Hello,
I have saved two CO versions of my project. When i go to the project planning board the approved plan column is full of data and looks great but the other version as no information. I have SAPALL so this isn't an authorization issue. Can someone please help me work out was is wrong?
Thanks a lot
Jason

Hi,
   Basically there are possibilities of creating Plan version.
1) one you can create in CJ40 by manually feeding the Version ex:0,1,2 etc....
2) create one version in CJ40 and copy the same to another version in CJ9BS.
once the versions are created make the changes of values in the respective versionand save the changes.
Please check the version comparission in S_ALR_87013539 - Project Version Comparison: Plan.
Comming to plan board which fields did you picked up for comparission?
Rgds
Sudhir Reddy

Similar Messages

  • Unicode in Project Planning Board Screen (CJ20N)

    Hi,
    I'm facing a problem of unicode as follows:
    I inputed some unicode (Vietnamese) at Project Structure screen, It is ok. but when I switch to Project Planning Board screen, It don't work. I also cannot input Vietnamese with unicode at this view.
    Text example: "Các công tác chuẫn bị"
    Please help!
    Thanks
    Long

    Hi,
    Found something on Service.sap.com
    Thought would be useful..
    To access this page you need a login id for service.sap.com
    https://websmp108.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000557148&
    thanks..

  • Default print settings in the Project Planning Board CJ02N CJ2C

    Hello
    When you print the Project Planning Board CJ02N/CJ2C - there is an option to change the page setup.
    I would like to change the default settings for left,right, top and bottom margins for all users.
    Can anyone suggest where this would be done ?
    Thankyou
    Ros

    Hi Varun,
    Thanks for the fast repply!
    Please see below the CJ2C and CNE5 screen shots:
    Thanks and Regards
    James

  • Project planning board report to microsoft project report

    hi all
    good morning
    i want to convert the project planning board report to Microsoft project and primavera report ...
    please guide me through the steps......
    Thanks in advance
    Surya

    Hi,
    OpenPS for Microsoft project (OpenPS4MSP) is an Add-on to SAP R/3 Project System which enables users to transfer project related data between Microsoft Project and R/3 Project System.
    Refer SAP Note: 579761 for OpenPS.
    Then to integrate SAP and Primavera , you can use various integration tools available. One of them is Primavera Inspire.
    Refer :
    http://www.oracle.com/applications/primavera/primavera-inspire-for-sap.html
    Regards,
    Amit

  • Scheduling comparision in Gantt Chart- Project planning board

    Hi All,
    I Need to use the "Scheduling comparision" in Project planning board gantt chart. This is to compare the original status of activities before and after scheduling.
    But the "Scheduling comparision" button in the PPB does'nt seem to work.
    ( I am selecting the activity and then pressing the button for"display original status" )
    How do I use this functionality?
    Thanks in advance.

    Hi Potluri Srinivas ,
    After some tests, I still donot get, how does this functionalties work either.
    I assume, it is linked with the setting in 'option' -> 'planning board' -> 'diagramm area' -> 'orginal schedule'.  But I donot know, how the two things linked directly.
    If you find it out, please post it.
    Thanks and  regards,
    Zhenbo

  • Activity bar not displaying on Project planning board

    Dear All,
    I am getting one problem related to project planning board. I am working on a system in which when i am trying to run  project planning board, its coming but in that gant chart i am not able to see bar for activity. Bar for project definition and wbs coming properly. In tabular form also i can see the activities. But the only problem i am not able to see bar for activity with relationships. I have check almost all configuration related to project planning board profile and also scheduling proflies.
    Kindly suggest what can be the reason for the same.
    Regards
    Abhishek Sinha

    Hi Abdul,
    Thanks for reply. I have check all these options but all things are in place. OPT7 setting also right there. Kindly suggest what other setting can affect. In the planning board i can see the activity at left hand side corner with details but in gantt chart where we see bar chart for schdulines there activties are not coming.
    Kindly suggest.
    Regards
    Abhishek Sinha

  • Network Header at  the Project Planning Board gantt chart

    Hi again,
    Does anyone knows a configuration to allow the network header to appear in the project planning board gantt chart?
    Tks
    James

    Try transaction OPT7
    Double click on the appropriate Profile
    On the Table Area Tab, select the flag for the field "Display Network"
    Hope this helps
    Regards
    Steve

  • Project Planning Board - Customising

    Hello All,
    Do we have an option to customize project planning board.
    If yes where exactly in SPRO can we do this, and does anyone have any documentation on what all can be configured in project planning board.
    Points assured.
    Thanks in advance.
    Warm Regards,
    Jatinder Bansal

    Project planning board customization is available at IMG. path IMG>PS>Structures>Project Planning Board.
    Planning Board is based on Gannt chart. the customization includes, Define Time Profiles, Define profiles for time scales ,  Define scale for the time axis, Define Profiles for the Project Planning Board, Maintain Report Assignment from the Planning Board & Capacity Leveling/Capacity Evaluations.
    Regards
    Murali

  • Small Font for Date in Project Planning Board

    Hello Friends?
    Iam Using ECC 6.0 C Version in our Company. iam facing a problem in <b>CJ2B</b> that Date is displaying in very small font. i could n't solve that problem till date. Can any body help me where can we make settings for making fonts size bigger for <b>dates</b> other than zooming in Planning Board.
    Appreciable for ur kind information.
    Thanks.

