Budget control issue

Dear all
First I am doing bottom up planning and then i am doing copy of planned total to budget.When i am doing change the quantity of material and rate,the system showing error of budget exceeding 
Budget for WBS element RE-09-06.01 was exceeded by 1,875.00 INR in document item 001 Ntwk actvty 4000005 0010 .
Regards
K.Muthukamatchi

this is now locked
thread is duplicate
please update previous thread and do not unnecessarily create new one
I will delete this thread later on

Similar Messages

  • Beginning Balance of Accumulated Repair Cost and  Budget Control

    Hi All,
    My client has two requirements which I have problems working on in SAP.
    1. How do we put the beginning balance of accumulated repair cost of each equipment? Example Equipment A had $ 40, 000 worth of repairs prior to the company's use of SAP, and this balance becomes the initial balance during repair cost reporting (thus if the first work order issued for that equipment in the SAP system costs $5,000, accumulated cost in cost analysis shatll be $45, 000 alread) .
    2. How do we implement budget control in Plant Maintenance, such that a work order that is over budget cannot be released? or needs to be approved by another more superior user before release?
    Thanks, answers would be of great help.
    Regards,
    Andrew

    Andrew,
    I suspect the only way to do this without Asset Accounting is to create a bespoke ABAP report. You would also need a customer table to hold the repair cost/equipment data. Alternatively, if you have a cost object per equipment (say cost centre) then you could add this value to the cost centre. Either way I would discuss the issue with you finance team first.
    In terms of budgetting; this can be done 3 ways:
    - Investment programs (IM)
    - Projects and WBS (PS)
    - Individual maintenance orders (PM)
    You can set threshold parameters which determine if the order can be released..
    PeteA

  • Budget control for automatic Purchase orders

    Hi All,
    We are facing problem in budget availability check for automatically generated Purchase orders through MRP run.
    We are able to control the budget check for manual Purchase orders  but how can we control budgets for automatically generated Purchase orders.
    we are using IM budgeting for orders.
    Please let me know your valuable inputs for the above issue.
    Thanks in advance.
    Regards
    Nagesh

    Hi,
    You have to run FM_MRP_PR transaction in order to transfer MRP documents to FM for budget control.
    Regards,
    Eli

  • Budget Exceeded Issue - Activated budget profile for existing project

    Dear Experts,
    I have a Project and not using any budget profile, already actual data exist only in CJI3 no data in CJI5.
    Now I assigned Budget Profile in that project.
    While entering Budget in T-code CJ30, I can see values in assigned values for a wbs elements.
    Example -
    WBS Element - XXXXXX-02  - 2000 (Assigned) - Here Budget Profile not assigned in the project
    Same WBS Element - Once Budget Profile assigned, when am assigning same 2000 budget am getting budget exceeded issue.
    If I give 2500 I am not getting any errors, My tolerance as only Warning message.
    Please Suggest - Screenshot attached
    Thanks,

    Hi Pavan,
    As soon you enter your budgeting fig the availability control triggers, this check your assignment with available budget.this the reason you are getting error as you say there are already actual posting in CJI3.In this you need to balance first the fig which is appear in assigned column in CJ30.
    Its a good practice to give budget first release it & then start procurement,confirmation etc.
    Check this in budget profile availability control.
    Regards,
    Sachin.

  • Plant stock procurement with budget control

    Hello,
    Our client has centralized stores which caters to FOS (Factory Operating Supplies) requirements of various projects and departments. Some of the FOS items include u2013 Wielding rods, Personal Protective Equipments (PPEu2019s) etc. These are procured at plant level.
    We have following requirement u2013
    1)     Above mentioned FOS material should be procured as Plant stock with budget control
    We have following queries regarding this requirement u2013
    We want this material as plant stock which will be issued as per requirement. If I create PR, PO without account assignment, there is no budget control. 
    If we procure this material against cost center, material do not come in stock.
    Please guide for solution.
    Regards,
    Milind Dumbre

