Component backfush at each confirmation

Hello All,
I am using CO12 transaction for time reporting and operation cinfirmations. The first operation has backflush indicator. Some times 2 operators( employees )  work on the same first operations and their time is reported in CO12 on separate lines with only one of them has the yield quantity and other line has a yield of 0.
SAP system is suggesting the material to be consumed for each line of activities to be confirmed . Is this a normal behavior and should the system suggest component consumtion even though the yield quantity is 0.
Thanks,

Vivek,
Thanks for your help. I chcked and recreated transaction. System posted 2 GI for 2 lines , One with yoild of 1 and other with yield of 0 .
Order     Operation    Yield      Activity
1002300 0100           1            .5
1002300 0100            0           2.5
It posted 2 document . I checked Goods movement tab and it did show 2 lines. The component to be backflushed in batch controlled .
Thanks

Similar Messages

  • Planned and actual consumption for each confirmation

    Dear All,
    There is a production order. it has two operations. i have made three confirmations of each operation for that order. now i want to see the planned and actual consumption for each confirmation. how is it possible.
    However i know that on order we can see planned and actual consumption but it is for total order but i want to see planned and actual consumption for each confirmation. Actually client wants that on 2nd confirmation what is planned consumption and what they consumed on actual. thanks

    Hi,
            In standard SAP this type of report not be there, but u can make it by using BOM,Confirmation table, & material document table.
    Use AFRU to get posted document no for confirmation & detail by joining it with MSEG by mblnr & MAZHR.
    now u get plan component qty by using mast & stpo if ur bom not changed in Production order , if in order component may be change then use afko & resb table & by comparing base qty or order qty & confirmation qty get plan component qty for confirmation.
    Thanks
    Rakesh

  • Can it be  a seperate cost component structure for each company code?

    Company Code No 1 Setting:
    Company Code XXXX with Chart of accounts X(Quantity + Value updation in material type)
    In the existing company code(XXXX) ,Cost component structure is defined as
    All company code---->All Plants----> All Costing Variants -
    >Cost component Structure AA
    Company Code No 2 Setting:
    Scenario:
    Now  I am creating a new company Code YYYY) which is  is allowed  for quantity updation  alone and  trying to create a product cost collector to carry out Production confirmation through Repetetive manufacturing (."Error = Cost object component split costed with Value of Zero"
    Can it be possible to have a seperate cost component structure for each company Code?
    Company Code YYYY with Chart of accounts Y which is different from Company code 1(Quantity  alone in material type)
    If possible ,Can anybody provide a procedure to do the configuration of Cost Component structure

    Hello,
    As I understand your question, All the thing which are releted to costing are done only at the controlling area level not at company code.
    As your req diffrent cost componenet for diffrent company code is depend up on how you define the controlling area.
    Hope it will clear you
    Regards
    Ravi

  • Using a different default component state within each page state

    I am using a custom component in multiple page states but would like to have a different default state (for the same custom component) within each page state.
    Is there anyway to use a different default component state within each page state .
    When I change the default state at a component level it seems to go across all my page states.  Any solutions?
    Thank you

    I guess I can just add that interaction for that component!
    I think my brain is just catching up

  • Rounding up component quantities during Production Confirmation

    Hello gurus. I have the following situation.
    I have a BOM for finished product "X" that contains a component "Y" and a box "Z". The box fits 16 of these pieces. So in the BOM I type a usage quantity of .062 for component "Z" (I'm limited to 3 decimals).
    Then I create a Production order for X for 32 pieces. The component overview correctly shows me requirements of 32 pieces of "Y" and 2 pieces of "Z".
    The problem is; when I confirm this order in CO11N; as long as I report 32 pieces, I get a required quantity of 2 pieces for "Z", but if I want to report a partial quantity of 23 pieces, then it tells me I only need 1 piece of "Z".
    I still need to use the 2 boxes but the system is rounding down to 1 piece. Only if I type 24 pieces or more, it puts it up to 2 pieces.
    Is there a way to make SAP always round UP these quantities. Instead or rounding down/up depending on the quantity?

