Analysis of Active Availability Control

Hi PS gurus,
I'd like to know what is the meaning of the columns in the Availability Control Analysis report (accessible via Extras --> Availability Control --> Analysis in CJ30 or Cj32)
NWA 4054504 0020                                                            
  COSP 2008 60 0071150000  COIN D PHP                                 0.00  
  COSP 2008 22 0071150000  RMBE D PHP                                 0.00  
  COSP 2008 21 0071150000  RMBA D PHP                                 0.00  
  COSP 2008 12 0071170000  KAZV C PHP                        42,902,013.71- V
  COSP 2008 12 0071170000  KAZO D PHP                        45,959,430.83  V
  COSP 2008 04 0071150000  COIN D PHP                        12,728,966.62  
Thanks and KR,
Mike

Mike,
The meaning of the columns are as follows:
Considering as example
COSP 2008 12 0071170000 KAZV C PHP 42,902,013.71- V
COSP: table where entry is stored
2008: posting year
12: value type
0071170000: cost element
KAZV: business transaction
C: Debit/Credit
PHP: currency
42,902,013.71-: amount
V: reason for exclusion from assigned value (see values at the to of the report)
Hope this clarifies
Regards
Martina

Similar Messages

  • ME21N :  Budget exceeded despite active availability control

    we have created a Purchase order  with internal order  based on Puchase requisition.
    We have noted that the creation of PO isn't blocked with error message BP604 (item && order
    budget exceeded).(the budget in internal order is 1,00 )
    We have checked this internal order with transaction KO22 .
    NB : This problem is encountered only if we create a Purchase order
    based on purchase requisition. if we create a PO directly : we have the message BP 604.
    thank you for your help

    Thanks for your reply.
    we haven't this problem in 2010. the PR and PO are blocked with the error Message BP 604 even if PR is based on purchase requisition.
    Best regards.

  • Project Availability Control

    Hi,
    I would like to confirm if availability control / check happens only at actual posting level or also during commitments and other trigger points?  Please also advise where to set the proj availability control for different trigger points.
    Vivian

    SAP as provided different business transaction groups to control budget at different levels (PR,PO, FI Postings etc).
    Please refer Note :628978
    Glimpse of the note:
    Business transactions are assigned to a business transaction group in the availability control. You can define tolerance limits for each budget profile for the availability control actions in the various business transaction groups. It is not clear which business transactions belong to the individual business transaction groups of the active availability control.
    Business transaction group 00 (Purchase requisition)
    Business transaction group 01 (Purchase order)
    Business transaction group 03 (Goods movement)
    Business transaction group 04 (Financial accounting document)
    etc.
    Venkat

  • Availability control not activated - Real Internal Orders

    Hi Experts,
    I have created one order type with Object class overhead, budget profile 0000001. Defined  Tolerance Limits for Availability Control.   And I have created one order and maintained budget. If postings are exceeding the budget, system is simply saving it not giving any alerts.  I have done KO30, system showing the message "Availability control not activated in any further objects".  Where I  am missing the configurations?
    Regards,
    Rajeswari

    Hi,
    Check whether the commitment management has been activated.
    Check in transaction OKKP for Order management & commitment mangement active in controlling area level.Check the company code assignment also in controlling area.
    Then check the activation of the Activate Open-Item Management in Order Types in Tcode KOAO.
    whether commitment mangement tick is active against the order type.
    Activate the availability control as automatic orelse activate when you assign budget in KO22 transaction.
    Check both the setting.In some case it may not work in DEV server if you active later,Transport request to QAS & check it will work.
    Regards,
    Raj

  • Problem in activating the Funds Management BCS and Availability Control

    Hi experts.
    After running the program RGLIUGEN to generate the required includes in program SAPLGLIU, the generated programs come with syntax errors. When I manually correct the errors ,the program post the budgets and budget releases but does not update values for availability control to the effect that whenever one tries to post any amount against the budget, we get the following error  :
    Overall budget exceeded by 100.00 USD (FM PB Availability Control) for document item 00001
    All suggestions will be appreciated

    The following tolerance limits regarding payroll entries are currently configured in the system. Once the 90% level of the budget is exceeded, the system will generate one notice. After the 100% is reached, the system will repeat the notice every time an entry occurs.
    90%      Warning message – Internal mail (only once)
    100%    Warning message – Internal mail (repeatedly)