    Hi
    If you have PS implemented
    then you can use account assignment category Q in PO and WBS element which will control your budget
    Or Go with value base contract or Quantity base contract with vendor so you can control it
    Regards
    Kailas Ugale
    Edited by: kailasugale on Nov 12, 2011 7:48 PM

  • Assigned and Committment Budget Control in AR

    Dear friend,
    Would like to find a solution for a business case for my company.
    AR Credit Control Dept would like to implement a control for all Credit/Debit requisition (currently is through hard copy mannual)by key customer accounts for list of Advertising and Promotion within budget.
    a) Credit/Debit Requisition to be log,
    b) actual Credit/Debit issued to be checked again budget.
    c) able to have flexibility to increase/decrease budget.
    d) there are few programs for each key Customer Account
    e) there are list of product brand to be promoted in each program.
    f) Able to view an any point in time for the assiged, actual and balance budget for each Key Customer Account.
    Consideration :
    i) Currently we had already used IO to denote brand to be promoted but without activating budget control.
    ii) IO may not be suitable as I cannot check for credit/debit requisition raised.
    iii) this proposed module has to be in AR related.
    Please enlighten me which would be the most suitable module to be explore in SAP R/3 4.6C ?
    Thank you & best regards
    Elaine
    Moved to this forum as a more appropriate place (Marilyn)
    Message was edited by: Marilyn Pratt

    Hi,
    thanks for your respond. However your may have misunderstood my question... Anyway thanks a lot.
    Basically, my users would like to track some Advertising and Promotion Expenses which currently is done at FI-AR. Promotion Expenses were claim by customers monthly and we wanted to control these claims as there is a capping to it. Very often these claims from customer were exceeded at year end.
    I have done the following proposal :
    a) using IO no, and Budget to monitor the promotion
       claims.
    b) using PR to PO to show the commitment amount before
       actual (=GR) via IO no.
    c) linkaged customer with vendor codes
    d) contra customer with vendor line items
    However, user wanted to list down :
    1)the customer (=vendor) that has allocated with this budget. (how)
    2) able to change budget (IO maintenance)
    3) how to apportion by % for each IO to say 3 brand of
       products. note that i have already activated CO-PA in
       the system & IO is currently used as statically.
    Would appreciate any advise...
    Thanks & cheers....
    Elaine

  • Budget Exceed Issue in work Order (P.O) in Production Server.

    Hi Friends,
    I am getting different type of budget exceed issue, that to only in Production server.
    Here the issue is when I am creating the work order P.O (Acc.As. Cat.P, Itm Cat. D) with different service line items with respective WBSe with in the budget limit, then I am doing SES for some quantity, now when I am changing (I am decreasing not increasing) the same P.O line item available quantity and creating the new version now system is calculating the old version line item quantity + new version quantity (nothing but double) then giving budget exceed error.
    One more strange thing is, if I change quantity for one line item then system is giving budget exceed error for another line item which is having the different WBSe which was saved with out giving any error at the time of P.O creation.
    This issue is happening only in Production server ....same scenario I have run with the same values in both Dev. and Qau. (Where the config. is same in all 3 clients) but in both the clients it is working fine...but in production why the system is behaving in such a way I am not getting. 
    In the below I have given the test scenario...
    Service P.O Creation
    Line Item
    P.O Quanity
    Value
    WBS
    Budget
    Commitment
    SES. Quatity
    Actual cost
    1
    10
    100
    WBS 1
    2000
    1000
    5
    500
    2
    20
    200
    Wbs 2
    4000
    2000
    10.00
    1000
    3
    30
    300
    WBS 3
    6000
    3000
    15
    1500
    4
    40
    400
    Wbs 4
    8000
    4000
    20.00
    2000
    Service P.O change with new version
    Line Item
    P.O Quanity
    Value
    WBS
    Budget
    Commitment
    SES. Quatity
    Actual cost
    1
    6
    100
    WBS 1
    1000
    1000
    5
    500
    2
    20
    200
    Wbs 2
    2000
    2000
    10.00
    1000
    Budget exceed with the double value
    3
    30
    300
    WBS 3
    3000
    3000
    15
    1500
    4
    40
    400
    Wbs 4
    4000
    4000
    20.00
    2000
    If any one has come across with this type of issue and solved ...please suggest me ..
    Regards,
    Srikanth

