Hi Team,
We posted time sheet for the june month but posting date has been selected july 1  insted of june 30th 2011
useing trnasaction code :CATT JOB
can some body give me suggestion how to come up with problem like
is there any possiblity to reverese the time sheet or cancel that posting..?
if we cancel there any impact which already posted time sheets entries ?
thanks
Ranamka

Hi Ajay and Bernhard,
In Asset Master the depreciation is settle to start in 01.10.2010, I already run depreciations for all assets in period 10 but not for period 11.
I only acquired the asset after running depreciation for period 10, so in AFAB I have to run depreciation again for period 10 in "repeat" mode right?
Problem is...when I do that, the outcome is zero as if I didn´t make a new acquisition for that period, after that I went to asset explorer (AW01N) and in tab "Posted values" depreciations only starts in period 11.
Example (of what is shown in asset in AW01N):
Acquisition value: 1000 $
Acquisition date: 15.10.2010
Dep. start date: 01.10.2010 (period 10 already been run)
Posted values:
- period 11: 50 $
- period 12: 25 $
Why depreciation doesn´t starts in period 10? Instead period 11 "eats" values from period 10. I want to run again period 10 but it doesn´t have values. Can you tell me why this happens?
Thanks in advance,
MG.

Similar Messages

  • Declining balance depr.key - phase 2 posting in wrong period

    Hi,
    I have problems with the posting of depreciation. The posting of depreciation calculated in phase 2 in the depreciation key is not posted in the period that I want.
    The requirement is that during the planned useful life declining balance depreciation should be posted. In the period following directly after the end of the useful life the remaining net book value should be depreciated and posted.
    An example:
    Asset acquistion in october 2009: 100000
    Useful life 5 years
    Declining balance depreciation 25% (based on net book value)
    I would like the following depreciation to be posted:
    Year     APC     Depr     Net Book Value at year end     
    2009     100000     6250     93750      3 months (october- december)
    2010          23438     70313     
    2011          17578     52734     
    2012          13184     39551     
    2013          9888     29663     
    2014          5562          9 months depreciation (january - september)
    2014          24101            0     Remaining net book value depreciated in october
    I have tried to achieve this by creating a depreciation key with 2 phases:
    1. The first phase is the settings for the declining balance depreciation that should be posted during the useful life of the asset.
    2. The second phase is the total depreciation of the remaining net book value.
    I have tested and both phases individually - and they work perfectly correct.
    When combining the 2 phases the depreciation of phase 2 is posted in january 2015 (not in october 2014 as expected /wanted).
    The settings of the depreciation key is:
         Base     Decl. Bal     Period     Multi     Change
    Phase 1     0012     001     006     005     5
    Phase 2     0017     001     006     017     
    A copy of the standard depreciation key DE25 (for Finland) is used as a template and the phase 2 added.
    All the methods allocated to the depreciation key are standard delivered SAP- except for the period control 006 which is changed to 01/01/01/01 ("01 - Pro rata at period start date").
    A copy of the country template chart of depreciation for Finland (0FI) is used. I have checked the settings of the chart of depreciation and they seems to be correct.
    When reading the SAP documentation I cannot find out what I am doing wrong.
    In the documentation for the change over method used it is pointed out that with this change over method the switch should take place in the exact period - which is exactly what I want.
    Is there anyone who have an idea I woulb be most grateful!
    Regards,
    Åsa

    Thanks for your answer - but unfortunately it didn´t solve my problem.
    We already use the settings that you suggested.
    //Åsa

  • CProject No items found in worklist of time sheet, what's wrong?