  • Question about project plan value and  availability control

    dear expert:
    I had built a project, and with CJ30, Allocated budget is 10000, in one of  WBS element.
    I created  a network and internal activities,
    when I  assiged a material component (Res + PR) and system can be saved even if the total plan cost value is crossing the budget value.(There is no PR created, now. )
    But, Budget checking is showing error message that budget is exceeded when I created any external service activity and crossing the budget value.(There is also no PR created, now. )
    My question is: what is the difference of the two plan value? Why one is relevant to the budget,and the other is not?
    Note:1) the tolerance limit with ++ (all activity groups), usage say 100% & action 3 (error) to the budget profile. The budget prifile is considered with only overall budget.
    2)In tables COSP, "value types" are all 01 (plan), but VRGNG field values ​​are different, components plan is: KPPE
    Service activities are: KPPP
    3)in CJ30 u2013 Extras>> Availability Control>> Analysis. I could see the following in red colour, these values system not considering into account.
    Entries in this color make no contribution to the assigned value!
    V: Value type not relevant ( Act./Plan/Stat.Act./Stat.Plan/Commt)
    D: Delivery
    S: Settlement to object with no budget control
    R: Revenue cost element
    C: Cost element is exempt cost element
    M: Minimum from actual + commitment and plan per order value update
    P: Plan value is not on apportioned order / network
    B: Plan Costing Single Position
    S: Funds Commitment in Balance
    Following is for material
    COSP 2011 01 8001110100     0000000200 KPPE D RMB             200,000.00  RMB   B
    Following is for service
    COSP 2011 01 8001110400  KPPP D RMB                                10.00  RMB
    regard
    mao jian

    Hi,
    Its not per item category. If  N or L sytem will check the budget if in your system if proper GL's are maintained in OBYC settings BSX and GBB > VBR nad cost elelemtns are created for them. for this you have to cosult with your MM / CO consultant.
    PS is highly inteergratd with CO and all values are updated per cost elements. If values are not updated in cost elements then budget chek wil not happen.
    In you case for material values may be updated in cost elements due to improper OBYC setting so budget check was not done.
    Chekc your OBYC setting and try to create material PR system will check for the budget.
    Check and confirm.
    regards,

  • Availability control on statistical WBS element

    Hi everybody,
    The issue deals with <i><b>availability control on statistical WBS element</b></i>.
    <u>Part 1</u> : I released 25000 as budget (CJ32) for a <b>statistical WBS element</b>.
    Availability control is active for this WBS element.
    We made a good receipt (MIGO) for 20000 on an AUC (asset under
    construction) - so we get the value as statistical value on the WBS
    element -, then invoice verification (MIRO) and finally the asset
    transfer (ABUMN) from asset under construction to fixed asset.
    On this statistical WBS element we get +20000 (MIRO) and -20000 (ABUMN).
    The problem is that the amount that is used for the availability check
    is 0, instead of 20000 as you can check !!!
    We set a budget on the statistical WBS element in order to have the
    availability check ... and this is not working as the system in the described case shows 25000 as available but for me we should have only 5000 (= 25000 - 20000).
    <u>Part 2</u> : This is working perfectly (I get the expected value for available) when we use a <b>"real" WBS element</b>, put an expense on it, then run the period end closing tranction CJ88 in order to transfer the cost on an AUC, and finally run CJ88 again in order to transfer from AUC to fixed asset.
    Did anybody already encountered this problem with statistical WBS element ? How did you solve this (we would like to keep our statistical WBS element) ?
    Thanks in advance for your help.
    Benjamin

    Hi Benjamin,
    Pl go through the link below :
    http://help.sap.com/saphelp_47x200/helpdata/en/3e/a98337dd34ca76e10000009b38f8cf/frameset.htm
    I have not faced this but as far as I remeber for AUC Statistical assignments have some limitations.
    Any specicfic reason for keeping the WBS Statistical? Are you able to see "0" zero on this WBS in CN41.
    Regards,
    Sudhanshu
    PS: Assign points as a way to say thanks.
    Cheers,
    Sudhanshu

  • How to use active X controls to read/write protect an excel or word document created by created by Save Report to File VI

    Hi all,
    I'm trying to creat a word and excel documents using Save Report to File VI. When wiring a password to this last VI, the document created are only protected against writing but not reading. How can I use active X controls to password protect these documents against reading?
    Thanks a bunch!
    O

    There is no predefined functionality available in LabVIEW. So you have to implement this on your own.
    It seems to me that you own the Office Report Generation Toolkit. You can use the Excel Get ActiveX References.vi from the Excel Specific >> Advanced palette to get access to the "generic" ActiveX Excel references. Starting from this point, you can use property and invoke nodes to get to the setting you are going to modify.
    Please refer to this link for information on Excel password protection. I have not searched for the object giving you access to those settings though....
    hope this helps,
    Norbert
    CEO: What exactly is stopping us from doing this?
    Expert: Geometry
    Marketing Manager: Just ignore it.