    Hi,
    I have face similar issue in deleting PO line items.
    Even though I delete items, system check budget for deleted qty with the currency conversion + value & gives budget exceed error.
    In some cases we have asked user to deactivated AVAC asked to do the transaction, which is not recommended.
    You can try running CJBN & CJBV in sequence for affected WBS.
    Thanks & reg,
    Sam

  • Budget Control at top level WBS only

    Hello All,
    I have a requirement from client where I need to activate the Budget control (90% warning and 100% error). I have done the setting accordingly.
    Now the scenario is such that when client is doing budgeting, they are allocating the budget only at top level WBS (they have a different legacy, where they are doing there detail planning n budgeting, but since they want the feature of budget control in PS, they will do minimal budgeting in PS). As per my settings when I budget top level WBS and save the availabity control is activated (with no budget on lower level WBS). Now when I try to do some postings/or assign that WBS to PO, even with a value of 1 USD, i am getting an error of budget exceeded, which is fine as per the settings as that WBS is having 0 budget.
    The requirement from client side is such that they want AVAC to be activated only at top WBS and do postings to lower WBS. But if the total of lower WBS exceed the budget of top WBS, they should get an warning or error. For example:
    WBS level  BUDGET ACTUALS
      1               100
      2                              50
      2                              50
    so as soon as the actuals touch 100, the system should give an error/warning. Note that the 2nd level WBS are not budgeted in SAP, so budget is 0 on them.
    I have 2 questions:
    1.Is it possible to activate AVAC only for top WBS ?(without any enhancement/development)
    2.How the AVAC will work, if the total of 2nd level WBS exceeds the budget of top WBS (as explained in example above)?
    Awating your replies.
    Thanks
    Sarang

    Thanks Virendra, it was useful.
    I tried other way round also i.e. by not marking the release tab in OPS9 and activating AVAC in CJ30.It works in that way too.
    For my other question, regarding activating AVAC only at top level, we can achiebve that by using transaction control in user status.
    Thanks
    Sarang

  • Manual Budget Planning with Budget Control System

    Hi Friends,
    The below scenario i have found in Periodic/Closing Operations:                                        
    What is the purpose of Manual Budget Planning with Budget Control System
    Can anybody provide the link or document with configuration for above scenario
    Thanks
    Venkat
    Edited by: venkata raju khottari on Feb 14, 2009 2:52 PM

    Dear venkata raju khottari,
    Budget control is one part of Project System.  Normally we have two types of Budgets one Budget for CAPEX and Budget for Over Head expnes.  Max companies PS will take care by the Budgets.  If u need any information let me know.
    thanqu
    raj

  • Budget and budget control system

    what is the differnce between budget and budget control system. is it possible in sap each po (purchase order) wise budget.if its possible in sap please provide config steps.

    Hi, guy
    In SAP, we can use IO, PS, FM to make the budget. The budget control system is a sub-module of FM. If you want to get some config step, please kindly refer SAP Best Practises.

  • Budget Control System in SAP

    Hi,
    I want active Budgeting Control system in SAP. Please let me know how I can activate, from first step to last step. Please help me.
    Thanks & Regards,
    Hemant Maurya

    Hi,
    For activating Budgeting
    In OKKP activate the Order management active for the budgeting in orders
    Commitment mangement active for the commit manaement active.
    Activate which all the area you want budgeting,Ex Projects,Sales order,costing object.
    Define Budget profile in OKOB.
    IN KOAB maintain the assignmnet of budget profile to order types.
    IN KOAO activate the commit management check box against the order types.
    Define the tolerance limit for the budgeting.
    Maintain number range in OK11.
    Now create any internal order & assign budget in KO22 transaction,check the same.
    Regards,
    Raj.