    Hi Hari,
    Once you are into CJ2B, Please follow the following steps:
    1. Click on the icon " Planning board Assistant"
    2. Select the gantt Chart----Misc. in diagram Area
    3. In the Selection of the "Text" of "Date Descript."--- Select "Dates one-line " ( This is applicable if your date is on the left or right side of the date bar)
    4. Now you can change the Font colour, Font and Font Size, Bold or Italic.....
    5. To Confirm the setting Click on "Update graphics" button on the screen.
    6. Now, If you notice, the dates fonts will be as per your requirement.
    If this does'nt work.. Try to explore in this area only..Probably try selecting other "Text" in the "date Descript."
    Hope this helps.
    Warm regards,
    Srinivas Potluri

  • Activity Confirmation  -  Gantt Chart  -  Planning board

    Hi
    suppose i have a activity duration from 1st february 2009 to 28th february 2009
    on 15th february i confirm 0nly 10% of the work as completed in the activity confirmation screen in the degree of processing field and also enter the start date as 1st february 2009 and the finish date as 15th february 2009.
    when we look at the planning board in CJ20n transaction subsequently (gantt chart) the activity bar shows a colouring from 1st february to 15th february instead of showing only 10% of the activity bar coloured for completion of the work
    where is it possible to see the percentage completion of an activity graphically as 10% this data is available in table format in CN48N transactio

    Hi,
    we can view in table format by selecting the fileds related to percentage of completion in the project planning board (gantt chart).
    The requirement you had explore is possible in MS projects, but in standard SAP we can't view in the graphically mode.
    Regards,

  • Unicode in Planning Board Screen (CJ20N)

    Hi,
    I'm facing a problem of unicode as follows:
    I inputed some unicode (Vietnamese) at Project Structure screen, It is ok. but when I switch to Project Planning Board screen, It don't work. I also cannot input Vietnamese with unicode at this view.
    Text example: "Các công tác chu&#7851;n b&#7883;"
    Please help!
    Thanks
    Long

    Hi,
    Found something on Service.sap.com
    Thought would be useful..
    To access this page you need a login id for service.sap.com
    https://websmp108.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000557148&
    thanks..

  • SAP project planninng board to primavera....

    hi all
    asking the question for the second time....didnt get the correct input yet..........
    i have used OpnePS and converted project data to Microsoft project........
    Can any one tell me how and wht are the requirement to convert project planning board data to primavera......
    Thanks in advance....
    Surya

    Dear Surya,
    What do you mean by convert PPB data to Primavera? Assuming that you want to export the PPB data to Primavera i would like to comment that like Open PS there is no free software available to carry out the conversion you are talking about..
    Either you have to take the help of your ABAPer and develop a source code to export the required data to Primavera or if u or ur organization can afford they can go for some softwares like Inspire etc..We had integrated SAP PS and Primavera P6 in our previous project with the help of ABAP development.
    Regards,
    Gokul

  • Project Scheduling in Planning Board

    Dear Experts,
    When I am scheduling the project (all wbse and network) through planning board, after clicking the schedule icon a pop-up window is coming and in the pop-up window it is written Select set of dates .
    Any idea why this pop-up is coming.
    How can I remove poping-up of Select Set of Dates Window.
    Thanking you.
    Best Regards,
    Abdul.

    Dear Mr. Virendra Pal,
    Thank you very much for the detailed reply.
    I have removed the tick for forcast date and actual date from set of dates view button on the planning board, and kept tick only for basic dates and earliets dates, Now the pop-up window is not coming, when I am clicking schedule icon.
    Thanking you.
    Best Regards,
    Abdul.

  • Actual and Plan Versions annual view - Multiple versions per company code

    Good Day,
    Iu2019m creating an FI-CO query with an annual view of both Actuals and Plan Values, which uses period and version as input values. The dilemma is around the plan versions which are hardcoded per company codes (eg. 1 Company Code = versions 501 u2013 512)
    Can anyone suggest a possible solutions as normally there is only one version used for planning but in this instance there are multiple versions per Company Code.
    Currently the report is hardcoded for one Company Code and going forward it should cater for more than one(Company Company* 12 Version)
    Kind Regards

    Remove restriction on comp code. There could be 2 models.
    1. Include comp code, value type and version in the rows. This way you get multiple records for a comp code. One record for actual data and one record each for plan versions. To have this model at the query, the data model in the cube also should be in this way (what we call as the account model), multiple records differentiated into actual/plan by valuetype and different versions by version.
    2. Include comp code in rows. Create selections, one for actuals (restrict with key fig and value type 10, actuals), one for each plan versions (restrict key fig with value type 20, version 501. Create one selection for each version this way). This way we have one record per comp code with diff key fig for actual and plan versions. We call this as key fig model. To have this model at the query, the data model in the cube could be account model or key fig model. If it is key fig model then no need of selections. The key fig could be taken directly from the cube.

  • Project Online - offline project plan prompts for date range to be entered when accessing Resource Usage view

    When I save a project plan to my local computer from Project Online and open it up in an offline mode and access Resource Usage view I get prompted with Date Range dialog boxes with the first one saying "Show resources/assignments that start or finish
    after:" and the second one with "And before:".
    I don't have any filters that are setup in Project Online that are not available in offline mode to trigger these prompts.
    Please let me know what could be causing the date range prompts. Thanks.

    Hi,
    You probably retrieve an enterprise filter into your local file. Just open the organizer from MS Project, go to the filter tab (be sure to have your project selected in the drop down menu at the top left of right of the organizer) and delete the date range
    filter.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |