Transfer cost from CE(WIP) to WBS(project)

Dear Gurus,
My client has settled all his WIP cost into a G/L, now we want to transfer this cost from G/L to WBS.
Please assist what can be an ideal way of doing this so that we get both Fi and Co documents.
Thanks and Regards,
Manish
Edited by: mash215 on Apr 9, 2010 8:52 AM

Why dont you reverse the settlement?
Sorry, I assumed that you have done settlement from WBS to G/L.
Edited by: Ahmed Rifaee on Apr 9, 2010 1:00 PM

Similar Messages

  • How to transfer costs from one WBS to another WBS?

    Hi,
    I want to transfer costs from one WBS to another. Remember two currencies are maintained viz. local and group.
    So how can i transfer the balance such that both the local currency and group currency balance gets transferred.
    Please ensure that the transfer should show 0 balance outstanding in CJI3 report.
    I need to transfer because WBS is holding some value which was not settled in the previous year.

    Hi
    You can transfer the Amount from One WBS to Another through KB11N. In this you Choose the Screen Variant as "_WBS/Network_" and do necessary steps.
    Hope it helps.
    Regards
    Babu

  • How to transfer cost from old sales order (cancelled) to new sales order

    Hi Gurus
    I want to know, how to move cost from one sales order to another sales order.
    SD created sales order before 1 month and there was production order behind this. Production was completed and all the cost was moved to sales order and also SD has raised invoice on customer. This transaction was completed.
    The above order was rejected by customer due to some changes in the order. SD raised another sales order and production order was created to to additional work. Production transfered above stock (produce before on old production order) to new production order.
    My problem is stock is now transfered to new production order but cost is still sitting on old sales order. How do I transfer cost from old sales order to new sales order. SD cancelled old invoice and raised new one with full value (old + new work) on new sales order. Now cost is on old sales order and revenue is on new sales order.
    Please help.
    Thanks

    Hi
    I have reverse the sales order settlement, PP order settlement to sales order and I have also done KB11N for transfering the cost to the new production order.
    The only problem is I was unable to transfer labour hour confirmation as cost element used for this are not for transfering cost. If I will reverse the confirmation in PP order system will reverse material movement also which I don't want any more. Can you please tell me how to I reverse the Labour hours with out affecting goods movement?
    Many thanks

  • Transfer cost from one WBS to another WBS

    Hi,
    I have transfered Actual Costs from one WBS to another WBS manually using transaction KB11N - Manual Reposting of Primary Cost.
    But in S_ALR_87013542 report, Still the old WBS is visible with No costs.
    What are the consequence of doing the transfer and where it will affect?
    Can i delete the old WBS after transfer?
    Thanks
    Vinoth

    Vinoth G wrote:
    Hi,
    >
    > I have transfered Actual Costs from one WBS to another WBS manually using transaction KB11N - Manual Reposting of Primary Cost.
    >
    > But in S_ALR_87013542 report, Still the old WBS is visible with No costs.
    Once you do a transfer posting system will pass a credit entry (negative value) to the old WBSE. so the net effect will be zero.

  • S_ALR_87013532 report -plan cost not rolling upto the WBS/Project level

    Dear All,
    Plan cost from production orders is not rolling up to the WBS/Project level in S_ALR_87013532 ( Plan/Actual Variance report).
    Where as plan cost from network is properly rolling up to the WBS/Project level in the above report. 
    Please suggest what could be the reason for this issue. Is any configuration needs to be done for this.
    Thanks & Regards,
    Vishal

    Dear sir,
    Thanks for the reply & sorry for late response from my side.
    OPSV settings are already maintained in our system.
    Some how i realized  later that cost are actaully getting rolled to the WBS level, but we have observed one more discrepancy.
    Example -
    Production order "X" value - 100 (  as seen through co03)
    Production order "X"value- 40 ( as seen through report s_alr_87013532).
    We found that  in report  s_alr_87013532 , although my total  producton order value of 100 is represented at the WBS /Project level, but at the production order level , it is showing value of 40. 
    On further analysis we found that for production order X
    Materail cost- 60
    Labour cost-40
    The material cost of 60  is not getting fetched against production order "X" in report " S_ALR_87013532".
    There are very few cases , where such discrepancy is seen.
    Kindly suggest.
    Regards,
    Vishal