  • 5s Volume control issues

    Anyone having volume control issues?  My wife's 5s (less than a month old) is having issues with the up volume.  If she mutes it using the down volume, it won't go back up.  I can get it to work if I hold the volume a long time and it eventually comes back.  Or last time i had to remove her case, hold the volume and release several times before it finally kicked in.  Any thoughts or ideas?  Thanks.

    Hi,
    Please test in other computer to see if the issue persists, it may be caused by the bad output channel.
    But for better solution, I recommend you go to MSDN forum for further help.
    http://msdn.microsoft.com/en-US/
    Thanks for your understanding!
    Regards,
    Ada Liu
    TechNet Community Support

  • Budget controlling for PO using internal order

    Dear experts ,
    can anyone tell me the step by step procedure to have a budget controlling on PO based on budget ?
    Regards
    anis

    Dear Anis,
    Create Statistical IO and assign budget to them. Then at the PO enter A at the Account assignment or K and you enter the IO number.
    If you want the system to check for budget go to SPRO -> Controlling -> Internal Orders -> Budgeting and Availability Control you define Budget RPofile etc and at the selection 'Define Tolerance Limits for Availability Control' you define for you Company code how the system reacts during PO creation. You give tolerances to display messages if the budget is close to depletion etc
    Bare in mind that PO create commitments and when the invoices are posted the amount becomes actual. You can check report S_ALR_87013019.
    Hope it helps. Generally i have used it, it is very good solution and easy to implement.
    BR

  • SRM 7.0 for Public Sector integrated with FM (Budget Control System)

    Hello!
    I'm starting an implementation project of ERP 6.0 and SRM 7.0 for Public Sector.
    It would be necesary the integration not only SRM with ERP but with FM (Fund Management), with BCS (Budget Control System) specifically.
    Is it possible? has anyone experience on it?
    Thks so much in advance and best regards!
    Marcela.-

    Hi,
    Certainly... If you have FM implemented in your project, you will have to make integration with SRM.
    I did it some 3 years ago and it was quite problematic (a lot of notes were created by SAP on this matter, also as initiative from our project), but since then, I assume, it should not pose specific problems.
    Regards,
    Eli

  • Budgeting control system

    Hi Experts,
    We are using ECC6, but would like to know if there is an available transaction code or program in the system that can  provide for preventive budgeting control system where the accounts are validated on-line with the available balance
    Thanks.

    Hi Ajay,
    We are uploading the budget in 7KEX per GL account per profit / cost center
    Thanks.

Maybe you are looking for

  • F110 - Payments not picked up during first run

    I executed payment run value dated as at 26.02.07 some error had occured. At first I've created one ID(A) witth 66 payments.However, after I check the payments there were actually still invoices not paid for that day. Hence, I perform another run wit

  • Preformance in mapping

    can you give me the order for graphical,java,abap and xslt mappings in preformance point of view?

  • ITunes Store - information on TV and Movie files

    Is there anyway that one can find out the image size of the items in the iTunes store prior to purchasing them? I would like to now if this TV show or that Movie is of a good size (read 720) and even perhaps what the data rate was before I buy someth

  • OS X Lion Installer

    Hi, Any idea on how to download "LION" OSX for iMac? My iMac is only capable of updating until "LION" (not MOUNTAIN LION) and i'm currently on LEOPARD. Thank you

  • Setting PMF parameters with JCA

    Hi, I am trying to use Kodo with JCA (in Jboss 3.2/WebSphere 5), but I don't see how to communicate properties to the PMF. For instance, how do I tell it which database driver to use? How do I ask for non-transactional reads or set other options? I d