    Hi Fernando,
    I had the same problem.
    If u keep the component quantity in fraction, the system will create more procurement proposal.
    We need to keep the base quantity of the BOM header more and avoid the fraction in component qty. This will increase your accuracy when high amount of quantity requirment.
    Anyway for the small amount system will do round off.
    By practically also for 23 quantities you need 2 Boxes. ( as you said   for 16 qtys one box).
    Regards
    Bala

  • Preventing additional component consumption after final confirm in PM Order

    Hi,
    I am trying to block the consumption of additional components after the final confirmation in a PM order, this is causing erroneous component consp. especially in orders with multiple operations.
    The user may choose a confirmed operation while recording a component, system gives an error but it does not prevent the recording of that component, I want the users to get an error and stop there in such a case.
    I hope I made myself clear, thanks in advance
    IW32 Screen: https://picasaweb.google.com/koray.tulumen/Paylasacaklarim#5707123654338971234

    OK once more I thought I should add screens to better tell what I was trying to ask, I could not do that with the old forum layout. Anyways, could I get that result (in the screens) thru customization. There have been other comments relying on Orders' user statuses but with multiple operations they are not usable, every operation is confirmed individually and order status does either let or deny material movements thru the whole order (all operations)
    Here are the screens, thanks again.

  • Component quantites change during confirmation

    Hi ,
    We are having make to stock scenario ,components are issued as per bom to production order ,but while confirmation of production order the issue quantities are changed manually ,due to this miss match in inventory quantities occur.
    How can we prevent quantity changes during confirmation of production order.
    Regards
    abhijeet

    Dear,
    You can use transaction SHD0 to create transaction variantvariant  for CO11N and hide Deletion button and make coponent quantity as out put only.
    Check this link,
    https://www.sdn.sap.com/irj/scn/wiki?path=/display/snippets/transactionVariant-AStepbyStepGuidefor+Creation
    Or you can use BADI for this also  WORKORDER_GOODSMVT, method GM_SCREEN_OKCODE_CHECK.
    Just activate the code:
    IF I_OKCODE = 'DELE'.
    C_ERROR_FLG = 'X'.
    ENDIF.
    Regards,
    R.Brahmankar

  • Issue in setting IBASE component of service confirmation item

    Hello Experts,
                   I am facing a problem while creating a service confirmation item with reference to Service order items.  I am using CRM_ORDER_MAINTAIN
    bapi.  Issue is in the Ibase component of the service confirmation items as it is always taking the Ibase component of Confirmation Header even though
    i am explicitly passing the Ibase component of service conf item of  with IT_SERVICE_OS parameter. I am making sure that i fill up MARKED_OBJECT correctly.
    in CRMD_ORDER  i can see the Ibase component of  header and item both but Header one is the marked as main reference object.
    Any idea why Component can not be set explicitly for for service confirmation item.

    To achieve the above, try the below fix:
    var buttonBar:ButtonBar = new ButtonBar();
    buttonBar.requireSelection = true;
    Hopefully this works for you . Cheers!!

  • Confirmation of activity on material GR (MIGO for PO)

    Hello Friends,
    For non stock items, I am generating material requirement in network with item category "N".  Based on my project requirement, I am putting requirement date for the material on "General Data" tab of component overview. I want my activity to be confirmed as and when I am making GR for this material.  Please assume that there is single component planned for each of the activity.
    Can anybody help me ? 
    Thanks and best regards
    Bharat Parikh

    Hi,
    As per std SAP activity confirmation is a manual activity.
    For this kind of scenario you need to go for development !!
    Regards
    Abhinay Gautam

  • How can I delete an old Development Component (DC)