  • TX CNS41 - settled cost from internal order to WBS element not displayed

    Hi PS Expets,
    I have a question regarding transaction CNS41 "Structure Overview" where cost settled from an internal order is not displayed in in the report for a selected project. This is in a ECC version 5.0
    Settled costs from internal orders are posted with transaction type KOAO on WBS elements and when you check report RCNSTFCO you can see that the following transaction types are deselected when executing transaction CNS41:
    delete t_rpsco_m where vorga = 'KOAO' "<   insert
                          or vorga = 'KOAL' "<   insert
                          or vorga = 'KOAP' "<   insert
                          or vorga = 'KOAQ' "<   insert
                          or vorga = 'KOAR'."<   insert
      CALL FUNCTION 'HFPM_RPSCO_TO_RPSCO_LIS_CONV'
    This is implemented according to OSS note 51971 in order to eliminate internal business volume in the project structure when executing a PS hierarchy report.
    But this also eliminate the display of the cost  from the internal order.
    Any ideas or a work around in order to display settled cost from an internal order on a WBS element in transaction CNS41
    Kind regards,
    Anne

    Hello Tison.
    I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
    Best regards.
    Jens Schmid

  • Transfer Costs from AUC to Work Order

    Hi,
    Pre go-live balaces where loaded directly to the AUC, as opposed to the Work Order then settled to the AUC.
    All of our capital reporting is done at work order level, therefore I want to transfer the balance from the AUC to the work order and then re-settle the work order back to the AUC. At present we cannot see the legacy costs relating to the capital project against the work order.
    Is it possible to transfer costs off the AUC back to the Work Order?
    Thanks
    Jonski

    Andres,
      Yes you could accomplish it through the process you had mentioned.It would probably be the simplest way to accomplish your requirement as well.
    Regards
    Narasimhan

  • Suggestions required for transferring cost from GL account to a Project

    Hi,
    We have a requirement where we want to transfer cost captured in GL to PA in a specific project.
    For example:
    Incurred a misc cost 100 (outside project) and posted to GL (a/c 600010)
    Dr 60010, Cr 120010
    Later, realized this should be absorbed as a project cost (a/c 220010)
    We need some mechanism to capture cost in project ABC such that Dr 220010, Cr 600010
    If we use Web ADI to upload 'Costed' transactions: Dr 220010 Cr <NULL> (GL Transfer Status - Accepted)
    If we use Web ADI to upload 'Accounted' transaction: Dr 220010 Cr 600010 (GL Transfer Status - Received), but in this case the entry is no passed to GL, to nullify the a/c balance in 600010
    Appreciate suggestions from experts, to address the requirement.
    Ashutosh

    Hi
    You can reverse the transaction posted in GL.
    Then load the amount to Projects, as costed, not accounted EI.
    When distributing the cost in PA it will generate the right accounting, and you could interface it to GL.
    Dina

  • How to Transfer Cost From an Internal Order to Another Internal Order

    Dear Sir,
    We had one Internal Order opened for Asset Under Commission (AUC) . We also had opened another Internal Order and cost were booked in this Internal Order also .
    Now , we want to transfer the complete cost from 2nd Internal Order to 1st Internal Order . During the Transfer , we want to maintain the same GLs (i.e in 2nd Order the GLs get credited and in 1st Order the same GLs must be Debited)
    Pl guide us , how to transfer the cost .
    Regards
    B Mittal

    You can do a regular FI posting debiting and crediting the same account, with a different internal order in each line item.

