,
    Y = TargetY,
    Column = Col));
    TheTargetLine.PrevSibling = TheSourceLine; // Insert the source line
    before the target line
    or
    TheTargetLine.NextSibling = TheSourceLine; // Insert the source line
    after the target line
    TheTargetLine.UpdateFieldFromData();
    I hope this help you !
    - Manuel -
    Manuel Deveaux
    Forte Developer
    Mutuelle Pr&eacute;viade
    FRANCE
    E-Mail : [email protected]
    -----------------------------------------

    There is no configuration for it. It should work.
    Can you try it in a different user account. If it works in a different account, then it is likely something in your current user account that is messed up. If it doesn't work in another user account, then it is likely something with Mail, itself. 
    You could try downloading and installing the 10.6.7 combo update. That may repair what is wrong.

  • Split records into two files based on lookup table

    Hi,
    I'm new to ODI and want to know on how I could split records into two files based on a value in one of the columns in the table.
    Example:
    Table:
    my columns are
    account name country
    100 USA
    200 USA
    300 UK
    200 AUS
    So from the 4 records I maintain list of countries in a lookup file and split the records into 2 different files based on values in the file...
    Say I have records AUS and UK in my lookup file...
    So my ODI routine should send all records with country into file1 and rest to file2.
    So from above records
    File1:
    300 UK
    200 AUS
    File2:
    100 USA
    200 USA
    Can you help me how to achieve this?
    Thanks,
    Sam

    1. where and how do i create filter to restrict countries? In source or target? Should I include some kind of filter operator in interface.
    You need to have the Filter on the Source side so that we can filter records accordingly the capture the same in the File. To have a Filter . In the source data store click and drag the column outside the data store and you will have Cone shaped icon and now you can click and type the Filter.
    Please look into this link for ODI Documentation -http://www.oracle.com/technetwork/middleware/data-integrator/documentation/index.html
    Also look into this Getting started guide - http://download.oracle.com/docs/cd/E15985_01/doc.10136/getstart/GSETL.pdf . You can find information as how to create Filter in this guide.
    2. If I have include multipe countries like (USA,CANADA,UK) to go to one file and rest to another file; Can I use some kind of lookup file...? Instead of modifying filter inside interface...Can i Update entries in the file?
    there are two ways of handling your situation.
    Solution 1.
    1. Create Variable Country_Variable
    2. Create a Filter in the Source datastore in the First Interface ( SOURCE.COLUMN = #Country_Variable)
    3. Create a new Package Country File Unload
    4. Call the Variable in Country_Variable in Set Mode and provide the Country (USA )
    5. Next call the First Interface
    6. Next call the Second Interface where the Filter condition will be ( SOURCE.COLUMN ! = #Country_Variable )
    7. Now run the package .
    Solution 2.
    If you need a solution to handle through Filer.
    1. Use this Method (http://odiexperts.com/how-to-refresh-odi-variables-from-file-%E2%80%93-part-1-%E2%80%93-just-one-value ) to call the File where you wish to create store the country name into the variable Country_Variable
    2. Pretty much the same Create a Filter in the Source datastore in the First Interface ( SOURCE.COLUMN = #Country_Variable)
    3.Create a new Package Country File Unload
    4.Next call the Second Interface where the Filter condition will be ( SOURCE.COLUMN ! = #Country_Variable )
    5. Now run the package .
    Now through this way using File you can control the File.
    Please try and let us know , if you need any other help.

  • Operation number and work center

    I'm looking for the link between inspection plan/recipe header and operation at table lavel.
    Reason: I have two inspection plan number with same group number but both has different counter and each has 4 operation and each operation has different work center.
    Now I can get header info in PLKO and operation level info in PLPO table. From PLKO I can pass PLNTY and PLNNR in PLPO table but this gives me 8 entry in PLPO table (4 for 1st group counter and 4 for 2nd counter).
    So my question is how to differentiate 4 operation of each inspection plan header. Even same issue facing at recipe level.
    I can't find any table. Do we have any BAPI?

    Detailing the above reply through SQVI.
    The Join.
    Selection Screen
    The output
    If you need you may have Header table (PLKO) also in the join to have more details.
    Jogeswara Rao K

  • Regarding - Drag and Drop operations between two outlinefields

    Hi,
    Has any one tried the drag and drop operations between two Outline widgets in a window.Any help appreciated.
    Thanks
    balsub

    There is no configuration for it. It should work.
    Can you try it in a different user account. If it works in a different account, then it is likely something in your current user account that is messed up. If it doesn't work in another user account, then it is likely something with Mail, itself. 
    You could try downloading and installing the 10.6.7 combo update. That may repair what is wrong.

  • Internal Profit (Between Two Profit Centers)

    Dear friends,
    My client has nearly 30 profit Centers (Each product/line) and final product of one profit center sya X is an in put of production process of another profit center say Y.
    Here problem is that Profit Center X wanted to claim some internal profit margine on Profit Center Y because it supplying materials and Profit Center X want to treat Y as an External customer.
    Friends, this profit is only shown in internal reports only (Profit center wise P & L Account) and it cannot appeared in Financial Statement. How this can be configured in the system? Please help me
    Thank you

    Hello Dasu,
    This situation is not unique to your client, but universal to enterprise operating with two or more company codes / business lines / products. 
    Recording inter-profit centre transactions at sales price is not that easy; however with the standard functionalities this can be achieved. SAP system has provided various functionalities with the combination of currency and valuation which is more commonly known as u201CTransfer Pricing or Multiple Valuation Approachesu201D.
    You define your currency and valuation profiles in Customizing under Controlling  Controlling General  Multiple Valuation Methods/Transfer Prices  Basic Settings  Maintain currency and valuation profile.
    You assign the currency and valuation profile in Customizing under Controlling  Controlling General  Multiple Valuation Methods/Transfer Prices  Basic Settings  Assign profile to controlling area.
    You activate the profile under Controlling  Controlling General  Multiple Valuation Methods/Transfer Prices  Activation  Activate multiple valuation approaches
    For more information, you may refer to
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/eb/13811243c411d1896f0000e8322d00/frameset.htm