    Hi,
    We have a standalone cProjects 4.5 system which we would like to link to our ECC 6.0 system.
    The accounting integration is in place and is working. Now we also like to fill the Cats worklist in the ECC 6.0 system.
    We have set up the ALE transfer and fulfilled these requirements:
    1.The customizing of the CATS Data Entry Profiles must be set correctly.
    2.The Link between the personal numer (Cat2) and Business Partner (cProject) must be maintained correctly. (note 954860)
    3.The business partner must be assigned to a role or task within the used time period
    4.The  involved cProject objects (role or task) must have a accounting assignment
    I have found this article:
    https://www.sdn.sap.com/irj/scn/wiki?path=/pages/viewpage.action&pageid=61926
    But that is of no help. In our systems, in the cProjects system, no iDoc is created.....
    Which other actions should we do before we can see the project in the worklist of Cats?
    Thanks!
    M.

    `Hi Zhenbo,
    The report says nothing. We would like to send the worklist info from cProjects to Cats, and afterwards get the information back.
    So no records in cat2 exist yet.
    But there should be an iDoc for the worklist......
    Yours,
    Miel

  • Depreciation posted in wrong period

    Hi All,
    I ran depreciation in period 10 for all assets, after that, I acquired a fixed asset  in period 10. After that I want to run depreciation again in period 10 in repeat mode, but modified depreciation values DON´T appear in period 10 in AW01N, the asset only stars its depreciation in period 11, why is that?
    If the modifications of asset values were done in period 10, shouldn´t depreciation values also start in period 10 and shouldn´t I be able to run depreciation in repeat mode for period 10?
    Thanks in advance,
    MG.

    Hi Ajay and Bernhard,
    In Asset Master the depreciation is settle to start in 01.10.2010, I already run depreciations for all assets in period 10 but not for period 11.
    I only acquired the asset after running depreciation for period 10, so in AFAB I have to run depreciation again for period 10 in "repeat" mode right?
    Problem is...when I do that, the outcome is zero as if I didn´t make a new acquisition for that period, after that I went to asset explorer (AW01N) and in tab "Posted values" depreciations only starts in period 11.
    Example (of what is shown in asset in AW01N):
    Acquisition value: 1000 $
    Acquisition date: 15.10.2010
    Dep. start date: 01.10.2010 (period 10 already been run)
    Posted values:
    - period 11: 50 $
    - period 12: 25 $
    Why depreciation doesn´t starts in period 10? Instead period 11 "eats" values from period 10. I want to run again period 10 but it doesn´t have values. Can you tell me why this happens?
    Thanks in advance,
    MG.

  • Adustment for wrong period transaction

    Actually, I have several invoice that is posted to wrong period, Since the previous period has been closed. I can't reverse the document and post to correct period again. So, how can I adjust this transaction in accounting. Can I post it to another G/L account? I do, how can I do that. Thanks!

    Reopen the period and then reverse your document and repost them with the correct date.
    I don't think if there is any other way except opening the period.

  • Increase future time sheet entry period

    Hi Gurus,
    Please help.  I am struggling to recall where limitations on time sheet entry are set and need help.  Specifically, we have users trying to enter time three weeks out and they are being limited to only entering time two weeks out.  Where do I go to increase the limitation for time entry so that time can be entered three weeks out?
    Thanks

    Hi,
    You have to make the setting in CAC1 for profiles ..Under time setting Period Type select 4 for monthly.......
    Regards,
    Kapil Kaushal

  • Wrong Work center picking up Time sheet

    Hi
    Scenario is as follows:
    Earlier Employee has HR assignment to one Work center 1 -WC1
    Later, Employee was Assigned to Work center 2- WC2
    Problem: When booking time sheet in CAT2 ,  for service order, WC1 was picking up, even though in Service order WC2 is assigned.
    We have deleted the Employee HR assignment from WC1 , but still in Time sheet WC1 is coming.
    Please suggest.
    Thanks.

    Is it possible for anyone to tell, from where the work center is being picked up in CAT2. We are processing time sheet booking for service order. The work center in service order is something different than what is picked up in CAT2.