    Hello,
    We've a sca-package with Java-WebDynpro Code and try to deploy it, but unfortunately the deployment doesn't work.
    Therefore we analysed the package and remarked, that two sda-components exist.
    An DevelopmentComponent with our current sources and an older DC, but nobody knows wherefrom the older DC comes.
    We wanted to delete this od component, but we can't delete it in any way.
    A) We tried to open the DTR as WebDav and try to delete the folder, but only the error message "Unable to delete ..." appears.
    It's only possible to delete the "ative"/"inactive"-folder, not the folder of the subtree.
    B) If we import the configuration of the track in our NWDS, and create a DC of it, the component isn't shown, so we also can't delete it in our NWDS.
    C) I didn't find a flag to delete it in the NWDI in the CBS, CMS or DTR-websiteu2026
    D) Following the link /people/daniel.wirbser/blog/2005/07/27/how-to-delete-development-components-in-netweaver-java-development-infrastructure-jdi it's not possible to do Step 2, because the action for the folder is disabled.
    This Dev component exists in each folder: dev/inactiv, cons/inactiv, dev/active und cons/active-Folder.
    (You can see it in the NWDS in Perspective "Development Configuration", but it also isn't possible to delete)
    I would be glad, if you have some more suggestions.
    Kind regards,
    Bettina

    Try below steps to remove the DC from DTR...This will asnswer your A point.
    1.Open the NWDs and go to DTR prespective.
    2.Select the DC that you want to delete->inactive->dcs->.dcref
    3.Delete .dcdef and then delete Sc folders
    4.Expland all the folders select the files and right click+delete.
    5.It will ask you to checkout the files before deleting.
    6.After click on delete check in the activity.
    7.Finally go to DTR workspace(http://,hostname>:port/dtr and delete the entire folder strucutre.
    8.Go to NWDS ->DTR prespective,Delete all individual files uder src folder by making an activity.
    9.After check in all the files will be deleted
    10.Go to DTR workspace remove the DC folder.
    Delete DTR workspace folder:SapNote:855537
    After removing the Dc from DTR workspace,delete the deployable object from SDM also.
    We wanted to delete this od component, but we can't delete it in any way.
    For B point:
    Go to NWDS ->WD prespective-.rightclick on the project+delete include all.It will remove the sc from your local workspace.
    For C point:
    Deleting the DC from DTR will delete the content from DTR workspace.Nothing to do with CBS and CMS.
    For D option:
    Follw the steps from 1 to 10 which i have given for point A.
    Regards,
    Lavanya.G

  • TO confirmation for picking: difference between RF and non RF transactions

    Hello,
    I am confirming one TO for picking in a outbound delivery process. My storage location is WM and HU managed and materials are batch managed.
    I noticed if I confirm TO through RF transaction (LM61), I have the following results per material on outbound delivery:
    one main item with 0 as delivery quantity
    several sub items (9000x), with as many lines as HUs confirmed. Qty is HU qty
    Now if I confirmed TO with non RF transaction (LT12), I do not have the same results:
    one main item with 0 as delivery quantity
    one or several sub items (9000x), with as many lines as batch confirmed (then potentially less sub items). Qty is aggregated per batch with several HUs.
    I need to use TO confirmation through RF.
    But this seems to have an impact on an inter company process where I'm using SPED functionality.
    Indeed, when I process post goods issue in the issuing plant, I have an automatic creation of the inbound delivery for the receiving plant (with same HUs).
    And then I have to proceed QM controls:
    - if I have confirmed picking TO with RF, inspection lots are created for each HU.
    - if I have confirmed picking TO w/o RF, inspection lots are created for each batch
    I need to manage inspection lots per batch and confirm TO with RF!
    I changed several QM settings on material, without success.
    Now I would like to know if this could be much more managed on LE side, specifically TO confirmation.
    Have you got an idea?
    Thank you

    I got a feed back out of this forum.
    The solution is to change delivery update settings in interface between WM and shipping, so that update delivery is not done after each confirmation item but after the the whole TO confirmation.

