Hello,
We have a requirement to do automatic time confirmation (while saving the order) on an operation when the user selects "DONE" standard text key on Operation line item. Is there a user exit or BADI available in Plant Maintenance that can be used for Automatic time confirmation?
I went through some of the user exist/BADI in PM and didn't find anything for automatic time confirmation. The only thing that I found useful was user exit CONFPM03 (which allows to carry our own checks once and operation is selected for confirmation).
Appreciate your responses. Thanks
Hi ,
Normally thru confirmation we enter actual hrs worked in IW41 .. but if you do not want to run that tcode then not sure of any BADI but i would suggest you to create a Z Programme which runs as a batch job at some 30min everyday . The Z Programme checks all the PM orders of particular order type which are with released status and then gets into operations and checks for standard text and if its value is DONE then calls programme SAPLCORU - IW41 Programme .. you can suitably put a variant for that batch job .. plz check the option with ABAPer ..
regrds
pushpa
Similar Messages
-
Automatic goods issue for outbound delivery, during the transfer order confirmation
Hello,
Could you please advise how to realize automatic goods issue for outbound delivery, during the transfer order confirmation in the WMS.
Now after creation of outbound delivery, i can't post the goods issue. Before i have to make the transfer order and confrim it and only after this i can post the goods issue in the VL02 t-code.
Could you please advise - what i have to customize that to make automatic GI for outb. delivery (i mean with creation material document) during the TO confrimation.
Thanks in advance.Hi Iiya
Check the below setting, might be helpful -
Operations in Preventive maintenance order has to release then only order has to TECO
Hi,Friends
is there any standard in R/3 that as soon as i am not releasing Operations in Preventive maintenance order, order should not be TECO
when ever i have released Operations then only Preventive Maint order has to be TECO
Your response is highly appriciated
Regards,
KumarKumar,
I'm still confused...
When you release the order header (REL), then all operations are also set to released (REL). You cannot individually release operations using the system status.
However, you can set user statuses for each operation which are configured in the IMG.
Please give more details.
PeteA -
User exit or BADI for technical closure of a maintenance order
Hello,
Please I need the help of you.
Is there any User exit or BADI for technical closure of a maintenance order
regardsHello ROB,
Please do not post duplicate thread.
You can check below two BADI's. ATP_PUBLISH_RESULTS and IWO1_SCREEN_MODIFY. Because I have got two BADI's through finder.
You can also check WO10004, WO10005, WO10006, WO10007, WO10008, WO10009, WO10010 and WO10011 user exits.
Thanks & Regards,
Abhijit -
Goods movement in QC confirmation for inprocess operation
Dear Friends,
I am doing inprocess inspection for routing operations. After results recording, I get the window where I am entering yield.
If I go to confirmation tab, I can enter the activities and qualntity. But ther I am not getting goods movement tab.
I want assign batch no. to material in the goods movement tab.
How can I get it?
Please help me.
Waiting for reply!
Thanks!
KiranNo Inputs?????
-
Confirmation for sub-operation
Hi Expert,
As we know that confirmation has to be maintaned for each work order confirmation.
Current condition, we also have to maintained confirmation for each work order sub-operation.
Is there any possibility that only operation level of work order that need to be confirmed? instead of sub-operation level? in assumption that work order created with both operation and sub-operation
illiustration:
Operation 0010 Greasing
Sub operation 0010/0011 cleanning
Sub operation 0010/0012 inspection
Confirmation conducted for operation 0010 Greasing only, instead of all operation and sub operations
Thanks
Pls Help
RgdsLeni,
There is nothing in the standard system that would force you to create confirmations at either operation or sub-operation level (unless you have done something in your system)
PeteA -
Unwanted automatic time change for no reason
I've got a 6021 that changes time by one or two hours for no apparent reason whether it's in automatic time adjust or not.
The firmware version is 4.10 092005; has it been improved since then?
CKYes, current version is 04.90. A firmware upgrade should sort out the problem for you
Best Regards
Dave -
PP - Actual time taken for an operation - seperate entry
Hello
We are on ECC 6.0
Whether there is alternate way available in SAP which enable us to enter separately the actual time taken by technical labour, non-technical labour and various machine for a particular operation in a process order (currently actual time for the operation as whole is entered)
pls. guide us.
Thanks.I am not sure but you can have different activity types for different labour and enter the time in that. We had proposed this to one of our clients but he said he didnt want it to be so complicated.
Regards
Yatin Thakkar -
How to analyse actual cost for each operation in Process/Production Order?
Hi all,
IN SAP, I know that we can analyze plan cost for Operation in Process Order/ Production Order.
However, I can not analyze Actual cost for Operation .
I know the object when I good issue material is ORDER, not OPERATION.
But, as requirement of users, they want to analyze actual cost for each Operation.
CAn SAP do this analyze?
If Yes, What should I do in SAP to have this reports?
THanks in advance,
Emily NguyenHi Emily,
as I see from one other message that you're using material ledger. Then your expectation is apparently to also see the actual costs of materials in your production order by operation.
This is not supported. Actual material costs are handed up in material ledger multi-level settlement from one material to the next, bypassing the production orders.
That means the production order will always contain the material costs valuated at plan price, not at actual price.
For activity prices that might be better, when you revalue the orders at actual activity prices with CON2. But even there I am not sure that it will always be assigned correctly to the operations.
