Query regarding Preventive Maintenance

HI Experts,
I am suggesting to my client during Preventive Maintenance generation of notification instead of Order , because they donot suppose to capture any cost.
So I have ganerated Notification but issues are :
(1) I want to take print of all task/operations, which are suppose to be copied in order , but here i have no created order , so how can I get those task/Operations from task list in my notification. any exit ???? or  other solution.
Regards,
Gaurav
09987797985

hi gaurav
try following user exits
QQMA0008 QM/PM/SM: User Subscreen for Additional Data on Notif. Item
QQMA0009 QM: Predefine QM Order Parameters
QQMA0010 QM/PM/SM: User Subscreen for Additional Data on Cause
QQMA0011 QM/PM/SM: User Subscreen for Additional Data on Task
QQMA0012 QM/PM/SM: User Subscreen for Additional Data on Activity
This will definetly work
Regards
Sujit

Similar Messages

  • Query Regarding Fetching of Maintenance View

    Hi Experts
    I have one query regarding fetching of Maintenance View.
    My Maintenance View is consisting of only one table.
    so i am unable to fetch the data using inner join.i also found
    one FM VIEW_GET_DATA  which fetches entire table with out
    any condition it may lead to performance issue. kindly suggest
    how do i fetch the data from such Maintenance View.
    Thanks
    Nishita G

    Hi,
    You can Direct Use the DML operations on the Underlying Database Table.( example 'SELECT' Statement and use 'WHERE' Condition for required output ).
    Regards
    Pavan Kumar

  • Table for Preventive Maintenance Generated Maintenance Orders for Equipment

    Dear All,
                   I want to Extract no of Preventive Maintenance Orders (PM02) for a month (according to Planned Date)  for a set of Equipments.
                   Which table I should refer so i wll get the Orders with specific order type , for specific equipments for a month ( Date Range).
    With best regards,
    Narendra

    for that use the following tables for report generation:
    AFIH : for equipment number selection and order numbers
    AUFK: For order dates and other data
    T003P: for order type.
    In a single you will not get all the answers. You have to join three four table for this. try using these tables. Or also you can create a query for this using SQ01.

  • Triggering of Preventive Maintenance based on Measuring Point

    Hi,
    I have set measuring point & defined upper range limit and lower range limit. Now I want to trigger preventive maintenance, based on reading enter against measuring point specifically if measuring point reading is above or below defined upper range limit or lower range limit.
    Letu2019s say example, If 10 and 5 is upper range limit and lower range limit, now in this case creation of notification / main order if user has enter measuring point value more than 10 or less than 5.
    Regards,
    Dipen Shroff

    Hi,
        You can do it via Condition Based Maintenance ..
    IMRC0001- U can use this User exit
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/a7/fa4c988f6611d29e8a0000e8323350/frameset.htm
    regards
    pushpa

  • User exit IPRM0002 for preventive maintenance

    user exit IPRM0002 for preventive maintenance
    has anyone used this user exit? or BADI: BAdI: IPRM_MCP_SCHE_CHANGE  ?
    I seem to have some difficulty in knowing how to use these....
    I need to basically be able to influence a calling date for next PMorder to be opened but documentation is not explanatory and, even if I do know what these exit/badi are used for, i do not understand how to use the parameters provided.
    can anyone help?

    Hi,
      I dont think you would be able to test the exit if you dont implement them for the user exits simply passing the parameters wont help,actually there is a process of implementing a USER-EXIT i suppose u would already be familiar to it, I order to activate the exit you have to create a project in CMOD transaction and assign the enhancement to that and then also create the include that is avaliable inside the FM and there you would be able to put your code.
      For the BAPIs ,yes the control should go inside the BADI once you put a breakd point inside the right method but there to you need to implement the BADI and then you can put your code in the method for the effects to take place and you can test.
    The detail process of implementation are already avaliable on SCN, It seems that you dont have developer authorizations so i would suggest to take help from some one who has, Best of Luck:).
    Regards,
    Himanshu

  • Doubt in Scheduling of performance based preventive maintenance

    Dear Experts ,
                                            This is with respect to scheduling of performance based preventive maintenance.
    I will put my doubt in example so that it will be easy for you to understand.
    I want to perform a preventive maintenance for every 100 litres of fuel consumption.
    annual estimate is 7200 litres , that means 5 litres a day.
    so as per plan , for every day 5 days , maintenance needs to be performed.
    same will be appear after scheduling in ip10 also.
    While updating in the measuring document , I know that , if 100 litres is updated before due date , then order will be generated in the current date itself.
    I just want to know how system responds , if 100 litres consumption takes more than 5 days , will the system generates order as per schedule date or will it wait to complete for 100 litres consumption ??
    Regards
    Keerthan Kumar