  • 0ca_ts_is_1(Time sheet data (Approved) No of records are wrong

    Hi Experts,
    we need to extract the data from 0ca_ts_is_1(Time sheet data (Approved) but the problem is the no of records in the table CATSDB  with status is 849 but in RSA3 (0ca_ts_is_1) there are 500 records only.
    could you kindly suggest me any OSS notes please.
    Thanks,
    Shaliny. M

    Hi Shaliny,
    in BW you will see only the time sheet data wich are ok, that means , which have been confirmed (Approve?)
    I hope this helps you

  • CATA: Time sheet: Transfer to target componets

    Could you please please give me an overview of what CATA (t-code) does?
    I have done some config in sandbox:
    I booked time in cat2 with a sender cost ctr + activity type and receiver cost center in ECC 6.0. With out running cata (t-code), I was able to see the actuals in cost center actual line item report and PS.
    I did not understand what was the purpose of CATA ?
    Thank you
    Ravi

    However, I am not sure but, I don't thinks so, because even I am workinng in ECC6.0,  I don't belive that this kind of development sap will do in any near future EHP or version. Please  let me know you are on which EPH in ECC6.0
    Because  than there is no point of approval  Functionality or T code - CAT4. It is one of the most required functionality of Any type of Time sheet.
    There is some thing wrong. Can you double check  and try to  replicate  the same in More reliable environment Quality.
    This is not at all std. SAP behavior.  Doe some analysis in in CJi3 with whose id actual cost got posted etc.
    With Regards
    Nitin P.

  • PS - HR ( time sheet)

    hello ppl i am doing a project on time sheet which includes a link between HR and PS....
    It would be nice if anyone  can explain me how is the master cost center and the sub cost centers are linked???
    cost center is created using a TC KS01 right.. is there any way we can link the sbu cost center to the master one???? because in project system we have a cost center for each activity. so at a time a person is assigned to more than one cost center how can this be done????
    i dono if this is a relevant question... plz correct me if i am wrong...

    Archana,
    For the purpose of project cost allocation you will have to use HR infotype 0315 - Time sheet defaults.
    You will have to update the sender cost centre to which you would want to post the project cost. The employees would be able to enter activity / network relevant to the sender costcentre only.
    The org.assignment costcentre is not very relevant to the project cost allocation. Ideally when any changes happen in the organisational assignment of an employee, the sender cost centre is also changed through activating dynamic actions. In other words, the master cost centre (In 0001 - organisational assignment) and sender cost centre is 0315 - timesheet defaults should be the same
    Let me know if u have any questions.
    Regards
    Raj

  • Time sheet-Reg

    Dear PM guys,
    During confirmation of order, we are entering the personnel number and Actual work.Based on this in Iw47 we can track the hours worked by particular employee or group of employees for a paricular period(ie posting date).
    Is it possible to have the same functionality in time sheet entry(instead of confirmation of order and entering personnel numbers).Since my client wants to explore the possibility to have timesheet entry,pl help me.

    hi
    you can use CAT2 and CAT9 instead of entering the confimation of order
    for detailed procedure have a look here and select <b>Scheduling Individual Capacity Using the Graphical Planner Table</b>
    <b>http://help.sap.com/saphelp_46c/helpdata/en/fe/67ec5c9d6f11d189b60000e829fbbd/frameset.htm</b>
    regards
    thyagarajan

  • Time Sheets -  anyone have a template they could share?

    Does any one have a time sheet template they could share. Trying to put together a sheet that can calculate the following:
    IN LUNCH OUT TOTAL
    8am 1 hr 5pm 7
    ANy help would be appreciated.