  • Cost Component Structure (OKTZ) Issue - Max number of cost fields reached

    Hello.
    I'm having this issue in OKTZ when adding new cost component in an exisiting cost component structure. it says "maximum number of cost fields reached (40)".
    not sure what to do with this.
    please see screenshot
    http://img39.imageshack.us/img39/1700/oktz.jpg

    Hi Andrew,
    When yo create the Cost Components in the Cost Component Structure, inside each Cost Component, there will be properties relating to whether the Cost in that Cost Component is Fixed / Variable, relevant to Inventory Valuation or not etc.
    To view these options...Go to OKTZ, select the line of your Cost Component Structure, double click on "Cost Component with Attributes" in the left side navigation. Now, you will be able to see  the list Cost Components on right hand side. If you double click on any Cost Component, you will see the properties of that Cost Component.
    There, you can see ther radio buttons "Variable Costs" and "Fixed and Variable Costs".
    Now, in Standard SAP, you will be able to create a maximum 40 Cost Components. The behaviour of the system goes like this.... If one Cost Component is only "Variable Cost", it will take the space of one Cost Component out of the maximum 40. If  one Cost Component is of "Fixed and Variable Costs", then it will take the space of two Cost Components out of the maximum 40. That means, if all of your Cost Components are "Fixed and Variable", then you will be able to create only 20 Cost Components.
    You can find the SAP explanation regarding this in the IMG Documentation...
    SPROControllingProduct Cost ControllingProduct Cost PlanningBasic Settings for Material Costing--Define Cost Component Structure. Check the IMG Documentation there to find the following text...
    Structure of the Cost Components in a Cost Component Split
    The cost components are listed in a cost component structure that can contain up to 40 cost components (cost fields).
    You can create up to 40 cost components that contain variable costs.
    For cost components that contain full costs, the system creates a second cost field for the fixed costs. This means that you can create no more than 20 cost components that are full costs.
    Revert back for further explanation...
    Srikanth Munnaluri

  • Cost component with attributes restricted to 20/40

    Hello Gurus,
    The cost components have been restricted to 20/40 (SAP standard) either by combining more than one values or accommodating the CO-PA requirements within that number. Now, the requirement is to have more number of entries than the max limit of 20 each (fixed/variable), system is throwing following message - Maximum number of cost fields reached (40) (Message no. KQ304).
    Basic system design- The system is limited to 40 cost component fields. Each cost component can be set to variable or total (fixed and variable). However, the database has two fields: "total" and "fixed". "Variable" is derived. So if you set a cost component to "total" you, in effect, set up two fields (total and fixed) that need to be maintained. If you set a cost component to "variable" you, in effect, set up just one field (total) that needs to be maintained. So the basic limiting factor is that if you set every cost component to "total", you can only have 20 cost components.
    Because of this system limitation the only option left for us is to utilize 40 elements at the most without the internal split of fixed and variable portions. Now, the split is also necessary as such this workaround solution also can’t be implemented.
    Is there any additional way (user exit or some additional solution) which will allow overcoming this limitation and increasing the table entries by more than 20/40?
    Thanks & regards,
    Nikhil

    Dear Experts,
    Let currently I am facing the same issue.
    I need to increase the cost components to get the effective results in my COPA report.
    I tried to increase the Limit but I am also getting the same error.
    Maximum number of cost fields reached (40)
    Message no. KQ304
    Diagnosis
    The maximum number of cost fields defined in the system for saving the fixed and variable portions of the cost components has now been exceeded because of the new cost component.
    Regards,
    Jyosh

  • Difference between component controller & Custom controller

    Hi all
    what is the main difference b/w component controller , custom controller & interface controller.
    i want to know the difference of these three in the real time environment.
    if anybody explains me with any simple example then it is great help to me....
    Thanks
    Suresh babu.