    Greetings Keerthan,
    That depends on:
    1) The frequency that you input Measurement Documents in
    2) Your Call Horizon on the Maintenance Plans
    3) Your Scheduling Period in your IP30 Deadline Monitoring variant
    Generally, SAP will adjust the schedule based on the Measurement Documents entered for the counter (1) to account for readings (usage) which are higher or lower than estimated.However, it will NOT reschedule any Orders already called. So to make sure the dates are usually adjusted to your usage, you want frequently input MDs, a high Call Horizon and a short Scheduling Period.
    SAP will determine a scheduled due date for the Order based on the Annual Estimate and the readings. So, if the due date is in 5 days and you are on a call horizon of 100% and a Scheduling period of 3 days, for example:
    a) if you do not input Measurement Documents from Day 0 onwards, the Order will be generated due for Day 5 when you run the IP30 on Day 2
    b) if you input a Measuring Document on Day 1 indicating that less than estimated or no fuel was used, the due date and call date may be pushed into the future and the Order will be generated after Day 2.
    c) if you input the MD after Day 2, this Order will already have been called and will not be rescheduled, but subsequent calls might.

  • Changing basic finish date in Preventive maintenance orders

    Hi Experts,
    My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
    Thanks in advance.
    best regards,
    Srinivas M

    Hi Praveen,
    I have done all setting and tested but there is no change.
    My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
    The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
    best regards,
    -Srinivas

  • How to change duration of Preventive Maintenance cylce in strategy plan?

    Hi,
    How one can change duration of Preventive Maintenance cylce in strategy plan?
    e.g. In IP11 we set Preventive Maintenance schedule as monthly and we want to change it as quarterly i.e. every 3 months from starting date.
    With Best Regards,
    Rajkumar

    Hi Mr Ramesh
    Thanks for reply .
    Kindly guide us about as what steps /Tcode need to be used to perform the following actions as suggested by you :
    a) Delete orders.
    b) Go to IP10 and Do a 'manual call' by entering the planned date to create orders for the deleted packages.
    Or
    Reschedule the Whole Maintance plan by entering appropriate dates.
    c) Also please clarify , that how the new Orders will get generated against the Deleted Orders .
    With Thanks and Rgds
    Sonia

  • Operations in Preventive maintenance order has to release then only order has to TECO

    Hi,Friends
    is there any standard in R/3 that as soon as i am not releasing Operations in Preventive maintenance order, order should not be TECO
    when ever i have released Operations then only Preventive Maint order has to be TECO
    Your response is highly appriciated
    Regards,
    Kumar

    Kumar,
    I'm still confused...
    When you release the order header (REL), then all operations are also set to released (REL). You cannot individually release operations using the system status.
    However, you can set user statuses for each operation which are configured in the IMG.
    Please give more details.
    PeteA

  • Preventive maintenance for equipments installed in plant area

    Dear experts,
    I want to implement Preventive maintenance for equipments installed in plant area.
    Requirement is that i should be able to create a maintenance plan & schedul it as per the due dates. Maintenance order should get created. This order can be linked to the service contract item for which service entry sheet is created & released.
    I want a control on service entry sheet creation if the order is not settled or the related inspection lot which is generated is not confirmed.
    Please give advice ,how to proceed.
    Regards
    Vivek Deshpande