    I realize this is a year old post but am donating a timesheet I created in case it may be helpful to others. Disclaimer: I am an absolute newcomer to Livescycle designer, but this form is a place to start for others to add features.
    The form uses JavaScript and accepts input from the user for the start date of the 2 week pay period, and then it calculates all the dates for the days of the week. It totals the hours entered and can be printed or emailed.
    The target email address has been left intentionally blank, and will need to be entered manually.
    Hope some find it useful...
    > http://www.davidbartholomew.com/PDF_TimeSheet.pdf
    ---and that Karma returns other kindnesses to me.
    -David

  • Payment Document reversed in wrong period

    Dear All,
    I need your help. I have reversed one Payment document in wrong period. Now Payment document is in period 09 while reversal document is in period 10.
    Is there any way to undo this reversal or else change the period in the reversed document?
    Here I need one suggestion as well. What will be the implication of this in period end closing activity?The payment document is closed and refering to reverse document as well.
    What I know is for period closing system checks for only open items.
    Please suggest on this.
    Regards
    Suchitra

    Hi Satya
    Yes You can do post with reference in F-02 and reverse the document.
    But when you initially reverse the payment document the document will close now either you reverse reversed document or closed payment document. The new document will have status as open.
    This open document will definetly effect month end closing. 
    I think solution suggested by Santosh is better one.
    Regards
    Suchitra

  • Error: No depreciation  posting required in period 009 (current period)

    Hi,
      I am getting error " No depreciation posting required in period 009"  and  009 is my current period.
       The description of the error says " Do depreciation is posted, since according to the posting cycle no postings are required in this period".   In fact this is the first time i am running depreciation. I want to post the depreciation for 1st period. More over i could not able to see the planned values in asset explorer also.
       Whenever i am entering this asset in the asset explorer it is  giving the above error. But while i run the depreciation its not giving any error. When i check in spool to view the depreciation, its giving msg as "List contains no data" check error log.
      Could anyone help me in resolving this error.  what could be the reason for this error.
    Thanks
    Sabera

    Hi,
      I checked in TABA table, its showing that till 9 the period depreciation has been posted. But i have not posted the depreciation. If it is posted, then it has to show in the planned values as posted, but its showing as "No depreciation"  and its not even showing the depreciation for other periods.  Could you able to clear this query? I wonder why it is giving this kind of error.
    Regards
    Sabera

  • Time sheet uploading from Non SAp to SAP R/3.

    Hi,
              I am trying to upload the time sheets from Non SAp to SAP with the datails like the sales oreder for which the employee worked, time spent ect.
              While uploading this from Excel to R/3 using se38, I am gettig an error saying "Enter sender activty also".
              I have checked if the activity type is checked in the CATS data entry profile, it is selected in the defaults.
             I have cheked in KP26, for the year we have given the planned activity also.
             In KSPI, I have run the price alculation for all the cost center with the activity type.
             I have seen the validity periods of the cost centers, activity typs are in line with 2010.
              I am able to upload the time sheets for a few employees and for a few it asks for the "Sender activity type".
              Please assist me, its very urent.
    Regards,
    Shilpa.

    For employees where you are facing this error, please check if Time Sheet defaults - IT0315 is maintained, and if not maintain it.
    Hope this helps.

Maybe you are looking for

  • Where do I use my Apple Id to locate workshops in San Antonio, TX on how to use my Iphone 4?

    Where do I use my Apple Id to locate workshops in San Antonio, TX on how to use my Iphone 4?

  • An error in muitplex burning"

    Hi I have attempted to burn a dvd, a running time of 50 minutes, into three subjects, but I kept getting "an error in mutiplex burning" I have defraged the hard disc but to no avail. Any help?

  • Screen flickers, occasionally goes black

    Hello all, iBook g4 bought refurb - 2-3 years ago... Occasionally the screen is flickering and I have had two occasions where the screen just went black but I could still see the desktop. Had to force restart. I have had 2 times where it was looking

  • Is it normal that my macbook pro cpu runs too hot?

    I downloaded the smcfan control since my laptop was running too hot and I only bought it 3 days ago. It says that my temperature goes up to 90c sometimes and it is too hot to even touch!! I am a bit worried, I adjusted the fan settigs to higher rpm a

  • 2011 mac mini, grey screen on startup

    I've connected a usb keyboard in an attempt to enter commands. There is no indication of any power to the keyboard, ie caps lock or num lock lights are not on. There doesn't appear to be power to the usb ports. Any ideas?