  • Budgeting & Availability Control

    Hi Gurus
    We had activated Internal Order Budgeting & Availability Control check & had used it to procure Fixed Assets. The internal order is created (t-code KO01) & budget value is assigned (t-code KO22). The internal order is assigned to an asset (t-code AS01). This asset is used for procurement in MM module - purchase order (t-code ME21N), goods receipt (t-code MIGO) & subsequently invoice verification (t-code MIRO).
    We have a unique situation. Some of our colleagues have created the order, assigned the order to the asset & completed the procurement cycle without assigning the budget. Now we would like to assign the budget to the internal orders we had missed & would like to check the availabilty control for all the transactions we had carried out. Is there a way to meet our requirement. What are the alternatives available to us?
    Thanks,

    Hi,
    I suggest you collecting the data on these orders (KOB1/KOB2), sum up the amounts and check what budget these orders required. There is no retroactive availability check possible. You can switch it on, but it will be active only for future postings.
    Regards,
    Eli

  • Purchase Requisition Committment and Availability Control

    Hi,
    We are using availability control based on usage 1 i.e. during the budget allocation/release, the availability control gets activated.
    Now i have poject structure where a user have already created PR i.e. committment of 10000 USD and whereas i got an budget of 5000 USD. So when i go in CJ30 and CJ32, then system is not allowing me to release the budget as the existing committment is greater than the budget.
    My question is that do this PR committment is to be considered as Real comittment. My understading is that if there is no budget then the committment of any type should not be allowed at first instance. How generally it works?
    Thanks in advance

    My understading is that if there is no budget then the committment of any type should not be allowed at first instance.
    Rajesh, Not everybody will use the budgeting functionality for Project, So it is not forbidden in Std. SAP design. But, if you want to forbid posting of committment cost or actual cost before budgeting, then read these notes
    Note 599813 - Availability control before budgeting
    Note 602588 - Availability control before budgeting
    Follow the suggestions mentioned in the note.
    Is there anything by which we can avoid the committment creation by using the user status on WBS element (even though the commitment is created at activity, it gets rolled up to the parent WBS)?
    As Gokul mentioned, you can restrict creation of PR on WBSE by User Status, but you cannot restrict rolling up of Commitment cost from activity to WBSE by any user status.
    Edited by: Ahmed Rifaee on Aug 13, 2010 3:22 PM

  • Internal Order Budget - Availability Control

    I have done the budget profile, entered the budget figures, created internal order budget with the required profile.  However, when I entered the fi document with this statistical IO, system does not give any message as per the tolerance setting actions.  I tried to run the activate availability control again.  But the system gives a message that availability control is not activated.  Why this is happening ?  Where can I see the availability control is activated for this Internal order ?

    Hi
    1. Check if your order is released
    2. Check in budget profile (OKOB) if activation type is "1" and whether you have checked "overall" or not....
    3. Hope you have defined tolerance limits against the combination of contr area and budget profile
    Regards
    Ajay M

  • Can Budget Availability Control be turned off at WBS elements Level?

    For Project and WBS elements, we activate the budget  availability control in the budget profile and assign the budget profile to the Project. So once we budget one WBS elements under that project and release the project, the availability control is active for all WBS elemens under this project.
    My question is whether we can turn off the availability control for one WBS element under that Project and let the availability control on for the other WBS elements under that project.
    thanks,
    Ting

    Hi,
    I doubt if this can happen. CJBW will deactivate avalability control for entire project. Try OPSX for that particular WBS, it will reset budgeted status. Not sure if this will help, try and confirm.
    One more way could be assigning userstatus to the WBS and restricting 'Availablity control' by that status. This option looks more practical.
    Regards
    Edited by: Shrikant Rakate on Sep 10, 2008 9:21 AM

  • FUNDS MANAGEMENT (FM PB Availability Control)

    BUDGET CONTROL, FUNDS MANAGEMENT (Budget Control Document 1700013859).  The Activity Group is PAYROLL.  Getting message that states the following:
    Budget Consumption 122,733.14 USD (FM PB Availability Control) less than annual budget for document item 00001.
    Can someone tell me what the threshold is?  (i.e. 90% expended) and can this warning message be modified from the standard SAP message to better inform departments as to what is occurring.  They have not run out of funds, but have reached a threshold that needs to be monitored.