    Hi Vivek,
    Not sure on clearly what u need .. but have a look at some of the plans and examples of their usage for better idea ..
    1. Types : Time Based or Performance Based
    2. Single Cycle Plan [Time Based] : Ex u2013 Maintenance of a Vehicle every 03 months
    3.Single Cycle Plan [Performance Based] :Ex- Maintenance of a Vehicle every                                1000KM .
    4.Strategy Cycle Plan [Time Based] : Ex- Maintenance of a Vehicle every 03                                            months, 06 months etc.
    5.Strategy Cycle Plan [Performance Based Plans] : Ex u2013Maintenance of Vehicle                                                                          every 1000km , 2000km etc.
    6.Multiple Cycle Plan with single cycle set [Time or Performance Based] : Ex u2013                                                    Maintenance of a vehicle every 3months or                                  500km
    7.Multiple Cycle Plan with Multiple Cycle Sets [Time of Performance Based] : Ex- Maintenance of a Vehicle every 3months or 500km and 6months or 1000km
    8. The above given are explained with callobject as Maintenance Order. For getting inspection Lot then you can use order type PM05 calibration order in your Maintenance Plan and MO gets created as per the plan cycle and inspection lot gets created once u release the MO ..
    9. If you want MP related to service items then create MP with service procurement as Maintenance plan category in IP41 .. for remaining you can put MO as Maintenance plan category  .. for details refer to SAP Help ..
    regards
    pushpa

  • Preventive maintenance order header description

    Hi all,
    Preventive maintenance order (from Plans) header description is showing the task list title instead of Plan title.
    normally Plan header or item header short text will be the order header short text, what is the reason for this
    kind of problem.
    Pl give your suggestions
    Thanks

    Hi!
    I have checked by creating a maintenance plan with item and task list. I t is taking maintenance item header text in maintenance order. Would you please elaborate. If any user exit or any enhancement has beed done with this acivity?
    Regards,
    Vaibhav

  • Preventive maintenance order actual completion time and date

    Hey gurus,
    In preventive maintenance order the basic and scheduled start dates are picked from the maintenance plan. Now the actual start and end dates are in display mode. My client wants an overall completion time and date of the preventive order and not of individual operations. Also at the end of the month they want to see the total time spent on preventive maintenance. Can you suggest any way to sort out the above problem.
    Regards,
    Abhishek

    hi.
    the basic start date and end date is coming from maintenance plan. but you can change that dates according to your requirment. For that you have to remove the automatic schduling check in the dates header in maintenance order. Afetr that you can put basic start and end dates as per your requirement.
    Also the actual start and end dates and coming when you confirm the operation.
    When you confirm the first operation, that date the system will take as actual start date and the day you confirm you last operation or fully confirmed the order will be taken as actual end date.
    So i dont think yu have any problem. You can take basic start or basic end dates for this and change the dates as per your maintenace requirments.

  • Restrict the Preventive Maintenance Order creation through IW31 for few users.

    Dear Guru's,
    Good Day.
    My client requirement is he wants to restrict the Preventive Maintenance Orders through Transaction IW31 for few users. Is it possible through authorization? Please do the needful.
    Regards,
    Bhanu.

    possible for order type.
    create a role with all order types (optional) including Prev. Maint Order type, obviously having T.code IW31. and create another similar role excluding Prev. Maint Order type.
    Assign earlier role to few users (want to give the permission of IW31 Prev.) and later role to all remaining users.
    Auth. Object: I_AUART, first test in sandbox or testing client.

  • PM & PP integration during preventive maintenance

    Dear Experts,
    Once maintenance dept . will schedule preventive maintenance plan for a machine for a year , is it possible to block production order or to show capacity load in CM29 on the maintenance date?? I have assigned PP work center in the equipment & also put system condiiton as zero in maintenance plan & also in task list. Frequency of the maintenance plan is 1 month.Request your help on this.Thanks in advance.
    rgds
    rajib

    Hi,
    Let clear one thing that  the Equipement is work center for the PP and for Plant maintenance it is equipment only.When creating order or plan some maintenance work on that equipement which workcenter for the PP. In PP module ther is standard functionality Capacity planning of work center in Routing when your maintenance work is going on that equipement then work center capacity get reduced due to your maintenace work which will reflect in PP capacity planning. according that reduced capacity planning production order release.there is no std functinality that you can intimate the PP that your work center is in maintenance not use it. it will reflect in capacity planning of PP routing.According that reduced capacity PP plan the production scheduling.and Production work will get adjusted or deayed according available capicity of PP work center.
    Regards,
    Rakesh

  • Workflow for Preventive Maintenance Job Approval

    I need a workflow for Preventive Maintenance Job Approval.
    Whenever a PM user issues for a Preventive Maintenance Job it should go for approval up to two level of authority.
    Can some one suggest some standard tasks or workflow template which will be useful for the purpose?
    Regards,
    Manas

    Hi Manas Santra,
    I dont think that there is a standard workflow is available for preventive maintanance.
    Thanks and Regards
    Balaji E.

Maybe you are looking for