  • Transfering Cost from one WBS to Other while retaining CE

    Dear Gurus,
    My client requires to transfer cost from 1WBS of a project to several WBS's. We maintain different CoCd's for all the projects. Client also wants Fi document to keep track of the transaction, hence he has reject option of Manual reposting.
    My requirement is as under, (for eg.)
    WBSA CE(111) to WBS1 (CE111) amt 123
    WBSA CE(222) to WBS2 (CE222) amt 655
    WBSA CE(333) to WBS3 (CE333) amt 998
    WBSA CE(444) to WBS4 (CE444) amt 456
    WBSA CE(555) to WBS5 (CE555) amt 124
    WBSA CE(666) to WBS6 (CE666) amt 564
    WBS's 1-6 may or may not be from same project.
    but in reality when I test settlement rule for 1st transaction, I realized a behavior of settlement rule as belows,
    Cost 123 in WBSA CE(111)  went to WBS1 but proportionally splitted to various CE's i.e. CE111= 5.2,CE111= 27.6,CE111= 42,CE111= 19.2,CE111= 5.2,CE111= 23.8.
    Please assist.
    Manish

    Hi once more ...
    i will try to elaborate based on your example...
    please use transaction OKEU to create source structure.
    Create (for example) 1 source structure (ex ZZ) with
    6 different assignments
    (ex assignment 1 for cost element 111
    assignment 2 for cost element 222
    assignment 3 for cost element 333
    assignment 4 for cost element 444
    assignment 5 for cost element 555
    assignment 6 for cost element 666)
    Then you have to maintain the settlement rule of your sender wbs element WBSA and create 6 different segments as you may probably have done already.
    Be careful when entering the settlement rule use F8 button to go to Settlement parameters and insert the source structure ZZ that you have created.
    Then in each of the the assignments fill in the appropriate Source assignment field: in the example it will be
    WBS1 assignment 1 for cost element 111 ->Source Assignment 1
    WBS2 assignment 2 for cost element 222 ->Source Assignment 2
    WBS3 assignment 3 for cost element 333 ->Source Assignment 3
    WBS4 assignment 4 for cost element 444 ->Source Assignment 4
    WBS5 assignment 5 for cost element 555 ->Source Assignment 5
    WBS6 assignment 6 for cost element 666 ->Source Assignment 6...
    This way the system will not take proportionally from each cost element the amount but will only look for the cost elements
    you have specified.
    If you have more cost elements in your wbs WBSA (sender) that you don't want to settle then create an assignment 7 with the rest of the cost elements that will not be settled.
    Run the settlement to see the results (CJ88,CJ8G)
    Try it and let me know for your findings....
    Pan
    Edited by: Panagiotis Papaspyridakos on Apr 7, 2010 4:50 PM

  • Material cost by period  for WBS/ Project

    Hi, I am working on one reporting requirement.
    Requirement is like that material  actual cost & quantity  which issued to WBS/ Project in perticular period.
    I am having some idea. Like COEP table via value type 4 I can fetch the actual cost for the porject.
    How to fetch the cost for only material consumbed by proejct.
    Please extend your help. so, I get more clear path to work ahead. 
    Regards
    Nitin P.

    Hi,
    Pls check Automatic Posting account (OBYC).
    There is G/L account maintained againt Valuation Class in Transaction GBB.
    When u assign material which is having maintained Valuation class , G/L account gets automatically picked up.
    using this u can get values from COEP.
    Regards,

  • Cost from SO

    Hi,
    Can any one explain the scenario when Production Order comes into picture during Assenbly Processing.
    How the Prod Order get trigger and how the cost will flow in PS.
    And is it possible to transfer cost from sale order to projects??
    Regards

    Hi,
    In my opinion, if you trigger PP order from SO, PS wont come into picture. The scenario will be 'Made to Order'. If you trigger Network then PS will play imp role. If possible, you could eleiminate PP order and carry out production with help of network order itself.
    Regards

  • Allocation of cost from service cost center  to production cost center

    Dear sir ,
    Will I use to distribute the cost from service department to production department  and that cost centers also using for activity planing will get currect result in product costing ?

    Hello,
    Can you clarify what you want to do ?
    Allocation of cost from service cost centers to production cost centers can be done with the help of Assessment / Distribution cycles and you can do a activity planning using the same costs as well. The steps for activity planning would be as under:
    1. Create primary cost planning in the service and production cost centers (KP06)
    2. Create activity planning in the production cost centers (KP26) without any rate
    3. Run assessment / distribution cycles to transfer cost from the service cost centers to production cost centers (KSUB / KSVB), in case you are not transferring based on activity quantity then also do SKF planning in KP46
    4. Run plan cost splitting in case you have more then one activity type (do config for splitting structure beforehand) (KSS4)
    5.  Calculate Plan price for the production cost center activity types (KSPI)
    BR // SG

  • Transfer Cost for Sub Assembly

    The client have seveal sub assemblies that are transferred from other plant. However in certain scenario the current plant can make this sub assembly. In the buying plant BOM exists for these sub assemblies. Now, how can achive the following -
    1: Transfer cost from selling plant to buying plant
    2: Since the major quantity is transferred from selling plant, this transfer cost should be et as standard cost for this sb assembly
    3: The cost from BOM roll up should NOT be set as standard cost
    Thanks for your input on this.

    Dear Anusha,
    If your sub-assembly (semi-Finished ) products are having a released standard cost estimate for the
    period,again while taking the costing run for some other FERT(Higher level assembly)materials the same
    will be taken into consideration for this new material,and again the system wont make new calculations
    for the same.
    Say suppose if B is a sub-assembly which is used in making A and C.
    Now let's assume first you take a cost rollup for A ,at that time the system will do the calculation for B
    also.Provided if you are doing it in CK40N.
    Again while taking the cost rollup for C,already calculated value for B will be used.
    check and revert back.
    Regards
    Mangalraj.S

  • Transfer material from Valuated project non valuated project

    Hi Experts,
    While i am trying to transfer material from Valuated project stock to Non valuated project with T.Code MB1B movement type 415 'Q', I am getting following error.
    WBS element  has different inventory valuation
    Message no. CN769
    Diagnosis
    The project definition for WBS element  only allows the following stock control:
    No project stock
    No project stock with defined valuation M
    ' ' = non-valuated project stock
    'M' = valuated project stock
    System Response
    Account assignment not possible.
    Procedure
    Change the settings for the project stock in the project definition (Control tab) or use a suitable WBS element.
    Kindly suggest me how to trafer material from Non valued project stock to valuated project stock.
    Regards

    Actually, you sohuld not be transferring stock to non-vlauated proejct directly. In case of non-valuated project, stock is never valuated while in case of valuated project it is valuated. So there is basic difference in valuation method. This will create inconistency if you attempt ot transfer it directly.
    You should rather transfer this stock to general stock and then transfer to non-valuated project stock.
    Regards,
    Mahendra

Maybe you are looking for

  • Issue with 6021 and CATRK-91 and adaptor

    I have used a CARK-91 with a 6210 for a number of years and have recently changed my phone to a 6021. I purchased a CARK-91 adaptor and although it charges the phone OK, the phone reports "enhancement not supported". I have tried powering off the HFU

  • Tutorial on using a non-database object with ADF?

    I'm just starting with ADF and could use some advice. I'm making my way through the first ADF 11g tutorial ("Developing Rich Web Applications with Oracle ADF") and just want to make sure I'm headed in the right direction. While the tutorial is an exc

  • Question on Siebel/JDE integration

    I am a long time Siebel developer and am fairly new to JDE EnterpriseOne. My company has initiated a switch from Siebel 7.5.3 Service to JDE. The idea is to convert the Siebel data into the JDE database, but I am questioning this approach. Does anyon

  • Iterate through RowSet within radio buttonButtonGroup

    Hi, I am trying to iterate through a RowSet within a radioButtonGroup to dynamically generate a radiobutton group. I tried the repeater function, looks like it won't work. Any example code is appreciated. Thanks! Zhenhao

  • Start wls_forms via scheduler?

    I was wondering if anyone on 2008r2 64 had tried starting wls_forms (10.3.4) on startup configuring that via the windows scheduler? (This is then not the same as making it a service as oracle talks about in 1060058.1 Seems like the service thing has