    Hi Suresh,
    Component Controller and Custom Controller are more or less the same. Both are related to a particular component in the webdynpro application you create.
    Component Controller:-
    For each component of yours there will be a component controller, were in you can define context variables and methods, events etc.. This usefull while using models.
    Simple example where we can see this is, when you create global context variable in this controller and map this variable to the view controller context variable of different view, which enables you to pass the value of the variable from one view to another.
    Custome Controller:-
    They also have the same the function but as the name suggest there function can be customised. That is we can have more than one custom controller for a component. This is usefull when we need to create seperate execute methods for inputs from model import( Both webservice and rfc call).So you can seperate each other. Example is there in the more sample codes and application section.
    Interface Controller:
    There is only one interface controller for a component. It is mainly used when we need to communicate between two components.There is sample application for communication between two components in the sample codes and application section.
    Regards
    Sreedhar.

  • Custom Component Classes

    Hi all
    I have been learning flex for a few months now and absolutely
    loving it!
    But there is one thing I can't get my head round. I use to be
    a Flash user mostly which is probably why I am getting confused....
    I want to be able to make custom components that all use one
    custom class.
    For example, I have custom canvas components that are 'pages'
    which I am loading dynamically as and when needed. When they load I
    want them to fade in using the fade effect. Up until now I have
    written the code to do this on each component, which is quite
    annoying considering I have many pages.
    I would like a custom class with the code in it for the fade
    which every 'page' component uses, so each will fade in when
    loaded.
    I could this really easily using MovieClips in flash, but
    flex seems different. Maybe I am getting confused with regards
    Canvases and MovieClips.
    Please can someone help me? :)

    "gamedesign1000" <[email protected]> wrote
    in message
    news:gn17i4$eha$[email protected]..
    > Hi all
    >
    > I have been learning flex for a few months now and
    absolutely loving it!
    > But there is one thing I can't get my head round. I use
    to be a Flash user
    > mostly which is probably why I am getting confused....
    > I want to be able to make custom components that all use
    one custom class.
    > For example, I have custom canvas components that are
    'pages' which I am
    > loading dynamically as and when needed. When they load I
    want them to
    > fade in
    > using the fade effect. Up until now I have written the
    code to do this on
    > each
    > component, which is quite annoying considering I have
    many pages.
    > I would like a custom class with the code in it for the
    fade which every
    > 'page' component uses, so each will fade in when loaded.
    > I could this really easily using MovieClips in flash,
    but flex seems
    > different. Maybe I am getting confused with regards
    Canvases and
    > MovieClips.
    >
    > Please can someone help me? :)
    >
    >
    Why not just define the effect in the main file and then
    apply it from the
    outside, rather than locking your component into one effect:
    <yourNameSpace:YourCanvas width="200" height="200"
    creationCompleteEffect="{someEffectYouMade}" />

Maybe you are looking for

  • Text message time stamp while phone is off

    Does anyone know how to find out when a text message was actually sent by the person who sent it to you? I turn my phone off at night and sometimes for short periods during the day and when I turn it on I get several text messages at once.  However i

  • Disconnected device shows up in Airport utility

    I have several Airport Extreme and Time capsules connected to my network. One of my Airport Extreme devices seemed defective so I removed it from my network. It's unplugged, no power at all and no light showing. Yet when I open Airport Utility on my

  • Color coding in Address Book

    I am trying to rid myself of all Microsoft apps. I have switched from most of them to iWork. Everything except for Entourage. Does anyone know how I can color code (maybe there is a plug-in I can buy) my Address Book groups so they show up color-code

  • "Design" view as a separate panel for dual-display

    I just started using CS6 and was really hoping to see a new workflow enhancement for dual-display production with the "Design" view. I code all of my markup by hand in the code view. I would love to see the "Design" view in a separate panel that I co

  • RollOver handlers issue

    Hello, I have stumbled across the following problem. In flex i have defined (mxml or actionscript, doesnt matter) a group which contains a rectangle kind shape (Spark Path) and a few buttons which are all instances of a self made button component. No