    The following tolerance limits regarding payroll entries are currently configured in the system. Once the 90% level of the budget is exceeded, the system will generate one notice. After the 100% is reached, the system will repeat the notice every time an entry occurs.
    90%      Warning message – Internal mail (only once)
    100%    Warning message – Internal mail (repeatedly)

  • Availability Control problem

    Hello Friends,
    WBS actual postings moved over defined budget tolerance value.Availability
    control type is 1, CJ03 shows the status AVAC (Availability Control Active).
    In configuration for availability control it is specified if total value reach 90% of budget value then throw an  error and if it surpases 110% of budget value  throw error message
    When i checked the 'Change documents in Status management' for the WBS element ISBD or insufficient budgeting status changed lot of time from 'Active' to 'Inactive' as shown.
    ISBD Insufficient budgeting"
    Inactive  08/01/2006 11:29:36 PDUFRE            Create Purchase Order           
    Active     07/28/2006 02:56:14 RKNA    
    Inactive  05/18/2006 08:30:24 JGUIDRY            Change budget operative
    Active    05/12/2006 14:57:28 PDUFRENE        Create Purchase Order           
    Inactive 05/12/2006 11:14:53 RHYMEL             Change Purchase Requisition     
    Active   05/12/2006 10:18:41 SFOLSE             Create Purchase Requisition     
    Inactive 01/18/2006 15:41:04 PPALA                Create Purchase Order           
    Active   01/18/2006 15:41:04 PPALAHAN         Create Purchase Order           
    ISBD or insufficient budger is shown if as per the availability control restriction actual or committment surpasses proposed tolerance limit.
    Is it possible to surpass this error and post to WBS.? Does this depends on any user status, because when i tried simulation is quality system ,system popped up error showing value exceeded available limit.
    Please give your suggestion, i heard this is a serious SOX violation.
    Rahul

    Hi
    ISBD error message will come the moment when the budget is almost exhausted. You could have done Cost planning and Budgeting for the WBS element. If you are utilising most of the amount of budget within the short period, system will throw this error as in the background, system divides the amount budgetted for individual months period and system forecasts the expense for the balance period based on the actuals incurred for the WBS element till that period. This happens because of the Availability Control being active.
    Regards,
    K Lakshmanan

  • Why doesn't firefox use Active X Controls

    I need to have Active X Control to access my banking process. I have this on IE but prefer to use Firefox, how can I make Active X Control work on Firefox

    Firefox does not support ActiveX technology for multiple reasons.
    * ActiveX is only available on Windows operating systems, and as a result webpages that require it will not work on Linux or Mac.
    * ActiveX integration with the Windows operating system has made it a target for malicious software.
    [https://support.mozilla.com/en-US/kb/ActiveX]

Maybe you are looking for

  • The system of installing updates has changed, and no longer works

    Updates used to happen by Firefox asking "There is an update for Firefox - do you wish to install it now or on restart?". I would check the restart option, and next time I launched Firefox it would tell me that an update was being installed. Now I ge

  • HI, IN TRAINING AND EVENT MGT

    HII Each employee attending training can be required to complete a Pre and Post Learning Evaluation form. A dynamic action can be included in the system which automatically includes the creation of a date for completion of a Pre Learning and Post Lea

  • Display keeps going to sleep?

    The last few days the display (maybe the whole computer?) has been randomly turning off on me and the light on the open button turns on, as if my computer is sleeping or closed. Sometimes it takes a few taps on the spacebar to turn back on and someti

  • I Want to Buy MacBook Pro 15" In Installments Can Anyone Here Tell me The Plans Of Installments

    I Want to Buy MacBook Pro 15" In Installments Can Anyone Here Tell me The Plans Of Installments... Please Give Me Proper Information With Interest.. Thanks In Advance

  • How to make and use customised DataSource

    Hi Gurus. If we are not making cubes for Inventory etc for which DS is already available, how can we create data sources in order to load the desired data in BW.means if Database fields are entirely different kind regards rajesh