There is currently an enhancement in development, the operation level costing. But that will affect more the planned cost side not the actuals. Might be interesting to learn more about your requirements and the use case behind.
best regards,
Udo -
User exit for changing operation scap in PP order
Hi,
I want to know user exits for changing operation scrap in PP production order. Please help
Regards
ShaliniI could found only one at the moment...
QEVA0002 - Calculation of share of scrap in inspection lot
check if it is helpful.....else u can go on
CMOD - Utilities - SAP Enhancements - (Remove Maximum No of fields) - Execute (F8)
You will get all user exits.
Now i need points.... :)...My score is not gettin increased... lolz
kapil -
Multiple doc type setting for service PR generated from Maintenance order
Hi Gurus,
My client has multiple company code and has different document type for PR and PO as per the company code. For generating the service PR from maintenance order system take the document type of PR defined in the config.
Is it possible to define multiple document type for service PR depend on the company code/ Plant level?
Kindly help.
Regards
DPHi Ravi,
I used the User Exit COZF0001 . Since we can assign only one PR doc type in the config .
I have assigned one PR doc type in configuration which will work for a company code and all their respective plant. So in this case user exit wont do any job for changing the doc type.
You will defined a condition in the User exit saying that if company code /plant which you get it from maintenance order is not same (Config ) then provide the PR doc type which you want to create for respect plant or company code.
I dont have coding right now with me. You need a small coding to be done to create the separate PR doc type in EBAN-BSART
with respect to plant . Check in your configuration at what point of time you are creating the PR either in saving or release of MO. You can take the even to activate the User exit.
Consult your ABAPer they can do in 10 min.
DP -
Confirmation for Split operation in Production order
Hi Experts,
I have one production order say order no. is "100000000000" and its order qty is 100pcs and in operation no. "20", i have splitted the operation into two individual capacities and allocated 50pcs to each individual capacity. Now can any one explain me or tell me the steps required for confirming the operation quantity by individual capcity.
Regards,
Satya.Hi,
Thanks for your response on my post.
As you mentioned I am using T-code CO11N for Production confirmation, but in this screen if I select operation no. 20, by default, system is read work center from production order "operation overview" screen. Now I want to capture the confirmation quantity against "induvidual capacity" and want to see some reports based on "induvidual capacity" level of the same work center.
Could you pl. advise on this.
Regards,
Satya. -
Received a print confirmation for a job I didn't order
I received a "ePrint Job Received" email for a job I know nothing about.
The email came to me from a catchall address of a domain I have:
[email protected]
I don't know what to do about it, I don't want to be billed for anything, and I have no idea how ePrint works, or how you would have billing information for me anyways.
Please advise.What is ePrint?
HP ePrint is a free service that allows you to print documents and photos from any mobile or network-connected device (such as a phone, laptop, tablet, or other mobile device) to your HP ePrint-enabled printer. Each HP ePrint-enabled printer has its own unique email address. After you enable HP ePrint on your HP ePrint-enabled printer, you can print from your mobile or network-connected device by sending an email to your HP printer's email address. With HP ePrint, you can print from anywhere, at any time. If you can send an email, you can use HP ePrint.
Source: Getting Started with ePrint -
Report for basic dates change in maintenance order
Dear friends,
Client requirement is to see the orders for which basic dates have been changed. The scenario is when preventive maintenance is done , if the work cannot be done on the date(basic date in maintenanc eorder), the basic date is changed for a convenient time. They want to have a report showing all the ordres for which the basic dates have been changed and the changed dates detail( ie. initial basic date, changed basic dates).
best regds
ArunOnce you get the Change Document header data from CDHDR you will then need to get the change details from CDPOS.
Have a look at program RSSCD200 via TCode SE38.
There may well be a suitable function module for this...
PeteA -
Automatic inclusion of a task list in a Maintenance Order
I have created some general maintenance task list. When I want to include some operations from the task list in a work order,
the complete list is included. Is not possible to select some operations to be included?
ThanksHi,
you can have selection of operations while integrating tasklist into order through customizing. The node is Plant Maintenance and Customer Service-> Maintenance and Service Processing->Maintenance and Service Orders-> Functions and Settings for Order Types->Default Values for Task List Data and Profile Assignments. In this screen flag the operselection for the given ordertype and plant.
Maybe you are looking for
-
I bought a radeon 9800 pro graphics card to upgrade my 64mb. stock card and before installing noticed that the new card has one DVI port and one VGA port. the box says it runs dual displays, right now I have dual CRTs running but want to run two flat
-
Changes made in iWeb not reflected online
Hello, I succesfully rehosted my website after mobile me closed and decided to make some changes whilst I was doing so. With the site live again I noticed an incorrect link. I have fixed it in iWeb and tried to publish the site again. iWeb tells me
-
My Mac crashed. Can I retrieve the data somewhere that was entered before the crash?
I use numbers to organize all of my work. I hadn't saved the new information for about a day and a half and my Mac crashed. That's never happened before. When i restarted the computer, all of the new data that was entered since the last save was g
-
Playing clips to log and set in and out points for scenes I will use later. Something changed with the new update and I think it is a bug. When I hit the I and O keys to set in and out points on a clip before dragging to the sequence, it zooms in o
-
File not found when clicking public links to share files through Creative Cloud
Only getting File not Found page from links made to share CC filles. Can see them if I'm logged in but I dont need to share them with myself obviously! So no good for sending / sharing with clients as described in the features? Please advise because